36C25025Q0238 0002.pdf

PDF 440 KB Posted

Attached to
J047--Replace Degraded Piping in C-2099 583-25-518
Solicitation number
36C25025Q0238-1
Issued by

About this file

This document is an Amendment of Solicitation/Modification of Contract (Standard Form 30) for solicitation 36C25025Q0238, issued by the Department of Veterans Affairs Network Contracting Office (NCO) 10 in Cincinnati, OH. The amendment's primary purpose is to answer Request for Information (RFI) questions and provide attachments related to a project to replace degraded hot water piping in a mechanical chase within a VA facility.

Key details include that the project is classified as a Level III ICRA (Infection Control Risk Assessment) and requires asbestos abatement. The hot water shutdown and piping replacement is expected to be performed during a weekend, with contractors having access to a C-wing staff freight elevator. The new platform for accessing the pipes can be built off the existing platform, and the VA plumbing shop will refill the heating hot water system after pipe replacement. Mechanical press connections are not allowed per VA specification. The quote submission deadline remains March 25th, 2025, and the contract includes specific requirements for platform access, system testing, and adherence to asbestos abatement regulations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 3

0002 02-28-2025

583-25-3-650-0018

583-25-518

36C250

Department of Veterans Affairs Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati OH 45219

36C250

Department of Veterans Affairs Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati OH 45219

To all Offerors/Bidders

36C25025Q0238

X

X X

See CONTINUATION Page

583-3650162-650-854200-3223 23NRNR000

X 1

The purpose of this amendment is to answer submitted RFI questions (see page two)

See attachments (see page three) :

1-H8_HvacPlnBdlg1ScndFlrB - Replace Degraded Hot Water Piping 583-25-518 Replace Degraded Hot Water Piping - Combined Specifications 583-25-518 Replace Degraded Hot Water Piping - ICRA S

The due date for quotes remains March 25th, 2025.

Jeffery Hairston

RFI Questions and Answers

1. Please identify the ICRA classifications, and requirements for this project.

a. See attached signed ICRA form establishing this project as Level III. This project is also subject to all requirements for asbestos abatement according to local, state, and federal regulations per the specifications, also attached.

2. Can the contractor build off of the existing platform, or should the permanent access be completely separate from the existing platform.

a. The new platform can be erected off the existing platform so long as access to the existing platform and ladders are not impeded.

3. Are there any existing drawings of the pipe that is being replaced? As-Builts?

a. See attachment "1-H8_HvacPlnBdlg1ScndFlrB - Replace Degraded Hot

Water Piping" for the original drawing.

4. What size pipe is the riser line?

a. Refer to the original drawing attached that details the riser pipes as either 2" or 2-1/2" within the mechanical chase. The contractor should plan for either condition, but it should not be expected that original drawings are 100% accurate.

5. Will contractors have access to a freight elevator to get material to the project area?

a. Yes, contractors will have access to the C-wing staff freight elevator.

6. Please confirm that all work shall be completed during the weekend? Including the abatement and building of the temp or permanent access.

a. The hot water shutdown and piping replacement is expected to be performed on the weekend. The contractor will be able to set an infection control barrier and asbestos containment earlier in the week during normal work hours to complete platform erection and asbestos abatement before shutdown on a Saturday.

7. Please indicate where and the limits of the permanent platform shall be, or is the permanent platform for valve access only?

a. The permanent platform will be for valve access only. If the permanent platform bid option is selected, it is expected that the platform that is erected to perform this work will remain after the work is completed and require no alterations.

8. Please indicate if the contractor is responsible for flushing the hot water supply and return after new pipe is installed.

a. System flushing will not be required. The VA plumbing shop will refill the system with hot water after the pipe is replaced. This is heating hot water and is not potable.

9. Please indicate any required testing after the new pipe is installed.

a. Per the above, the VA will refill the system, but the contractor shall remain on site during this time to verify the installation is leak free and no additional issues are present in the installation.

10. Are there any specific tolerances or detailed specifications for the piping connections?

a. See attachment "583-25-518 Replace Degraded Hot Water Piping -

Combined Specifications" for the detailed construction specifications for this project. Note mechanical press connections are not allowed per VA specification.

Attachments:

1-H8_HvacPlnBdlg1ScndFlrB - Replace Degraded Hot Water Piping

583-25-518 Replace Degraded Hot Water Piping - Combined Specifications

583-25-518 Replace Degraded Hot Water Piping - ICRA S

File details come from the government source that posted it. Updated .