This document is a 2nd Set of Request for Information (RFI) Questions and Answers for a Department of Veterans Affairs project involving sewer system and water loop improvements. The RFI addresses several key technical and administrative details, including asbestos abatement (estimated 70 linear feet of 6-inch diameter pipe insulation), staffing requirements for project roles such as superintendent, Site Safety and Health Officer (SSHO), and Quality Assurance/Quality Control (QA/QC) personnel. Additional clarifications sought include confirmation about tax inclusion in proposals, wage determination details, and compliance with VA Technical Information Letter (TIL) guidelines.

Most answers in the document reference "previous RFI Questions/Answers", indicating this is part of an ongoing clarification process for solicitation 36C25025B0007. One substantive response confirms that the most current Wage Determination will be included in the contract award, suggesting potential wage rate flexibility. The project appears to be for the Veterans Health Administration's Veterans Integrated Service Network 10, with specific technical uncertainties being addressed through this iterative RFI process to provide potential bidders with comprehensive project information.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Improve Sewer System and Water Loop 610-21-104, newest first.
File Type Posted
36C25025B0007 0011.pdf PDF
Attachment - 321723.pdf PDF
Attachment - Updated DB WD.pdf PDF
Attachment - 331000.pdf PDF
Attachment - 329000.pdf PDF
Attachment - RFI Questions and Answers.docx DOCX document
36C25025B0007 0010.pdf PDF
36C25025B0007 0009.pdf PDF
Site Walk Sign-In Sheet - Improve Sewer System and Water Loop.pdf PDF
36C25025B0007 0008.pdf PDF
36C25025B0007 0007.pdf PDF
36C25025B0007 0006.pdf PDF
36C25025B0007 0005.pdf PDF
36C25025B0007 0004.pdf PDF
36C25025B0007 0003.pdf PDF
36C25025B0007 0002.pdf PDF
36C25025B0007 0001.pdf PDF
Attachment VIII - Specs.pdf PDF
Attachment V - Drawings set 4 of 6.pdf PDF
Attachment I - WD.pdf PDF
Attachment IX - Limitation on Subcontracting Cert.pdf PDF
Attachment VII - Drawings set 6 of 6.pdf PDF
Attachment IV - Drawings set 3 of 6.pdf PDF
Attachment X - EMR.docx DOCX document
Attachment II - Drawings set 1 of 6.pdf PDF
Attachment XI - RFI Form-36C25025B0007.docx DOCX document
Attachment VI - Drawings set 5 of 6.pdf PDF
Attachment III - Drawings set 2 of 6.pdf PDF
36C25025B0007.docx DOCX document
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2nd Set – RFI Questions and Answers

1. Regarding asbestos abatement: There is a spec section for asbestos abatement callout the following:

B. Extent of Work: 1. Removal, clean-up and disposal of asbestos containing materials (ACM) and asbestos/waste contaminated elements or debris in an appropriate regulated area for the following approximate quantities; Estimated

(70) linear feet of (6 inch) diameter pipe insulation.

Exact extent of work is unknown and needs to be field verified for underground piping and structures. Asbestos work will be on an as needed basis.

Please confirm for bidding purposes that the ONLY abatement we are to include is 70 LF of 6" diameter pipe insulation.

ANSWER: See previous RFI Questions/Answers

2. What material is the 2" waterline. I do not see a spec section or detail for this waterline.

3. Will the sign-in sheet from site visit be available in addendum?

4. Please clarify if a superintendent can be a dual hat to cover the requirements of

SSHO?

5. If no to the question above, will the SSHO need to be full-time for this project?

6. Please clarify if a superintendent can be a dual hat to cover the requirements of

QA/QC?

7. If no to the question above, will the QA/QC need to be full time for this project?

8. Can a superintendent be a triple hat to cover the requirements of SSHO and

QA/QC?

9. Please confirm if tax should be included in our proposal?

10. Please provide the latest wage determination for this project’s county.

ANSWER: See Attachment – Updated DB WD

11. Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation?

ANSWER: The most current Wage Determination will be included in the contract award.

12. Please confirm the current design documents meet current VA TIL guidelines

File details come from the government source that posted it. Updated .