This document is a solicitation (Solicitation Number: 36C25024Q0592) for custom cabinetry and millwork for the pharmacy areas at the Richard L. Roudebush VA Medical Center in Indianapolis, Indiana. The Department of Veterans Affairs is seeking proposals for modular casework, laminate tops, stainless steel counters with integrated sinks, project management, installation, and warranty services.

Key details include:

  • Proposals are due by 12PM ET on May 21, 2024
  • Vendors must provide detailed technical drawings, product specifications, project management plan, and pricing information
  • Evaluation criteria include technical capability, past performance, and price
  • The government will complete demolition and site preparation, and the vendor must coordinate phased manufacturing, delivery, and installation
  • All products must meet healthcare and pharmacy standards for materials, finishes, and functionality
  • The vendor must provide field measurements, submittals, and samples for government approval prior to production
  • Installation and warranty services are required.

View the file

Other files

File Type Posted
36C25024Q0592 0003.docx DOCX document
36C25024Q0592 0002_1.docx DOCX document
36C25024Q0592_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions with Answers

1. Given questions are not due until 10 June, will the 17 June proposal submission timeline be moved out at all?

a. RESPONSE: No the deadline to submit quotes will not be adjusted at this time.

2. Can the project drawings be shared so we can see phasing plans, ICRA barriers, wall layouts for power and data, etc. so that we can ensure no conflicts with contractor’s work.

a. RESPONSE: We don’t have drawings for something like this. Shops will install barriers per the direction of infection prevention. No changes will be made to power or data. VA scope is to remove existing items, do any wall repair/paint and potentially do flooring. Vendor will bring in casework to prepared place

3. What is the plan for power and data for equipment? Currently they are using surface mounted raceways to existing back panels on casework. VA elevations are not showing new equipment to have back panels. Does any of this need planned for in the casework? Current furniture has lots of rough-cut outs to access

a. RESPONSE: We would need to continue surface mounted raceways since the walls are cinder/concrete. Electricians have indicated historically this is the only option for those rooms. Emergency power will be needed for the fridge and Script Pro. There are also additional emergency power outlets in there for a total of 6. Existing power will not change. Layout needs to match existing to ensure that equipment can access the power. We are not going to supply a power plan.

4. Task lighting is being requested, where will the power be located for each elevation to power the lights? Are you looking for hardwired task lighting or plug in?

a. RESPONSE: Task lighting – plug in is preferred. Maximize lighting for workspace and under cabinet if this maximizes lighting. May not be feasible for plug.

5. Can the contractor’s timeline be shared so we have a better understanding of phasing order and timing to coincide with the phasing and understanding entire project durations start to finish.

a. RESPONSE: Timeline will be set during kickoff and a full project timeline will be created in conjunction with VA shops completing prep of areas.

6. Can you share the VA Interior design drawings with us, they are small and blurry in the solicitation. We would like to be able to read all comments and dimensions clearly. PDF and or CAD is preferable.

a. RESPONSE: See Pages following questions with responses to this amendment.

7. Can you please clarify what your requesting pricing on for item C. 7th floor vault outside A7086J. The solicitation drawings reference the small 2’ wide piece of casework inside the vault but site visit discussion was that it needed to be the elevation outside of the vault, a 6’ in length elevation.

a. RESPONSE: It is the area inside the vault.

8. Solicitation says to begin taking order June 2024. Assuming this is no longer accurate, when is the first phase expected to be onsite?

a. RESPONSE: Date will be late summer

9. Solicitation requests line-item pricing for current furniture removal. Would that plan be to remove the existing equipment, leave the site, wait for GC’s work to complete, then return to install that space/phase?

a. RESPONSE: No removal is needed – only install of casework, etc.

10. Demo is to include waste removal; will vendor be provided space onsite to drop a waste dumpster? And if so, where will this location be? Can this dumpster remain for the entirety of the project, or must it be pulled/removed for every phase?

a. RESPONSE: If vendor desires to bring dumpster, VA will provide a location depending on size, dates, etc.

Questions with Answers

11. Solicitation states that vendor should allow for 3 revisions per line item, will the vendor be able to adjust pricing after each revision?

a. RESPONSE: No, there will be no allotment for price adjustments. This designation is being changed effective immediately with this amendment posting to no more than 1

12. Which loading docks will the vendor be directed to use? Will this be the same or different for each phase/space being delivered. Example when delivering to phases in the 7th floor compounding pharmacy will the vendor use the same dock and delivering route when delivering to the main outpatient pharmacy on 2nd floor? Can the VA provide a delivery route drawing from dock to elevators to pharmacy entrances for each 2nd and 7th floor pharmacy.

a. RESPONSE:

i. First floor installs: the west dock will be utilized. Basement hallway to the C- wing elevators and to the outpatient pharmacy areas

ii. Seventh floor installs, the Engineering/East dock will be used. Basement hallway past Engineering to the A-wing service elevators will be used

13. What is the delivery truck maximum length to delivery at the loading dock(s)?

a. RESPONSE:

i. The West dock can accommodate a 53’ trailer.

ii. The Engineering/East dock accommodates a shorter trailer or a box truck.

14. Is the VA requiring flooring protection for the entirety of the delivery route?

a. RESPONSE: No, vendor must take proper care to avoid damage during delivery.

15. Does this route have barrier to entry at access door needing badging to move through?

a. RESPONSE: VA staff will provide entry into the Pharmacy areas. All other areas do not need badging access.

2'

9'-82" A A-7087

1'-2"

2'-1" 11'-51"

FLOOR PLAN

SCALE: 1 " = 1' - 0"

REFER TO MTR ITEMS MM1

NOTE AND ADDITIONAL SPECIFICATION " THICK SOLID SURFACE MATERIAL

1. 3" RADIUS FROM OUTSIDE CORNERS OF SOLID SURFACE

COUNTERTOPS

2. 1" STANDARD COUNTERTOP OVERHANG FOR BASE

CABINETS

3. SINK SHOWN IS A REPRESENTATION ONLY

4. VERIFY ALL DIMENSIONS ON SITE PRIOR TO FINAL DRAWING PRODUCTION AND FABRICATION.

PHYSICALLY TEMPLATE THE AREAS WHERE DIMENSIONS ALONE MAY NOT BE SUFFICIENT.

B

CONSIDER EXISTING BEAM HEIGHT

WASTE BIN RECEPTACLE

9'-81"

ELEVATION A

1'-17"

CONSIDER EXISTING BEAM DIMENSION

MOVABLE SHELVES 1'-6"

3'

3"

SECTION B

1'-6"

9'

1'-6"

11"

6'

SCALE : 3/16" = 1' 0"

REV : REV : REV: REV:

A-7087 PHARMACY
BREAKROOMOPTION A
INTERIOR DESIGN - ENGINEERING DEPARTMENT

RICHARD L. ROUDEBUSH VETERANS' ADMINISTRATION CENTER 1481 W. 10TH ST INDIANAPOLIS, INDIANA, 46202

MAIN PHONE : (317) 554 0000

DRAWN BY : CMM

1'-111"

A

7'-43"

1. 3" RADIUS FROM OUTSIDE CORNERS OF SOLID SURFACE

COUNTERTOPS

2. 1" STANDARD COUNTERTOP OVERHANG FOR BASE

CABINETS

3. SINK SHOWN IS A REPRESENTATION ONLY

4. VERIFY ALL DIMENSIONS ON SITE PRIOR TO FINAL DRAWING PRODUCTION AND FABRICATION.

ADJUSTABLE SHELVING

Sink

7'-43"

ELEVATION A

2'-01"

2'-6"

OPEN AREA

Stainless Steel Counter Top

4"

3'-4"

41"

5'-31"

A-7086 PHARMACY

NON-STERILE DISPENSING AREA

INTERIOR DESIGN - ENGINEERING DEPARTMENT

DRAWN BY : CMM

6'-01"

3'-6"

REFRIGERATOR STORAGE EQUIPMENT

2' 2'

REFRIGERATOR

2' A COMPUTER

1. 3" RADIUS FROM OUTSIDE CORNERS OF SOLID SURFACE

COUNTERTOPS

2. 1" STANDARD COUNTERTOP OVERHANG FOR BASE

CABINETS

3. SINK SHOWN IS A REPRESENTATION ONLY

4. VERIFY ALL DIMENSIONS ON SITE PRIOR TO FINAL DRAWING PRODUCTION AND FABRICATION.

Solid Surface Counter Top

MOVABLE SHELVING

9'

A-7086J PHARMACY NARCOTICS ROOM
INTERIOR DESIGN - ENGINEERING DEPARTMENT

DRAWN BY : CMM

B C

13'-31"4

A

8' 2'-6" 2'-6"

TASK LIGHT

NOTE AND ADDITIONAL SPECIFICATION

" THICK SOLID SURFACE MATERIAL

1. 3" RADIUS FROM OUTSIDE CORNERS OF SOLID SURFACE COUNTERTOPS8

2. 1" STANDARD COUNTERTOP OVERHANG FOR BASE CABINETS2

DRAWER DRAWER

DRAWER

1'-10" 4' 8'

1'-10" 4'

4" 4" 8" 2'-8" 3'-4" 8"

8"

41"2

3.

SINK SHOWN IS A REPRESENTATION ONLY
4.VERIFY ALL DIMENSIONS ON SITE PRIOR TO FINAL DRAWING PRODUCTION AND FABRICATION.

PHYSICALLY TEMPLATE THE

SCALE: 1 " = 1' - 0"4

AREAS WHERE DIMENSIONS ALONE MAY NOT BE SUFFICIENT.

1'-6" 3' 3' 3' 3'

3' 3' 3'

3' 1'-6"

2' 2'

TASK LIGHT TASK LIGHT TASK LIGHT

4"

8" 2'-8" 3'-4" 8"

8" 3'-4" 2'-8"

2' 2'-6"

13'-101"2

11"

41"2

41"2

11"2

13'-101"2

2'-6" 2'

SECTION C

REV :

REV :

REV:

REV:

DRAWN BY : CMM

A-1061A PHARMACY VAULT

INTERIOR DESIGN - ENGINEERING DEPARTMENT

2' 7'-1"

2'C-1069

EQUIPMENT B

D

EXISTING WORKSTATION ISLAND

EQUIPMENT A

11'-9" B C

5' 2'-6"

2' 2'

2' 9'-6" 6'-7"

18'-1"

A SCALE: 3/16" = 1' - 0"

2'-6" 5'

EQUIPMENT A EQUIPMENT B

SCALE: 3/16" = 1' - 0"

6'-7"

1'-8 7 "16

6"

ADJUSTABLE SHELVES

8"

2' 2'-4"

2' 2'-4"

2'-4"

ELEVATION B

2' 2'

2' 2'

6 LAYERS FIXED SHELVING

7'

1'-51"2

2' 2'

ELEVATION D

2' 1'-8" 2'

1'-8 7 "16

8"

ELEVATION C

C-1069 PHARMACY NARCOTICS VAULT
INTERIOR DESIGN - ENGINEERING DEPARTMENT

DRAWN BY : CMM

2'-10" 3'-6" 3'-6" 4'

C-1061 COMPOUNDING

1'-3"

AREA 2'

B TASK LIGHT TASK LIGHT TASK LIGHT

2'-3" 1'-6" Stainless Steel Counter Top Sink

4" WASTE BIN FIXED

RECEPTACLE

3'-4" 2'-8" 8"

8"

41"

2'-4" 2' 2' 1'-6" 2' 2' 2'

FLOOR PLANELEVATION A
SCALE: 3/16" = 1' - 0"SCALE: 1 " = 1' - 0"

NOTE AND ADDITIONAL SPECIFICATION

1'-17"

" THICK SOLID SURFACE MATERIAL

1. 3" RADIUS FROM OUTSIDE CORNERS OF SOLID SURFACE

COUNTERTOPS

2. 1" STANDARD COUNTERTOP OVERHANG FOR BASE

CABINETS

3. SINK SHOWN IS A REPRESENTATION ONLY

4. VERIFY ALL DIMENSIONS ON SITE PRIOR TO FINAL DRAWING PRODUCTION AND FABRICATION.

3'-4"

PHYSICALLY TEMPLATE THE AREAS WHERE DIMENSIONS

ALONE MAY NOT BE SUFFICIENT.

2'

SECTION B

C-1061 PHARMACY

COMPOUNDING AREA

INTERIOR DESIGN - ENGINEERING DEPARTMENT

DRAWN BY : CMM

image6.png image7.jpeg image8.png image9.png image10.png image11.png image12.png image13.png image14.png image15.png image16.jpeg image17.png image18.png image19.png image20.png image21.png image22.png image23.png image24.png image25.png image26.png image27.png image28.png image29.png image30.png image1.png image2.png image3.png image4.png image5.png