36C25023B0055 0001.docx
DOCX document 18 KB Posted
- Attached to
- Z2DA--Project No. 539-23-203 - Upgrade Elevators Federal contract opportunity
- Solicitation number
- 36C25023B0055
About this file
This document contains an amendment to a solicitation for an upgrade elevator project at a Veterans Affairs medical center. The amendment provides answers to questions from prospective offerors to clarify the project scope. The project involves upgrading elevators at the specified location, but does not require any additional work on pneumatic tube systems or elevator repairs mentioned in the background, as those items have been addressed under separate projects. The superintendent may serve as both the superintendent and safety and health officer for the project. Flooring removal work refers only to resilient flooring and adhesive, not asbestos-containing materials. The bid opening date is unchanged. Offerors must acknowledge receipt of the amendment by the specified date and time to have their bids considered.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25023B0055 0002.docx | DOCX document | |
| Attachment IV - Limitations on Subcontracting.pdf | ||
| Attachment lll - RFI Attachment.docx | DOCX document | |
| Attachment l - DBA WD.pdf | ||
| vha directive 1192.01.pdf | ||
| Attachment II - EMR Attachment.docx | DOCX document | |
| 36C25023B0055_1.docx | DOCX document | |
| 22-119 BD Specs_.pdf | ||
| 22-119 BD Dwgs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 539-23-2-6905-0042 539-23-203 36C250 Department of Veterans Affairs Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati
OH
45219 36C250 Department of Veterans Affairs Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati
OH
45219 To all Offerors/Bidders
36C25023B0055 06-09-2023
X X X
539-3630162-6905-854200-3223 23NRNR000
This amendment is being posted to provide information and answers to questions received. That information begins on page two. The information to call into the bid opening is at the end of this amendment. There is no change to the bid opening date.
Luke Turner
CONTINUATION PAGE
Questions and Answers
· Spec section 01 35 26 states that the SSHO is to be separate from the project superintendent. On this type and size of project, is a separate SSHO necessary?
· It is authorized that the Superintendent can also be the SSHO.
· In Box 10 of the solicitation, last paragraph, line 2, "the project will also make repairs the elevator in the ED". Can you please clarify what is meant by this statement? Are there specific repairs to the elevators that need to be included in this bid?
· The repairs mentioned were completed under a separate project. No work outside what is outlined in the specs and drawings is expected of the contractor.
· In Box 10 of the solicitation, last paragraph line 2 & 3, it reads "It will also upgrade the pneumatic tube system as needed to include the diverters and blower which can no longer be supported with their current parts and is approaching the end of its life." There is no mention of pneumatic tube systems in the provided drawings or specifications. Can you please clarify what is being asked of the contractor in this statement?
· Similar to answer above. The pneumatic tube system is no longer in the scope of the project to “Upgrade Elevators.”
· Section 09 65 19 - 3.2C refers contractors to section 02 82 13.19, Asbestos Floor Tile and Mastic Abatement of the specification for removal of flooring and adhesive containing asbestos. This section is not included in the specifications. Please provide.
· Spec Section 09 65 19 – 3.2 should only have one (1) bullet point stating: “1. Remove existing resilient floor and existing adhesive.” Any reference to asbestos can be removed. The specs have been updated accordingly.
File details come from the government source that posted it. Updated .