This presolicitation notice is for a construction project to resurface and re-stripe the parking lot at the Fort Thomas Division of the Cincinnati VA Medical Center located in Fort Thomas, Kentucky. The project includes repairing, resurfacing, and re-striping the existing parking lot and adjacent sidewalk areas in four phases to minimize disruption. Phase 1 involves small site repairs, Phase 2 focuses on resurfacing the main entrance, Phase 3 addresses the northern parking lot portion, and Phase 4 covers the southern parking lot portion. The period of performance is 90 calendar days from notice to proceed. The Department of Veterans Affairs seeks bids due by May 5, 2023. The government intends to award a contract to complete the full scope of work but may use deductive alternatives if funding is insufficient.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Presolicitation Notice Presolicitation Notice

SUBJECT*
Resurface and Stripe Parking Lot at Fort Thomas, KY. Project #539-23-201

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
45409-1337
SOLICITATION NUMBER*
36C25023B0046
RESPONSE DATE/TIME/ZONE
05-05-2023 12:00pm EASTERN TIME, NEW YORK, USA
ARCHIVE
15 DAYS AFTER THE RESPONSE DATE
SET-ASIDE
SDVOSBC
PRODUCT SERVICE CODE*
Z2LZ
NAICS CODE*
236220
PLACE OF PERFORMANCE
Fort Thomas

Cincinnati VAMC

1000 S. Fort Thomas Ave.

Fort Thomas KY

POSTAL CODE
41075
COUNTRY
USA

CONTACT INFORMATION

CONTRACTING OFFICE ADDRESS
Network Contracting Office (NCO) 10

Department of Veterans Affairs

3140 Governor’s Place Blvd. Suite 210 Kettering OH 45409-1337

POINT OF CONTACT*

Contract Specialist Brian Rosciszewski Brian.Rosciszewski@VA.gov 937-268-6511 x 4421

Inquiries by email only, please.

ADDITIONAL INFORMATION

AGENCY’S URL
https://www.cfm.va.gov/til/
URL DESCRIPTION
VA Technical Info. Library

AGENCY CONTACT’S EMAIL ADDRESS

EMAIL DESCRIPTION

DESCRIPTION

STATEMENT OF WORK (SOW)

Fort Thomas Division (Cincinnati VAMC) 1000 S. Ft Thomas Ave Ft Thomas, Kentucky 41075

1. Contract Title. Project # 539-23-201 “Resurface and Stripe Parking Lot at Fort Thomas, Kentucky.”

2. Background. The chosen contractor shall provide complete construction services including labor, materials, equipment, and supervision required to complete Project# 539-23-201 “Resurface and Stripe Parking Lot at Fort Thomas, Kentucky” for the Cincinnati VAMC. This project will consist of repairing, resurfacing, and re-striping the existing Fort Thomas, Kentucky parking lot and adjacent sidewalk areas while adhering to the appropriate design guide requirements. Fulfillment of this project will further enhance a professional appearance, curb appeal, visibility of parking lines and improve the maneuverability and safety for the veteran patients and employees at the Fort Thomas facility.

3. Place of Performance. The project work will occur at the Fort Thomas Division, 1000 S. Ft Thomas Ave, Ft Thomas, Kentucky 41075 specifically within the existing on-site parking lot location.

4. Scope. The “Resurface and Stripe Parking Lot at Fort Thomas” project will include, but is not limited to, various repairs, milling, removal/replacement and crack filling of the existing parking lot, adjacent curbs & sidewalk areas at the Fort Thomas location of the Cincinnati VAMC. This work is divided into the following four (4) phases:

Phase 1 – Site Repairs Phase 2 – Entrance Resurfacing Phase 3 – North Parking Resurfacing Phase 4 – South Parking Resurfacing.

This construction project requires general contracting, demolition of existing conditions and safety and security for successful completion.

5. Specific Tasks. A general summary of tasks involved with this project are listed below by phase as currently documented in the project drawings & specifications. The intent of this phasing is to minimize impact on patients and employees throughout the course of this project. For a full and complete understanding of all required work to be completed under this project, carefully read through all aspects of the project drawings and specifications.

Note 1: Contractor to field verify measurements and quantities of all items needed to complete this project. Utilize drawing plans as guides for planning and striping parking lot once repairs & resurfacing have been completed.

Note 2: Any requirements listed in the project solicitation documentation that are unclear to the contractor or requires further clarification are to be documented and submitted via Request for Information (RFI) to be formally answered by the project’s CO/COR.

A. Phase 1 – Site Repairs: This phase will include small site repairs including curb ramp reconstruction, concrete sidewalk milling, concrete sidewalk removal & replacement, concrete pavement removal & replacement, and concrete sidewalk milling/crack filling. Work shall be performed in such a manner to minimize disruption to the VA patients and employees. Patient and employee access to the building shall be maintained at all times. Contractor to provide detour signage around road or sidewalk closures. This phase may not be construction concurrently with any other phase.

B. Phase 2 – Entrance Resurfacing. This phase will include the resurfacing and repairs to the main entrance drop off and access roadways. Work shall be performed in such a manner to minimize disruption to the VA patients and employees. Patient and employee access to the building shall be maintained at all times. Contractor to provide detour signage around road closures. This phase may not be constructed concurrently with Phases 3 or 4.

C. Phase 3 – North Parking Resurfacing. This phase will include the resurfacing and repairs of the northern portion of the onsite parking lot. Work shall be performed in such a manner to minimize disruption to the VA patients and employees. Patient and employee access to the building shall be maintained at all times. Contractor to provide detour signage around road closures. This phase may not be constructed concurrently with Phases 2 or 4.

D. Phase 4 – South Parking Resurfacing. This phase will include the resurfacing and repairs of the southern portion of the onsite parking lot. Work shall be performed in such a manner to minimize disruption to the VA patients and employees. Patient and employee access to the building shall be maintained at all times. Contractor to provide detour signage around road closures and provide a dedicated pedestrian detour. This phase may not be constructed concurrently with Phases 2 or 3.

E. Deducts. It is the intent of the VA to award a contract to complete the full scope of work as defined by the project drawings and specifications. However, if available funding is insufficient to match the construction bids received for the full project scope of work, the following items have been identified as deduct alternates as noted on the project drawings and specifications:

1. Deduct #1: Elimination of work related to select areas of sidewalk removal and replacement.

2. Deduct #2: Elimination of work related to the removal and replacement of accessible concrete curb ramps.

6. Performance Monitoring. Construction contract supervision will be conducted by the Project Section of Engineering Service at the Cincinnati VA Medical Center. Inspection will be made throughout the project and delivery and installation.

7. Security Requirements. None.

8. Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI). None.

9. Other Pertinent Information or Special Considerations

A. Identification of Possible Follow-on Work. None.
B. Identification of Potential Conflicts of Interest (COI). None.
C. Identification of Non-Disclosure Requirements. None.
D. Packaging, Packing and Shipping Instructions. None

E. Inspection and Acceptance Criteria. Project COR to conduct the final acceptance of satisfactory installation.

10. Period of Performance. Total Period of Performance: 90 calendar days from the effective date of the notice to proceed.

11. Technical/Administrative Requirements. Contracted work shall be conducted in accordance with the below VA Specifications.

A. Support features for each room can be found within U.S. Department of Veterans Affairs Office of Construction & Facilities Management Technical Information Library.

1. This resource provides information regarding construction specifications, construction procedures, design manuals, design guides, room finishes, and door/hardware schedules which should be followed throughout the administration of this contract.

12. Additional Info. The above SOW constitutes a basic outline of work required for this project but does not include all details required for the design, construction, and completion of this project. A pre-construction walkthrough and inspection of current conditions is recommended to determine all needs and requirements prior to starting the project.