S06 36C25023B0006 0003 - 553-20-101.pdf
PDF 174 KB Posted
- Solicitation number
- 36C25023B0006
About this file
This document package contains an amendment to a solicitation and the related federal contract opportunity. The amendment provides answers to additional questions from offerors seeking clarification on the solicitation for an elevator replacement project at the John D. Dingell Veterans Administration Medical Center in Detroit, Michigan. The estimated value of the project is between $5 million and $10 million. The contract will be a firm-fixed-price award made within 120 days of bid opening. The opportunity is exclusively reserved for qualified Service-Disabled Veteran Owned Small Businesses. Offerors should monitor the website for any changes and ensure registration in the necessary systems by the response date, which will be specified in the full solicitation to be posted in November 2022.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25023B0006 0003 – Elevator Replacement Building 100 – 553-20-101 – VAMC Detroit, MI
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 3
01-24-2023
553-23-1-3508-0001
553-20-101
Department of Veterans Affairs Network Contracting Office (NCO) 10 24 Frank Lloyd Wright Dr.
Lobby M, Suite M2200 Ann Arbor MI 48105
Same as Block 6
To all Offerors/Bidders
36C25023B0006
01-24-2023
X
X X
The purpose of this Amendment is to:
1. Provide answers to the additional Request For Information (RFI) questions and provide clarification to previous RFI questions.
End of Amendment 0003
RICHMOND MCCLOUD
Contract Specialist
SF 30 CONTINUATION PAGE 36C25023B0006
AMENDMENT 0003
THE FOLLOWING ANSWERS TO REQUESTS FOR INFORMATION QUESTIONS ARE HEREBY
PROVIDED TO CLARIFY, UPDATE, REVISE, OR CORRECT CONTRACT SPECIFICATIONS AND/OR
DRAWINGS.
QUESTION AND ANSWER 1
Q1: Each Elevator Machine Room has a material hatch on the floor, where do those hatches open to in the interstitial space below and is there a hatch in the interstitial spaces below the machine rooms that continue to the top floor of the building? If not is there a clear path in and out of the interstitial space to an elevator to move equipment in and out of the building?
A1: The hatch allows access into the interstitial space below - there is access from the elevator to the interstitial space and then up through the hatch - Contractor to coordinate with COR for exact path during construction. Additionally, see the attached pictures for reference.
QUESTION AND ANSWER 2
Q2: During the site visit it was mentioned that disruptive work would need to be performed after normal working hours. Can the VA define how many decibels they consider to be disruptive so that we can plan for and price after hours work accordingly?
A2: Repetitive impact noise on the property shall not exceed the following dB limitations:
Time Duration of Impact Noise Sound Level in dB More than 12 minutes in any hour 70 Less than 30 seconds of any hour 85 Less than three minutes of any hour 80 Less than 12 minutes of any hour 75
However, the VA has the right to stop work in the area when the noise is disrupting patient care. Contractor shall provide notification of any anticipated noise so that proper VA personnel can be notified.
QUESTION AND ANSWER 3
Q3: The Proposal Documents are not altered or laid out for the two (2) alternates that are required by the drawings?
A3: There are no Bid Deduct Alternates for this Solicitation. See page 1, Section 10, para 2 which states in part: "The drawings and specifications for this project contain references to deducted work. All references to deducted work are to be ignored.”
QUESTION AND ANSWER 4
Q4: There is no reference in the Table of Contents for Fire Suppression although work is required by the drawings and there is a specification provided in the body of the technical specifications.
A4: There is no associated scope of work relating to fire suppression systems or Division 21 on the project. Spec section 21 13 13 can be omitted from the project manual.
A.1 ADDITIONAL ATTACHMENTS
See attached document: Hatch Steel Beam.
See attached document: Hatch In Interstitial.
See attached document: Hatch Picture.
A.1 ADDITIONAL ATTACHMENTS