RFI 1 - RESPONSE 4-14-22.pdf
PDF 92 KB Posted
- Attached to
- Construction - Replace Roof (539-21-113)
- Solicitation number
- 36C25022B0029_1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI 4 - Response 4-19-22.pdf | ||
| RFI 3 - Response 4-19-22.pdf | ||
| 36C25022B0029 0003.docx | DOCX document | |
| Asbestos Report - signed.pdf | ||
| 36C25022B0029 0002.pdf | ||
| Pre-Bid Site Visit Sign In Sheet (4-11-2022).pdf | ||
| 36C25022B0029 0001.docx | DOCX document | |
| Contractor EMR Certification Form.pdf | ||
| VHA Directive 1192_01_D_2020-08-10.pdf | ||
| 36C25022B0029_1.docx | DOCX document | |
| 539-21-113 Replace Roof Bid Drawings 2-18-2022.pdf | ||
| 539-21-113 Replace Roof Bid Specs 2-14-2022.pdf | ||
| Wage Determination 3-11-22 02.pdf | ||
| RFI Form.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI #1
RECEIVED 4/13/22
The project has 244 calendar days to complete this project. By the time this project is awarded, submittals approved, and the material delivered to the jobsite it maybe not enough time to install the new material because it is temperature sensitive. Will additional calendar days be allocated to project and storage of the material be added to the project till it is warm enough?
VA RESPONSE:
Bid the solicitation has it is written. Period of Performance is 244 calendar days from receipt of Notice to Proceed.
| 2022-04-14T13:35:53-0400 | |
| Yvonne Demorest 497489 |