36C24W25Q0254 0001 Amendment.pdf
PDF 377 KB Posted
- Attached to
- 7125--Police Lockers and Installation Amendment
- Solicitation number
- 36C24W25Q0254
- Issued by
-
Department of Veterans Affairs
About this file
This document is an Amendment (0001) to a federal solicitation for police lockers and installation, issued by the Department of Veterans Affairs Regional Procurement Office West. The amendment provides answers to eight vendor questions about locker specifications and installation details. Key details include: lockers will be installed in two rooms on a lower level, with each locker unit consisting of an 18"w x 24"d x 72"h upper section and an 18"w x 36"d x 18"h lower drawer unit, totaling 90" in height. The lockers can be stored at a warehouse and transported to the job site via loading dock, with no elevator required. The solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB), with a NAICS code of 337215 and a small business size standard of 500 employees.
The amendment clarifies that no peg board panels are required for the lockers, and provides floor plan diagrams showing the proposed locker layout. The original solicitation (36C24W25Q0254) remains unchanged, with quotes due on 07/15/2025 at 09:00 AM CST. The amendment serves to provide additional information to potential offerors and ensure clarity about the locker specifications and installation requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24W25Q0254 0001_1.docx | DOCX document | |
| 36C24W25Q0254_1.docx | DOCX document | |
| S02 Solicitation 36C24W25Q0254 Police Lockers.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 4
36C24W
Department Of Veterans Affairs Regional Procurement Office West (RPOW) 3237 Peacekeeper Way Building 200 Suite 204 McClellan Park CA 95652
To all Offerors/Bidders 36C24W25Q0254
07-08-2025 X
X X
See CONTINUATION Page
X 1
The purpose of this amendment is to provide all offerors with the questions and answers submitted.
This amendment is not extending the due date for solicitation # 36C24W25Q0254.
The due date for quotes will remain 07/15/2025 @ 09:00AM CST.
Complete Section 15A - C Below
///SEE CONTINUATION PAGES///
Robert Clark Contracting Officer
None
36C24W25Q0254 – 0001 CONTINUATION PAGES
QUESTIONS WITH ANSWERS
1. Do you have a floor plan with the locker layout that you could provide or at least a floor plan of the area the lockers will be installed?
a. See below:
2. I want to clarify if the total height of the lockers should be 90"h (72"upper unit + 18"base unit) or 72"h total?
a. It comes in two sections, the upper unit which is 72” and the lower which in 18”. When stacked they are a combined 90 High. See below.
Upper Locker Unit - 18”w x 24”d x 72”h Lower Drawer Unit - 18”w x 36”d x 18”h
3. Are they going to be installed side by side? If yes, how many are going to be in a single lane together?
a. Yes; please see diagram from question # 1.
4. Is there a storage area for the lockers prior to installation?
a. Yes, they can be received at a warehouse and then transported to the job site.
5. How many rooms are these going to be installed at?
a. 2
6. At what floor are the room/s going to be? If above ground, is there a service elevator we can utilize to help carry the lockers?
a. Lower Level. Elevator is not required.
7. How many stairs leading to the building?
a. None, delivery to loading Dock.
8. Does the locker need to have a peg board panel so hooks can be inserted for the belts?
a. Locker peg board panels are not required.
(END OF QUESTIONS WITH ANSWERS)
File details come from the government source that posted it. Updated .