S02-Attachment 3- PMRS Final Bid Set Specs-626A4-21-101.pdf

PDF 12 MB Posted

Attached to
Y1DA--36C249-22-AP-3684 - 626A4-21-101 - Renovate & Expand PMRS
Solicitation number
36C24922R0091
Issued by

About this file

This document provides details for a federal construction contract opportunity to renovate and expand physical medicine rehabilitation services at a Veterans Affairs medical center. The Department of Veterans Affairs Network Contracting Office 9 Central Region will issue a request for proposals on or about August 24, 2022 for construction services at the Alvin C. York VA Medical Center in Murfreesboro, Tennessee. The project scope involves renovating and expanding PMRS and related work with an estimated construction budget between $2 million and $5 million. The contract is fully set aside for verified service-disabled veteran-owned small businesses. Proposals are due on unspecified dates and the contract is for construction services to be completed under the requirements outlined in the project documents.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

214 Centerview Dr. Suite 300 Brentwood, TN 37027 615.370.8500 www.hfrdesign.com

L E G A C Y + I N N O V A T I O N

PROJECT MANUAL

100% Construction Documents

Date: March 2, 2022 for the

Renovate and Expand Physical Medicine and Rehabilitation Services

Alvin. C. York VAMC - TVHS Murfreesboro, TN VA Project Number 626A4-21-101

WOLD | HFR DESIGN

Brentwood, Tennessee Project #596A-19-101

Renovate and Expand Physical Medicine and Rehabilitation Services Alvin. C. York VAMC - TVHS

00 00 01 - 1

TABLE OF CONTENTS

Division Section Title Pages

DIVISION 00 SPECIAL SECTIONS

000115 LIST OF DRAWING SHEETS 5

DIVISION 01 – GENERAL REQUIREMENTS

010000 GENERAL REQUIREMENTS 29

013216.15 PROJECT SCHEDULES 11

013323 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES 13

013526 SAFETY REQUIREMENTS 31

014219 REFERENCE STANDARDS 9

014500 QUALITY CONTROL 16

014529 TESTING LABORATORY SERVICES 12

015719 TEMPORARY ENVIRONMENTAL CONTROLS 8

015816 TEMPORARY INTERIOR SIGNAGE 1

017419 CONSTRUCTION WASTE MANAGEMENT 7

019100 GENERAL COMMISSIONING REQUIREMENTS 78

DIVISION 02 – EXISTING CONDITIONS

02 82 13.19 ASBESTOS FLOOR TILE AND MASTIC ABATEMENT 62

02 82 13.31 ASBESTOS TRANSITE ABATEMENT 57

LIMITED ASBESTOS AND LEAD PAINT SURVEY 57

02 83 33.13 LEAD-BASED PAINT REMOVAL AND DISPOSAL 12

00 00 00 - 1

Table of Contents Generated by MasterWorks

SPECIFICATIONS GROUP

Facility Construction Subgroup

DIVISION 03 - CONCRETE

033053 (SHORT-FORM) CAST-IN-PLACE CONCRETE 13

DIVISION 04 - MASONRY

040513 MASONRY MORTARING 5

040516 MASONRY GROUTING 4

DIVISION 05 - METALS

055000 METAL FABRICATIONS 12

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

066111 DECORATIVE PLASTIC RESIN FABRICATIONS 4

066116 SOLID SURFACING FABRICATIONS 6

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

072113 THERMAL INSULATION 6

078100 APPLIED FIREPROOFING 10

078400 FIRESTOPPING 6

079200 JOINT SEALANTS 10

DIVISION 08 - OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES 9

081400 INTERIOR WOOD DOORS 8

083113 ACCESS DOORS AND FRAMES 6

084113 ALUMINUM FRAMED ENTRANCES AND STOREFRONTS 10

085113 ALUMINUM WINDOWS 9

087100 DOOR HARDWARE 33

087113 AUTOMATIC DOOR OPERATORS 6

087113.11 LOW ENERGY POWER ASSIST DOOR OPERATORS 6

088000 GLAZING 15

089000 LOUVERS AND VENTS 6

DIVISION 09 - FINISHES

090516 SUBSURFACE PREPARATION FOR FLOOR FINISHES 8

092216 NON-STRUCTURAL METAL FRAMING 8

092900 GYPSUM BOARD 10

00 00 00 - 2

093013 CERAMIC / PORCELAIN TILING 19

095100 ACOUSTICAL CEILINGS 9

096513 RESILIENT BASE AND ACCESSORIES 5

096516 RESILIENT SHEET FLOORING 8

096519 RESILIENT TILE FLOORING 8

096723.30 RESINOUS (EPOXY BASE) HIGH PERFORMANCE DECORATIVE MORTAR

FLOORING

096800 CARPETING 8

098433 SOUND ABSORBING WALL UNITS 3

099100 PAINTING 23

DIVISION 10 - SPECIALTIES

101113 CHALKBOARDS AND MARKERBOARDS 4

101400 SIGNAGE 8

102113 TOILET COMPARTMENTS 3

102123 CUBICLE CURTAIN TRACKS 5

102600 WALL AND DOOR PROTECTION 7

102800 TOILET, BATH, AND LAUNDRY ACCESSORIES 11

104413 FIRE EXTINGUISHER CABINETS 2

DIVISION 11 - EQUIPMENT

110512 GENERAL MOTOR REQUIREMENTS FOR EQUIPMENT 5

DIVISION 12 - FURNISHINGS

122114 BETWEEN GLASS BLINDS 4

123200 MANUFACTURED WOOD CASEWORK 10

123600 COUNTERTOPS 5

END OF TABLE OF CONTENTS

Table of Contents Generated by MasterWorks: 12/13/2021

SPECIFICATIONS GROUP

DIVISION 21 - FIRE SUPPRESSION

210800 COMMISSIONING OF FIRE SUPPRESSION SYSTEMS 3

211313 WET-PIPE SPRINKLER SYSTEMS 11

DIVISION 22 - PLUMBING

220511 COMMON WORK RESULTS FOR PLUMBING 32

220519 METERS AND GAGES FOR PLUMBING PIPING 4

220523 GENERAL-DUTY VALVES FOR PLUMBING PIPING 14

220711 PLUMBING INSULATION 18

220800 COMMISSIONING OF PLUMBING SYSTEMS 4

221100 FACILITY WATER DISTRIBUTION 14

221300 FACILITY SANITARY AND VENT PIPING 16

221400 FACILITY STORM DRAINAGE 14

224000 PLUMBING FIXTURES 15

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

230511 COMMON WORK RESULTS FOR HVAC 37

230512 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT 11

230541 NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT 14

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC 9

230711 HVAC AND BOILER PLANT INSULATION 20

230800 COMMISSIONING OF HVAC SYSTEMS 4

232113 HYDRONIC PIPING 21

232213 STEAM AND CONDENSATE HEATING PIPING 27

233100 HVAC DUCTS AND CASINGS 16

233400 HVAC FANS 6

233600 AIR TERMINAL UNITS 6

233700 AIR OUTLETS AND INLETS 5

DIVISION 26 - ELECTRICAL

260511 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS 11

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 6

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 8

260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS 12

260800 COMMISSIONING OF ELECTRICAL SYSTEMS 4

260923 LIGHTING CONTROLS 5

262726 WIRING DEVICES 6

262911 MOTOR CONTROLLERS 7

262921 ENCLOSED SWITCHES AND CIRCUIT BREAKERS 4

265100 INTERIOR LIGHTING 10

DIVISION 27 - COMMUNICATIONS

270511 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS 45

270526 GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS 9

270533 RACEWAYS AND BOXES FOR COMMUNICATIONS SYSTEMS 15

271000 CONTROL, COMMUNICATION AND SIGNAL WIRING 10

271100 TELECOMMUNICATIONS ROOM FITTINGS 6

271500 COMMUNICATIONS STRUCTURED CABLING 18

274131 MASTER ANTENNA TELEVISION EQUIPMENT AND SYSTEMS 26

275116 PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 61

275223 NURSE CALL AND CODE BLUE SYSTEMS 64

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

280500 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY 64

280513 CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY 19

280526 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY 8

281300 PHYSICAL ACCESS CONTROL SYSTEM 33

282300 VIDEO SURVEILLANCE 24

282600 ELECTRONIC PERSONAL PROTECTION SYSTEM 12

END OF TABLE OF CONTENTS

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

"GI 00.01" "COVER SHEET"

"GI 01.01" "GENERAL DATA"

"GI 01.10" "WALL TYPE DETAILS"

"GI 01.20" "ACCESSIBILITY DETAILS"

"GI 01.40" "BASEMENT ICRA PLAN"

"GI 01.41" "ICRA ASSESSMENT"

"GI 02.03" "BASEMENT LIFE SAFETY PLAN"

"GI 02.04" "BASEMENT SCOPE OF WORK"

"GI 02.05" "BASEMENT PHASING PLAN"

"GI 03.01" "ASBESTOS-LEAD SAMPLE LOCATION DRAWING"

"GI 03.02" "ASBESTOS CONTAINING MATERIAL LOCATION PLAN"

"GI 03.03" "DUCT MASTIC PLAN"

"GI 03.04" "ASBESTOS KEYNOTES"

DEMOLITION

"AD 01.01" "BASEMENT DEMOLITION PLAN"

ARCHITECTURAL

"AE 01.01" "OVERALL BASEMENT FLOOR PLAN"

"AE 01.01A" "BASEMENT FLOOR PLAN AREA A"

"AE 01.01B" "BASEMENT FLOOR PLAN AREA B"

"AE 01.01C" "BASEMENT FLOOR PLAN AREA C"

"AE 01.01D" "BASEMENT FLOOR PLAN PART D AND MECH BASEMENT"

"AE 01.10A" "BASEMENT PLAN AREA A - DIMENSIONED"

"AE 01.10B" "BASEMENT PLAN AREA B - DIMENSIONED"

"AE 01.10C" "BASEMENT PLAN AREA C - DIMENSIONED"

"AE 01.10D" "BASEMENT PLAN PART D - DIMENSIONED"

"AE 03.01" "DOOR ELEVATIONS, SCHEDULE, & NOTES"

"AE 03.02" "DOOR DETAILS"

"AE 03.03" "WINDOW DETAILS"

"AE 08.01" "MISC. DETAILS"

"AE 08.02" "CEILING DETAILS"

"AE 08.03" "MISC. INTERIOR DETAILS"

"AE 09.01" "INTERIOR ELEVATIONS"

"AE 09.02" "INTERIOR ELEVATIONS - CORRIDORS"

"AE 10.01" "CASEWORK SECTIONS AND MISC DETAILS"

"AC 11.01" "OVERALL BASEMENT CEILING PLAN"

"AC 11.01AB" "BASEMENT CEILING PLAN PART A AND B"

00 01 15 - 2

"AC 11.01C" "BASEMENT CEILING PLAN AREA C"

"AC 11.01D" "BASEMENT CEILING PLAN AREA D"

"QH 12.01A" "BASEMENT EQUIPMENT PLAN AREA A"

"QH 12.01B" "BASEMENT EQUIPMENT PLAN AREA B"

"QH 12.01C" "BASEMENT EQUIPMENT PLAN PART C"

"QH 12.01D" "BASEMENT EQUIPMENT PLAN PART D""

INTERIOR DESIGN

"IN 01.00" "FINISH LEGEND & SCHEDULE"

"IN 01.01A" "ENLARGED BASEMENT FINISH PLAN AREA A"

"IN 01.01B" "ENLARGED BASEMENT FINISH PLAN AREA B"

"IN 01.01C" "ENLARGED BASEMENT FINISH PLAN AREA C"

"IN 01.01D" "ENLARGED BASEMENT FINISH PLAN AREA D"

"IN 02.01A" "ENLARGED BASEMENT PATTERN PLAN AREA A"

"IN 02.01B" "ENLARGED BASEMENT PATTERN PLAN AREA B"

"IN 02.01C" "ENLARGED BASEMENT PATTERN PLAN AREA C"

"IN 02.01D" "ENLARGED BASEMENT PATTERN PLAN AREA D"

"IN 03.00" "SIGNAGE LEGEND"

"IN 03.01" "SIGNAGE SCHEDULE"

MECHANICAL

"M-MK-00" "LEGENDS, NOTES, AND SYMBOLS"

"M-MD-01" "OVERALL GROUND FLOOR PLAN - HVAC DEMO"

"M-MD-02" "BASEMENT PLAN DEMO AND NEW"

"M-MH-01" "OVERALL GROUND FLOOR PLAN - NEW DUCTWORK"

"M-MH-01A" "GROUND FLOOR PLAN PART A - NEW DUCTWORK"

"M-MH-01B" "GROUND FLOOR PLAN PART B - NEW DUCTWORK"

"M-MH-01C" "GROUND FLOOR PLAN PART C - NEW DUCTWORK"

"M-MH-01D" "GROUND FLOOR PLAN PART D - NEW DUCTWORK"

"M-MP-01" "OVERALL ROUND FLOOR PLAN NEW PIPING"

"M-MP-01A" "GROUND FLOOR PLAN PART A - NEW PIPING"

"M-MP-01B" "GROUND FLOOR PLAN PART B- NEW PIPING"

"M-MP-01C" "GROUND FLOOR PLAN PART C - NEW PIPING"

"M-MP-01D" "GROUND FLOOR PLAN PART D - NEW PIPING"

"M-MK-01" "MECHANICAL SCHEDULES"

"M-MJ-01" "MECHANICAL DETAILS"

"M-MJ-02" "MECHANICAL DETAILS"

"M-MI-01" "MECHANICAL CONTROLS"

PLUMBING

"P-PI-01" "PLUMBING LEGENDS & NOTES"

"P-PI-02" "PLUMBING SCHEDULES"

"P-PI-03" "PLUMBING DETAILS"

"P-PI-04" "PLUMBING DETAILS"

"P-PD-01" "OVERALL GROUND FLOOR PLAN PLUMBING - DEMO"

"P-PD-02" "OVERALL PLUMBING - DEMO"

"P-PD-03" "OVERALL GROUND FLOOR PLAN PLUMBING - DEMO"

"P-PP-01" "OVERALL GROUND FLOOR PLAN - NEW GRAVITY"

00 01 15 - 3

"P-PP-01A" "GROUND FLOOR PLAN PART A - NEW GRAVITY"

"P-PP-01B" "GROUND FLOOR PLAN PART B - NEW GRAVITY"

"P-PP-01C" "GROUND FLOOR PLAN PARTC - NEW GRAVITY"

"P-PP-01D" "GROUND FLOOR PLAN PART D - NEW GRAVITY"

"P-PP-02" "OVERALL GROUND FLOOR PLAN - NEW PRESSURE"

"P-PP-02A" "GROUND FLOOR PLAN PART A - NEW PRESSURE"

"P-PP-02B" "GROUND FLOOR PLAN PART B - NEW PRESSURE"

"P-PP-02C" "GROUND FLOOR PLAN PART C - NEW PRESSURE"

"P-PP-02D" "GROUND FLOOR PLAN PART D - NEW PRESSURE"

"P-PW-01A" "PLUMBING RISERS - PART A - GRAVITY"

"P-PW-01B" "PLUMBING RISERS - PART B - GRAVITY"

"P-PW-01C" "PLUMBING RISERS - PART C - GRAVITY"

"P-PW-01D" "PLUMBING RISERS - PART D - GRAVITY"

"P-PW-02A" "PLUMBING RISERS - PART A - PRESSURE"

"P-PW-02B" "PLUMBING RISERS - PART B - PRESSURE"

"P-PW-02C" "PLUMBING RISERS - PART C - PRESSURE"

"P-PW-02D" "PLUMBING RISERS - PART D - PRESSURE"

ELECTRICAL

"E-EI-00" "ELECTRICAL SYMBOLS LEGEND, LIGHTING FIXTURE SCHEDULE, AND

GENERAL NOTES"

"E-EI-01" "PARTIAL ELECTRICAL RISER DIAGRAM - NEW WORK"

"E-EI-03" "ELECTRICAL PANEL SCHEDULES"

"E-EI-04" "ELECTRICAL PANEL SCHEDULES"

"E-EI-05" "ELECTRICAL DETAILS"

"E-EI-06" "ELECTRICAL DETAILS"

"E-EI-07" "ELECTRICAL DETAILS"

"E-ED-01" "OVERALL BASEMENT FLOOR PLAN - ELECTRICAL DEMO"

"E-ED-02" "OVERALL GROUND FLOOR PLAN - ELECTRICAL DEMO"

"E-EP-01" "OVERALL BASEMENT FLOOR PLAN - NEW POWER"

"E-EP-01A" "GROUND FLOOR PLAN PART A - NEW POWER"

"E-EP-01B" "GROUND FLOOR PLAN PART B - NEW POWER"

"E-EP-01C" "GROUND FLOOR PLAN PART C - NEW POWER"

"E-EP-01D" "GROUND FLOOR PLAN PART D - NEW POWER"

"E-EL-01" "OVERALL GROUND FLOOR PLAN - NEW LIGHTING"

"E-EL-01A" "GROUND FLOOR PLAN PART A - NEW LIGHTING"

"E-EL-01B" "GROUND FLOOR PLAN PART B - NEW LIGHTING"

"E-EL-01C" "GROUND FLOOR PLAN PART C - NEW LIGHTING"

"E-EL-01D" "GROUND FLOOR PLAN PART D - NEW LIGHTING"

"E-EY-01" "OVERALL GROUND FLOOR PLAN - NEW SYSTEMS"

"E-EY-01A" "GROUND FLOOR PLAN PART A - NEW SYSTEMS"

"E-EY-01B" "GROUND FLOOR PLAN PART B - NEW SYSTEMS"

"E-EY-01C" "GROUND FLOOR PLAN PART C - NEW SYSTEMS"

"E-EY-01D" "GROUND FLOOR PLAN PART D - NEW SYSTEMS"

FIRE PROTECTION

"F-FI-01" "FIRE PROTECTION LEGENDS NOTES AND DETAILS"

"F-FD-01" "OVERALL BASEMENT FLOOR PLAN - PART A - FIRE PROTECTION -

DEMO"

00 01 15 - 4

"F-FD-02" "OVERALL GROUND FLOOR PLAN - FIRE PROTECTION DEMO"

"F-FX-01" "OVERALL FIRE PROTECTION - NEW WORK"

TECHNOLOGY

"T-TJ-00" "GENERAL TECHNOLOGY INFORMATION"

"T-TD-01" "OVERALL BASEMENT FLOOR DEMO PLAN - TECHNOLOGY"

"T-TJ-01" "OVERALL BASEMENT FLOOR PLAN - TECHNOLOGY NEW WORK"

"T-TJ-02" "TECHNOLOGY - ENLARGED ROOMS"

"T-TJ-03" "TECHNOLOGY - DETAILS"

"T-TJ-03A" "TECHNOLOGY - DETAILS"

"T-TJ-04" "TECHNOLOGY - RISER"

00 01 15 - 5

11-01-15 i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

1.10 RESTORATION

1.11 PHYSICAL DATA

1.12 PROFESSIONAL SURVEYING SERVICES

1.13 LAYOUT OF WORK

1.14 AS-BUILT DRAWINGS

1.15 USE OF ROADWAYS

1.16 RESIDENT ENGINEER'S FIELD OFFICE

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.18 TEMPORARY USE OF EXISTING ELEVATORS

1.19 TEMPORARY USE OF NEW ELEVATORS

1.20 TEMPORARY TOILETS

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

1.22 NEW TELEPHONE EQUIPMENT

1.23 TESTS

1.24 INSTRUCTIONS

1.25 GOVERNMENT-FURNISHED PROPERTY

1.26 RELOCATED // EQUIPMENT // ITEMS //

1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT

1.28 CONSTRUCTION SIGN

1.29 SAFETY SIGN

1.30 PHOTOGRAPHIC DOCUMENTATION

1.31 FINAL ELEVATION Digital Images

1.32 HISTORIC PRESERVATION

1.33 VA TRIRIGA CPMS

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work to renovate and expand physical medicine and rehab services as required by drawings and specifications at the historic York Campus of the VA Tennessee Valley Healthcare

System, 3400 Lebanon Pike, Murfreesboro, TN 37129.

B. Visits to the site by Bidders may be made only by appointment with the

Contracting Officer.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. Base Bid includes all work described in SOW, Drawings and

Specifications.

B. Bid Alternate NO.1: Same as Base Bid except eliminate… No finishes in room HAC G18. Install new door into room and paint the existing frame.

Also add new signage.

C. Bid Alternate NO. 2: Same as Bid Alternate NO. 1 except eliminate. No work in corridor. Work to stop at intersection between G-30 and G-31.

D. Bid Alternate NO. 3: Same as Bid Alternate NO. 2 except eliminate replacement of windows. Update sealant and caulking around the windows and touch up paint on the frames and replace sills with solid surface finish, but all existing windows will remain as is.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

01 00 00 -2

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give two week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Guards:

Not required.

D. Key Control:

Up to 2 contractor keys will be issued to the Prime Contractor. If lost, the Prime Contractor shall pay $50 per key that is not returned to the issuing VA. Final Payment on the project will be held until keys are returned or reimbursement (in full) is made the issuing department. Lost or theft of these issued keys must be reported to the COR immediately.

E. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This

01 00 00 -3 information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

01 00 00 -4

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials(Laydown Area) shall be as determined by the COR see (I) below for requirements.

E. Workmen are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR and where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

G. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to

01 00 00 -5 be used during the work, and a schedule defining the duration of the work with milestone subtasks.

I. Construction Fence/Laydown Area: Before construction operations begin, Contractor shall provide and maintain a chain link construction fence, 2.1m (seven feet) minimum height, around the construction/Laydown area indicated on the drawings or as provided by COR. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum

375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR. Area within fence is the entire responsibility including upkeep and maintenance of the contractor. Grass shall be mowed and edges/fence line trimmed, trash policed.

J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

K. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any

01 00 00 -6 energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR

ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the Resident Engineer COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris

01 00 00 -7 and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads; walks and entrances must be approved by the COR.

N. Coordinate the work for this contract with other construction operations as directed by Resident Engineer COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR in areas where alterations will occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.

Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4 and VAAR 852.236-88).

01 00 00 -8

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain

01 00 00 -9 the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

4. PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors if required in project. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental Protection Agency (EPA) and the

Department of Transportation (DOT) as outlined in Code of Federal

Regulation (CFR), Titled 40 and 49 respectively. The EPA's Toxic

Substance Control Act (TSCA) Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform

Hazardous Waste Manifest (EPA Form 8700-22), along with the Uniform

Hazardous Waste Manifest Continuation Sheet (EPA Form 8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the Manifest to the Medical Center Chief.

a. Copies of the following listed CFR titles may be obtained from the Government Printing Office:

40 CFR 261........Identification and Listing of Hazardous Waste

40 CFR 262........Standards Applicable to Generators of Hazardous

Waste

40 CFR 263........Standards Applicable to Transporters of

Hazardous Waste

40 CFR 761........PCB Manufacturing, Processing, Distribution in

Commerce, and use Prohibitions

49 CFR 172........Hazardous Material tables and Hazardous

Material Communications Regulations

49 CFR 173........Shippers - General Requirements for Shipments and Packaging

49 CRR 173........Subpart A General

49 CFR 173........Subpart B Preparation of Hazardous Material for

Transportation

49 CFR 173........Subpart J Other Regulated Material; Definitions and Preparation

01 00 00 -10

TSCA..............Compliance Program Policy Nos. 6-PCB-6 and 6-

PCB-7

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work sites, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge

Elimination System (NPDES) permit is required for this project. The

Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that

01 00 00 -11 are required to comply with the permit process and permit requirements.

Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the

Contractor's method of operations and operations planning and the

Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

- Designating areas for equipment maintenance and repair;

- Providing waste receptacles at convenient locations and provide regular collection of wastes;

- Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

- Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

- Providing adequately maintained sanitary facilities.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to

01 00 00 -12 contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

1.11 PHYSICAL DATA

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result existing site and condition drawings and should be verified by contractor.

(FAR 52.236-4)

B. Subsurface conditions – not performed or required.

C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical

Center – Not available or required.

D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of

Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

Not Required

1.13 LAYOUT OF WORK

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings and in the electronic version (scanned PDF) to the COR within

01 00 00 -13

15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.

C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.

1.16 RESIDENT ENGINEER'S FIELD OFFICE

Not Required

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

Not Required

1.18 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevator for handling building materials and

Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR for use of elevators.

Personnel for operating elevators will not be provided by the

Department of Veterans Affairs.

2. Contractor covers and provides maximum protection of following elevator components:

a. Entrance jambs, heads soffits and threshold plates.

b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c. Finish flooring.

3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if

01 00 00 -14 these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractor’s expense.

4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractor’s expense.

5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractor’s expense, if recommended by elevator inspector after elevator is released by Contractor.

6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.

1.19 TEMPORARY USE OF NEW ELEVATORS

Not Required

1.20 TEMPORARY TOILETS

A. Contractor will provide ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies. All connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies. The

Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the

Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install meters at Contractor's expense and furnish the

Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified. Not Required

01 00 00 -15

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:

1. Obtain heat by connecting to Medical Center heating distribution system.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation COR’s discretion of use of water from

Medical Center's system.

1.22 NEW TELEPHONE EQUIPMENT

1.23 TESTS

1.24 INSTRUCTIONS

Not Required

1.25 GOVERNMENT-FURNISHED PROPERTY

None

1.26 RELOCATED // EQUIPMENT // ITEMS //

None

1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT

None

1.28 CONSTRUCTION SIGN

Not Required

1.29 SAFETY SIGN

01 00 00 -16

1.30 PHOTOGRAPHIC DOCUMENTATION

A. During the construction period through completion, provide photographic documentation of construction progress attached to daily reports or as directed and filed per COR – Include photos of window anchors, insulation and any in wall work.

1.31 FINAL ELEVATION DIGITAL IMAGES

Not Required

1.32 HISTORIC PRESERVATION

Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the Resident Engineer COR verbally, and then with a written follow up.

1.33 VA TRIRIGA CPMS

Not required

- - - E N D - - -

01 32 16.15 - 1

Alvin. C. York VAMC - TVHS

SECTION 01 32 16.15

PROJECT SCHEDULES

PART 1- GENERAL

1.1 DESCRIPTION:

A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements

(Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.

1.2 CONTRACTOR'S REPRESENTATIVE:

A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (COTR).

B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.

C. The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.

1.3 CONTRACTOR'S CONSULTANT:

A. The Contractor shall submit a qualification proposal to the COTR, within 14 days of bid acceptance. The qualification proposal shall include:

1. The name and address of the proposed consultant.

2. Information to show that the proposed consultant has the qualifications to meet the requirements specified in the preceding paragraph.

3. A representative sample of prior construction projects, which the proposed consultant has performed complete project scheduling

01 32 16.15 - 2

Alvin. C. York VAMC - TVHS services. These representative samples shall be of similar size and scope.

B. The Contracting Officer has the right to approve or disapprove the proposed consultant, and will notify the Contractor of the VA decision within seven calendar days from receipt of the qualification proposal.

In case of disapproval, the Contractor shall resubmit another consultant within 14 calendar days for renewed consideration. The

Contractor shall have their scheduling consultant approved prior to submitting any schedule for approval.

1.4 COMPUTER PRODUCED SCHEDULES

A. The contractor shall provide monthly, to the Department of Veterans

Affairs (VA), all computer-produced time/cost schedules and reports generated from monthly project updates. This monthly computer service will include: three copies of up to five different reports (inclusive of all pages) available within the user defined reports of the scheduling software approved by the Contracting Officer; a hard copy listing of all project schedule changes, and associated data, made at the update and an electronic file of this data; and the resulting monthly updated schedule in PDM format. These must be submitted with and substantively support the contractor’s monthly payment request and the signed look ahead report. The COTR shall identify the five different report formats that the contractor shall provide.

B. The contractor shall be responsible for the correctness and timeliness of the computer-produced reports. The Contractor shall also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.

C. The VA will report errors in computer-produced reports to the

Contractor’s representative within ten calendar days from receipt of reports. The Contractor shall reprocess the computer-produced reports and associated diskette(s), when requested by the Contracting Officer’s representative, to correct errors which affect the payment and schedule for the project.

01 32 16.15 - 3

Alvin. C. York VAMC - TVHS

1.5 THE COMPLETE PROJECT SCHEDULE SUBMITTAL

A. Within 45 calendar days after receipt of Notice to Proceed, the

Contractor shall submit for the Contracting Officer's review; three blue line copies of the interim schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in the previously approved

CPM schedule program. The submittal shall also include three copies of a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data, including event cost.

Each activity/event on the computer-produced schedule shall contain as a minimum, but not limited to, activity/event ID, activity/event description, duration, budget amount, early start date, early finish date, late start date, late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start or start-to-start without lead or lag constraints. Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the Contracting Officer. The contractor shall make a separate written detailed request to the Contracting

Officer identifying these date constraints and secure the Contracting

Officer’s written approval before incorporating them into the network diagram. The Contracting Officer’s separate approval of the Project

Schedule shall not excuse the contractor of this requirement.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .