S02 - Attachment 4 - Combined Spec Vol 1.pdf

PDF 14 MB Posted

Attached to
Project 614-18-115, Renovate Operating Rooms
Solicitation number
36C24922R0015
Issued by

About this file

This document provides details for a federal contract opportunity to renovate operating rooms at a Department of Veterans Affairs medical center. The solicitation seeks a contractor to provide all necessary tools, labor, materials, equipment, permits, licenses, supervision and quality control to renovate operating rooms in accordance with the drawings and specifications. The work will be performed at the Department of Veterans Affairs Medical Center in Memphis, Tennessee. The solicitation number is 36C24922R0015 and was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9.

View the file

Other files

File Type Posted
S06 - Amendment 0006.pdf PDF
S05 - Amendment 0006 - Question and Answer.pdf PDF
S06 - Amendment 0005.pdf PDF
S05 - A0005 Amendment - Pre-bid Addendum 2022 10 06.pdf PDF
S06 - Amendment 0004.pdf PDF
S05 - Amendment 0004 - Questions and Answers .pdf PDF
S06 - Amendment 0003 - 614-18-115 - Renovate Operating Rooms Memphis VA.pdf PDF
S05 - Amendment 0003 - Attachment 3 - Site Visit Sign in Sheet - 614-18-115.pdf PDF
S05 - Amendment 0003 - Attachment 2 - Pre-bid Addendum.pdf PDF
S05 - Amendment 0003 - Attachment 1 - Questions and Answers - 614-18-115.pdf PDF
S06 - Amendment 0002 - Time Extension 10-7-2022.pdf PDF
S06 - Amendment 0001 - 614-18-115 - Renovate Operating Rooms - Memphis Tennessee.pdf PDF
S02 - Attachment 8 - Drawing Equipment.pdf PDF
S02 - Attachment 9 - Drawing Structural.pdf PDF
S02 - Solicitation - 36C24922R0015 - 614-18-115.pdf PDF
S02 - Attachment 2 - Contractor Safety and Environmental Record Evaluation Form.pdf PDF
S02 - Attachment 14 - Wage Determination - Shelby County - TN20220200 05-06-2022.pdf PDF
S02 - Attachment 5 - Combined Spec Vol 2.pdf PDF
S02 - Attachment 3 - Past Performance Questionnaire.pdf PDF
S02 - Attachment 13 - Drawing Electrical and Fire Alarm.pdf PDF
S02 - Attachment 1 - Pricing Schedule - Renovate Operating Rooms Memphis.xlsx XLSX spreadsheet
S02 - Attachment 10 - Drawing Fire Protection.pdf PDF
S02 - Attachment 12 - Drawing Plumbing.pdf PDF
S02 - Attachment 11 - Drawing Mechanical.pdf PDF
S02 - Attachment 6 - Drawing G001-003.pdf PDF
S02 - Attachment 7 - Drawing Architectural.pdf PDF
S03-(Presolicitation Notice) 36C24922R0015.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovate Operating Rooms Memphis VA Medical Center

Memphis, TN

January 31, 2020

Bid Specification Submittal Project Number: 614-18-115

Volume 1

Memphis VAMC

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01 33 23 Shop Drawings, Product Data, and Samples 01 35 26 Safety Requirements 01 42 19 Reference Standards 01 45 00 Quality Control 01 45 29 Testing Laboratory Services 01 45 35 Special Inspections 01 45 35.1 Statement of Special Inspections 01 45 35.2 Schedule of Special Inspections 01 57 19 Temporary Environmental Controls 01 74 19 Construction Waste Management 01 81 13 Sustainable Construction Requirements 01 91 00 General Commissioning Requirements

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 02 83 33.13 Lead-Based Paint Removal and Disposal

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete

DIVISION 04 – MASONRY – Not Used

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 05 36 00 Composite Metal Decking 05 50 00 Metal Fabrications

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation

Volume 1

00 01 10-2

07 81 00 Applied Fireproofing 07 84 00 Firestopping 07 92 00 Joint Sealants

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 08 14 00 Interior Wood Doors 08 31 13 Access Doors and Frames 08 71 00 Door Hardware 08 71 13.11 Low Energy Power Assist Door Operators 08 80 00 Glazing

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 09 06 00 Schedule for Finishes 09 22 16 Non-Structural Metal Framing 09 29 00 Gypsum Board 09 51 00 Acoustical Ceilings 09 67 23.30 Resinous (Epoxy Resin Composition) Mortar Flooring (RES-3) 09 91 00 Painting 09 96 59 Resinous Specialty Glazed Coating Systems for Walls, Ceilings, Wallboard, and Block CMU (RES-W1, RES-W2)

DIVISION 10 – SPECIALTIES

10 11 13 Chalkboards and Markerboards 10 14 00 Signage 10 26 00 Wall and Door Protection 10 44 13 Fire Extinguisher Cabinets

DIVISION 11 – EQUIPMENT

11 76 00 Hospital Operating Room Modular Filtered Diffuser System

DIVISION 12 – FURNISHINGS

12 32 00 Manufactured Wood Casework 12 36 00 Countertops

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural Components

DIVISION 14– CONVEYING EQUIPEMENT – Not Used

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems

DIVISION 22 – PLUMBING

Volume 2

00 01 10-3

22 05 11 Common Work Results for Plumbing 22 05 19 Meters and Gages for Plumbing Piping 22 05 23 General-Duty Valves for Plumbing Piping 22 07 11 Plumbing Insulation 22 08 00 Commissioning of Plumbing Systems 22 11 00 Facility Water Distribution 22 13 00 Facility Sanitary and Vent Piping 22 14 00 Facility Storm Drainage 22 40 00 Plumbing Fixtures 22 40 11 Custom Fabricated Scullery Sinks 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 22 63 00 Gas Systems for Laboratory and Healthcare Facilities

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING

(HVAC)

23 05 11 Common Work Results for HVAC 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 11 HVAC and Boiler Plant Insulation 23 08 00 Commissioning of HVAC Systems 23 09 23 Direct-Digital Control System for HVAC 23 21 13 Hydronic Piping 23 31 00 HVAC Ducts and Casings 23 36 00 Air Terminal Units 23 37 00 Air Outlets and Inlets 23 40 00 HVAC Air Cleaning Devices

DIVISION 25 – INTEGRATED AUTOMATION – Not Used

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 05 73 Overcurrent Protective Device Coordination Study 26 08 00 Commissioning of Electrical Systems 26 20 11 Isolated Power Systems 26 22 00 Low-Voltage Transformers 26 27 26 Wiring Devices 26 29 21 Enclosed Switches and Circuit Breakers 26 51 00 Interior Lighting

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 27 05 26 Grounding and Bonding for Communications Systems 27 05 33 Raceways and Boxes for Communications Systems 27 08 00 Commissioning of Communications Systems 27 10 00 Control, Communication and Signal Wiring 27 15 00 Communications Structured Cabling

00 01 10-4

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 13 00 Physical Access Control System 28 31 00 Fire Detection and Alarm

DIVISION 31 – EARTHWORK – Not Used

DIVISION 32 – EXTERIOR IMPROVEMENTS – Not Used

DIVISION 33 – UTILITIES – Not Used

DIVISION 34 – TRANSPORTATION – Not Used

DIVISION 48 – ELECTRICAL POWER GENERATION – Not Used

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWINGS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

G001 Cover Sheet

G002 Legends, Abbreviations and Notes

G003 Overall Phasing Plan

ARCHITECTURAL

LS101 Life Safety Plan

AD101 Third Floor Demolition Plan – Phase 1

AD102 Third Floor Demolition Plan – Phase 2

AD103 Third Floor Demolition Plan – Phase 3

AD111 Third Floor Reflected Ceiling Demolition Plan – Phase 1

AD112 Third Floor Reflected Ceiling Demolition Plan – Phase 2

AD113 Third Floor Reflected Ceiling Demolition Plan – Phase 3

A001 Second Floor Ceiling Access Plan

A100 Overall Third Floor Plan

A101 Third Floor Construction Plan – Phase 1

A101.1 Third Floor Dimensioning Plan – Phase 1

A102 Third Floor Construction Plan – Phase 2

A102.1 Third Floor Dimensioning Plan – Phase 2

A103 Third Floor Construction Plan – Phase 3

A111 Third Floor Reflected Ceiling Plan – Phase 1

A112 Third Floor Reflected Ceiling Plan – Phase 2

A113 Third Floor Reflected Ceiling Plan – Phase 3

A351 Third Floor Sections

A401 Enlarged Cardiothoracic OR Plans and Elevations

A402 Enlarged Robotics OR Plans and Elevations

A403 Enlarged Neurosurgical OR Plans and Elevations

A404 Enlarged General OR Plans and Elevations

A405 Enlarged ENT OR Plans and Elevations

A501 Partition Types and Details

A502 Plan Details

A503 Plan Details

A601 Room Finish Schedule and Signage Floor Plan

00 01 15 - 2

Drawing No. Title

A611 Door, Frame, and Glazing Schedules and Details

EQUIPMENT

QH121 Equipment Plan Cardiothoracic OR

QH122 Equipment Plan Robotics OR

QH123 Equipment Plan Neurosurgical OR

QH124 Equipment Plan General OR

QH125 Equipment Plan ENT OR

STRUCTURAL

S001 Structural Notes

S002 Structural Notes

S101 Third Floor Framing Plan

S102 Fourth Floor Framing Plan

S501 Steel Details

FIRE PROTECTION

F001 General Notes, Legend and Details

FD101 Third Floor Demolition Plan – Phase 1

FD102 Third Floor Demolition Plan – Phase 2

FP101 Third Floor Plan – Phase 1

FP102 Third Floor Plan – Phase 2

MECHANICAL

M-001 Legend and General Notes

M-002 Third Floor Air Balance Diagram

M-501 Details

M-601 Schedules

MD101 Third Floor Demolition Plan – Phase 1

MD102 Third Floor Demolition Plan – Phase 2

MD103 Third Floor Piping Demolition Plan

MD104 Fourth Floor Demolition Plan - Phase 1

MD105 Fourth Floor Piping Demolition Plan - Phase 1

MH101 Third Floor Plan – Phase 1

MH102 Third Floor Plan – Phase 2

MH103 Fourth Floor Plan

MP101 Fourth Floor Piping Plan

00 01 15 - 3

Drawing No. Title

MI601 Controls

PLUMBING

P-001 Plumbing Legend and Sequence of Work

P-501 Schedules and Details

PD101 Second Floor Demolition Piping Plan – Phase 1

PD102 Second Floor Demolition Piping Plan – Phase 2

PD103 Third Floor Demolition Piping Plan – Phase 1

PD104 Third Floor Demolition Piping Plan – Phase 2

PD105 Fourth Floor Demolition Piping Plan – Phase 1

PD106 Fourth Floor Demolition Piping Plan – Phase 2

PL101 Second Floor Gravity Plan – Phase 1

PL102 Second Floor Gravity Plan – Phase 2

PL103 Third Floor Gravity Piping Plan – Phase 1

PL104 Third Floor Gravity Piping Plan – Phase 2

PL105 Fourth Floor Gravity Piping Plan – Phase 1

PL106 Fourth Floor Gravity Piping Plan – Phase 2

PL201 Gravity Piping Isometric Riser Diagram – Phase 1

PL202 Gravity Piping Isometric Riser Diagram – Phase 2

PP101 Third Floor Pressure Piping Plan – Phase 1

PP102 Third Floor Pressure Piping Plan – Phase 2

PP103 Fourth Floor Domestic Water Distribution Plan – Phase 1

PP104 Fourth Floor Domestic Water Distribution Plan – Phase 2

PP105 Fourth Floor Medical Gas and Vac Distribution Plan – Phase 1

PP106 Fourth Floor Medical Gas and Vac Distribution Plan – Phase 2

PP201 Enlarged Floor Plan

PP301 Water Distribution Isometric Riser Diagram

PP302 Medical Gas and Vac Distribution Isometric Riser Diagram

ELECTRICAL

E-001 Legend and Schedules

E-002 Electrical Riser Diagram

E-003 Panelboard Schedules

E-004 Panelboard Schedules

ED101 Third Floor Demolition Plan-Phase 1-Electrical

ED102 Third Floor Demolition Plan-Phase 2-Electrical

ED103 Third Floor Demolition Plan-Phase 3-Electrical

00 01 15 - 4

Drawing No. Title r ED104 Demolition Plan-Phase 2 - Electrical

EL101 Third Floor Lighting Plan – Phase 1

EL102 Third Floor Lighting Plan – Phase 2

EL103 Third Floor Lighting Plan – Phase 3

EL501 Lighting Fixture Details

EP101 Third Floor Power Plan – Phase 1

EP102 Third Floor Power Plan – Phase 2

EP103 Fourth Floor Power Plan – Phase 2

EP104 Third Floor Power Plan – Phase 3

EY101 Third Floor Special Systems Plan – Phase 1

EY102 Third Floor Special Systems Plan – Phase 2

EY103 Third Floor Special Systems Plan – Phase 3

EY501 Details – Special Systems

FA101 Third Floor Plan – Fire Alarm

- - - E N D - - -i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 RESTORATION

1.10 AS-BUILT DRAWINGS

1.11 WARRANTY MANAGEMENT

1.12 USE OF ROADWAYS

1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.14 TEMPORARY USE OF EXISTING ELEVATORS

1.15 TEMPORARY TOILETS

1.16 AVAILABILITY AND USE OF UTILITY SERVICES

1.17 NEW TELEPHONE EQUIPMENT

1.18 TESTS

1.19 INSTRUCTIONS

1.20 GOVERNMENT-FURNISHED PROPERTY

1.21 REMOVED TEMPORARY ITEMS

1.23 CONSTRUCTION SIGN

1.24 SAFETY SIGN

Memphis VAMC 12-01-18

01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Memphis VAMC Renovate

Operating Rooms as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the

Medical Center Engineering Officer.

C. Offices of Toland Mizell Molnar, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his/her duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. The term “Resident Engineer” as referenced in any and all specification sections of this project manual is the COR.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Memphis VAMC Renovate Operating Rooms:

Work includes demolition, general construction and alterations complete as indicated and specified for this project. The work includes

01 00 00 - 2 modifications to the existing area including demolition of existing spaces as designated. All areas of work are part of the project including concrete, steel construction, carpentry, doors, finishes, specialty items, mechanical plumbing, fire protection, electrical systems work, rough-in for equipment, and other items as indicated and/or specified.

A. ALTERNATE NO.1: Delete all costs of work to apply high-glaze special coatings on the Phase 3 operating room walls and ceilings.

B. ALTERNATE NO.2: Delete all costs of demolition and installation work to remove existing vinyl flooring and base and install resinous epoxy flooring (RES-3) in Phase 3 operating rooms.

C. ALTERNATE NO. 3: Delete all costs of demolition and installation work to remove existing vinyl flooring and base and install resinous epoxy flooring (RES-3) in Phase 3 operating rooms and spaces including the semi-restricted corridor.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can

01 00 00 - 3 be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. Refer to Section 08 71 00, DOOR HARDWARE.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

01 00 00 - 4

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

01 00 00 - 5

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR .

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

01 00 00 - 6

G. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and

Contractor, as follows:

a. Phase 1:

Phase I work shall include General Operating Room, ENT Operating Room and adjoining equipment rooms and support spaces as defined in the construction documents as Phase 1.

b. Phase 2:

Phase 2 work shall include Cardio, Robotics and Neuro operating rooms and adjoining pump room, equipment rooms, support spaces and semi-restricted corridor as defined in the construction documents as Phase 2.

c. Phase 3:

Phase 3 shall include work in existing Ortho, Eye, Cysto and Echo/Hybrid operating rooms and in all existing equipment rooms, support spaces and areas and semi-restricted corridor as defined in the construction documents as Phase 3.

H. The surgery department will be occupied during performance of work; but immediate areas of alterations will be vacated.

1. Certain areas of the surgery department will be occupied by Medical

Center personnel from 6:30 am to 6:00 pm Monday through Friday:

01 00 00 - 7

a. Phase 1: Cardiac Supply, OR-2 Cardiac, Neuro OR-3, Vascular OR-4

General Surgery/ENT OR-5, Soiled Decontamination, Ortho OR-6, Eye

OR-8, Eye Equipment Endo/Hybrid OR-7, Cysto OR-9, semi-restricted corridor and adjacent support spaces.

b. Phase 2: Completed Phase 1 areas, Ortho OR-6, Eye OR-8, Eye

Equipment Endo/Hybrid OR-7, Cysto OR-9, semi-restricted corridor and adjacent support spaces.

c. Phase 3: Completed Phase 1 and Phase 2 areas and all areas in

Phase 3.

Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting, etc., to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

2. Phase 1, Phase 2 and Phase 3 areas of alterations mentioned in preceding Subparagraph 1 will be temporarily vacated while alterations are performed. Construction work to be performed between the hours of 6:00 PM to 5:00 AM Monday through Friday. Construction area access during weekends and holidays will be available to the

Contactor as coordinated and approved by the COR. Resinous flooring and special coating wall and ceiling work may need to be completed over weekends and holidays to allow required curing time. Phase 3 lighting work can be completed during the overnight schedule from

Monday through Friday.

I. When a construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

01 00 00 - 8

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

J. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR

ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

01 00 00 - 9

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

L. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

M. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:

01 00 00 - 10

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within building where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE

CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR

852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

01 00 00 - 11

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

01 00 00 - 12

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

1.10 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR’s review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

01 00 00 - 13

1.11 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the

Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

01 00 00 - 14

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance Bond: The Performance Bond must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of

01 00 00 - 15 expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for

Contractor response, and other details deemed necessary by the

Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.

This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

Following oral or written notification by the Contracting Officer, the

Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.

Include within the report the cause of the problem, date reported, 01 00 00 - 16 corrective action taken, and when the repair was completed. If the

Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

Code 1-Life Safety Systems

a. Fire suppression systems.

b. Fire alarm system(s).

Code 1-Air Conditioning Systems

a. Air conditioning leak in part of the building, if causing damage.

b. Air conditioning system not cooling properly.

Code 1 Doors

a. Interior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

Code 3-Doors

a. Interior personnel doors or hardware not functioning properly.

Code 1-Electrical

a. Power failure (entire area or any building operational after 1600 hours).

b. Security lights.

c. Smoke detectors.

01 00 00 - 17

Code 2-Electrical

a. Power failure (no power to a room or part of building).

b. Receptacles and lights not operational (in a room or part of building).

Code 1-Heat

a. Power failure affecting heat.

Code 1-Plumbing

a. Hot water heater failure.

b. Leaking water supply pipes.

Code 2-Plumbing

a. Flush valves not operating properly

b. Fixture drain, supply line or any water pipe leaking.

c. Toilet leaking at base.

Code 3- Plumbing

a. Leaky faucets.

Code 3-Interior

a. Floors damaged.

b. Paint chipping or peeling.

c. Casework damaged.

Code 2-Water (Hot)

a. No hot water in portion of building listed.

Code 3

a. All work not listed above.

E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting

Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC

01 00 00 - 18 signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

1.12 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to

01 00 00 - 19 each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

2. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

3. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

4. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

5. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.14 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevator for handling building materials and

Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR for use of elevators.

The COR will ascertain that elevators are in proper condition.

Contractor may use elevators as designated by the COR in the adjacent bed tower for daily use between the hours of 6:00 PM and

01 00 00 - 20

6:00 AM and for special non-recurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.

2. Contractor covers and provides maximum protection of following elevator components:

a. Entrance jambs, heads soffits and threshold plates.

b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c. Finish flooring.

3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractor’s expense.

1.15 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

1.16 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final

01 00 00 - 21 acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install meters at Contractor's expense and furnish the

Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:

1. Obtain heat by connecting to Medical Center heating distribution system.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR’s discretion) of use of water from Medical Center's system.

1.17 NEW TELEPHONE EQUIPMENT

A. The contractor shall coordinate with the work of installation of telephone equipment by others. This work shall be completed before the building is turned over to VA.

01 00 00 - 22

1.18 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work.