About this file
This solicitation is for construction services to install emergency generators and perform related work at the Memphis VA Medical Center in Memphis, Tennessee. The scope of work involves installing two diesel generators, a new generator building, switchgear, automatic transfer switches, and electrical distribution system modifications to provide backup power for COVID-19 patient isolation units. The contractor must complete all work within 270 calendar days and is responsible for demolition, site preparation, and general construction activities according to provided drawings and specifications. The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses and will be awarded on a lowest-price technically acceptable basis. Offerors must submit technical and price proposals by June 29, 2021 and meet various eligibility requirements, including active SAM registration and VetBiz verification.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24921R0091
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24921R0091 X 06-02-2021
TBD
614-21-4-5956-0010 614-20-115 90C Department of Veterans Affairs Network Contracting Office (NCO) 9 1639 Medical Center Parkway Suite 400 Murfreesboro TN 37129 Same as Block 7.
Robert Pritchard 615-225-4525 Project: 614-20-115, COVID-19 - Emergency Generators at the Memphis VA Medical Center in Memphis, Tennessee.
The VA Medical Center has a requirement for construction services for a contractor to completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work to install emergency generators to provide backup power to the equipment that maintains HVAC services supporting the COVID-19 patient care isolation units, Ward 4E and Ward 5E, in building 1A.
NAICS code 236220 is applicable for this project. The small business size standard is $39.5M.
The Project Magnitude is Between $2,000,000 and $5,000,000.
A scheduled site visit will be held on Monday, June 14, 2021 at 1:00pm, CST at the Memphis VA Medical Center. All participants attending will meet at the Memphis VA Medical Center, Building 1A, Room F102.
To obtain clarifications and/or additional information concerning the contract requirements, specifications and/or draw-ings, submit a written Request for Information (RFI) via email to the Contracting Officer, Robert Pritchard at robert.pritchard2@va.gov. RFI's must be specific in identifying section, paragraph and page number and must be in a question format. All RFI's submitted shall include the Project Number and Title, Contractor Name, City, State, Telephone, Email Address, Date submitted and RFI question(s).
No questions received after 12:00pm ET, June 23, 2021 will be answered unless it is determined to be in the best interest of the Government as deemed by the CO. Telephone requests for information will not be accepted.
Project will be procured under FAR 15.101-2 Lowest Price Technically Acceptable. Evaluation Factors are listed in the solicitation.
In accordance with P.L. 109-461, this acquisition is 100% set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) concerns. To be eligible to receive an award under this solicitation, the SDVOSB contractor must be listed and viewable in the Vetbiz Registry located at www.vip.vetbiz.gov. The vetbiz listing will be checked both at the time of offer submission, as well as prior to award. Offerors are advised that the fast-track re-verification prog-ram ended September 30, 2012. Consequently, Offerors in "reverification" status will not be eligible to submit offers for this project. In accordance with FAR 52.204-7, System for Award Management (SAM), all prospective offerors must have an active SAM's registration at the time of offer submission.
X X 52.211-10 X 1:00pm 07-06-2021 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Bid Item 1 (Base Offer) - _______________ Bid Item 2 (Deduct Alternate 1) - _______________ **Detailed pricing must be submitted on the attached form titled "S02 Solicitation Attachment 4 -Price Schedule"
614-36C0162-5956-854200-3220 23NR0JA10
90C Department of Veterans Affairs Network Contracting Office (NCO) 9 Robert R. Pritchard 1639 Medical Center Parkway Murfreesboro TN 37129 90C FSC e-Invoice Payment http://www.fsc.va.gov/fsc/einvoice.asp Invoice Setup Information 1-877-489-6135 Invoice must be submitted electronically
Setup 1-877-489-6135 X Robert Pritchard Contracting Officer
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| STATEMENT OF WORK | 5 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 9 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 13 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 13 |
| 2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 14 |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 15 |
| 2.5 52.228-1 BID GUARANTEE (SEP 1996) | 16 |
| 2.6 52.233-2 SERVICE OF PROTEST (SEP 2006) | 17 |
| 2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 17 |
| 2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 18 |
| 2.9 VAAR 852.223-70 INSTRUCTIONS TO OFFERORS—SUSTAINABLE ACQUISITION PLAN (SEP 2019) | 18 |
| 2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 18 |
| 2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 19 |
| REPRESENTATIONS AND CERTIFICATIONS | 20 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018) | 20 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020) | 23 |
| 3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 26 |
| 3.4 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018) | 27 |
| GENERAL CONDITIONS | 30 |
| 4.1 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018) | 30 |
| 4.2 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 31 |
| 4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 32 |
| 4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013) | 32 |
| 4.5 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015) | 34 |
| 4.6 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 34 |
| 4.7 SUPPLEMENTAL INSURANCE REQUIREMENTS | 36 |
| 4.8 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ALTERNATE I (APR 1984) | 36 |
| 4.9 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 38 |
| 4.10 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 41 |
| 4.11 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020) | 41 |
| 4.12 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION) | 41 |
| 4.13 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 42 |
| 4.14 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 43 |
| 4.15 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 43 |
| 4.16 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 43 |
| 4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 44 |
| 4.18 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 45 |
| 4.19 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) ALTERNATE I (APR 2019) | 46 |
| 4.20 VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019) | 47 |
| 4.21 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 48 |
| 4.22 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 48 |
| 4.23 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 49 |
| ATTACHMENTS | 50 |
STATEMENT OF WORK
A. GENERAL INFORMATION
1. Title of Project: COVID-19 Emergency Generators
Scope of Work & Background: Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work to install emergency generators to provide backup power to the equipment that maintain the Heating, Ventilation and Air Conditioning (HVAC) services supporting the COVID-19 patient care isolation units, Ward 4E and Ward 5E, in Building 1A at the Memphis Veterans Administration (VA) medical center in Memphis, TN. This work includes new generators, generator building, controls, equipment, and modification to the current electrical power distribution system. Work requires coordination with occupied operations in spaces alongside, above, and below the affected isolation units, to modify and/or install new engineering systems. Demolition and renovation involve all other features not described herein but denoted in drawings and specifications. The contractor must furnish all management, supervision, labor, material, equipment, tools, supplies, parts, and related services, in accordance with drawings, and specifications to be a complete and working system. Electronic copies of drawings and specifications of this work will be furnished by VA upon Contractor's written request to the CONTRACTING OFFICER (CO) or Contracting Officer's Representative. Copies of drawings and specifications are contractor's responsibility and expense. Contractor is responsible to verify existing and new dimensions, locations, measurements, and quantities. This project is located on the Main Campus of the Memphis VA Medical Center at 1030 Jefferson Ave, Memphis, TN, as required by drawings and specifications.
2. Statement of Bid Items:
a. ITEM 1 NEW WORK: The Contractor shall provide all necessary tools, labor, material, equipment, permits, licenses and supervision for “COVID 19 Emergency Generator”, Project 614-20-115 located at the Memphis VA Medical Center in Memphis, TN according to the drawings and specifications. Work includes installation of two (2) new diesel, engine driven generators, new switchgear, new automatic transfer switches, temporary generator docking stations, generator equipment pads, generator screen wall, construction of a new switchgear room. Work includes general construction, alterations, grading, drainage, necessary removal of existing structures and construction and certain other items. Construction duration is 270 consecutive calendar days, including holidays and weekends.
b. DEDUCTIVE ALTERNATE NO. 1: REMOVE 500KW GENERATOR AND ASSOCIATED ELECTICAL WORK. Delete 500KW generator. Delete generator feeders and duct-bank between temporary generator connection cabinet and generator. Delete generator annunciator wiring from cooling tower building to existing building. Delete 500KW generator accessory panel and associated transformer. Utilize temporary generator connection cabinet in lieu of single breaker docking station. Removal of gravel at 500KW generator. Addition of concrete pad at 500KW generator location for temporary 01 00 00 – 3 generator parking. Addition of equipment gate at 500KW generator fencing. Construction duration is 240 consecutive calendar days, including holidays and weekends.
B. CONTRACT AWARD MEETING
The contractor shall not commence performance on the tasks in this SOW until the CO has conducted a kick-off meeting or has advised the contractor that a kick-off meeting is waived.
C. CONSTRUCTION
This project will renovate the areas as shown on the drawings and specifications.
D. SPECIFIC MANDATORY TASKS AND ASSOCIATED DELIVERABLES
Description of Tasks and Associated Deliverables: The contractor shall provide the specific deliverables described below within the performance period stated in Section A. 2. a) & b) of this SOW.
Task One: Submittals
Deliverable One: Provide Submittals in PDF for VA review within 7 days of award.
Task Two: Work performance.
Deliverable Two: Provide completed work that is fully inspected and remediated within 270 days of award, or 240 days of award respectively, except as reduced or extended by the CO.
E. SCHEDULE FOR DELIVERABLES
1. The contractor shall complete the Delivery Date column in Attachment A for each deliverable specified.
2. Unless otherwise specified, the number of draft copies and the number of final copies shall be the same.
3. If for any reason any deliverable cannot be delivered within the scheduled time frame, the contractor is required to explain why in writing to the CO, including a firm commitment of when the work shall be completed. This notice to the CO shall cite the reasons for the delay, and the impact on the overall project. The CO will then review the facts and issue a response, in accordance with applicable regulations. If deliverable cannot be delivered within the scheduled time frame, compensation may be taken from the contractor.
F. CHANGES TO STATEMENT OF WORK
1. Any changes to this SOW shall be authorized and approved only through written modifications to the contract by the CO. A copy of each modification will be kept in a project folder along with all other products of the project. Costs incurred by the contractor through the actions of parties other than the CO shall be borne by the contractor.
G. REPORTING REQUIREMENTS
1. Daily Log.
2. Weekly Progress Reports.
3. Certified Payroll for Personnel working on the Contract.
H. TRAVEL [If applicable]
1. Travel is NOT applicable for this statement of work.
I. GOVERNMENT RESPONSIBILITIES [If applicable]
1. The Government will NOT provide any other service outside applicable drawings, specifications, and Statement of work.
J. CONTRACTOR EXPERIENCE REQUIREMENTS
· The contractor must inform the VHA COR when personnel are removed from the contract for any reason.
· If a key person becomes unavailable to complete the contract, proposed substitutions of key personnel shall be made to the COR and CO.
K. SECURITY AND CONFIDENTIALITY
It is agreed that:
1. The preliminary and final deliverables, and all associated working papers, application source code, and other material deemed relevant by VA which have been generated by the contractor in the performance of this contract, are the exclusive property of the U.S. Government and shall be submitted to the CO at the conclusion of the contract.
2. The CO will be the sole authorized official to release, verbally or in writing, any data, draft deliverables, final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract, presented to the contractor, shall be submitted to the CO for response.
3. Press releases, marketing material, or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.
4. Employees shall not be on site without appropriate badge. Employees are responsible for reporting to the Engineering office with acceptable photo ID to obtain a badge. The Engineering office is in room AEG19 on the Ground Floor of Building 1. VA approved badge shall be worn with the identification facing forward and visible above the waist. The employees may also be subject to inspection of their personal effects when entering or leaving the facility.
END STATEMENT OF WORK
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
This section describes the evaluation process, proposal preparation, the significant factors and sub-factors and criteria to be used in the evaluation process. This procurement action is a Lowest Price Technically Acceptable source selection process in accordance with FAR 15.101-2. Proposals will be evaluated for acceptability, but not ranked using the non-price factors/sub-factors. In order to be considered for award, an offeror must have an “acceptable” rating in every non-price factor/sub-factor under consideration.
The Government intends to award a single contract to a qualified Service-Disabled Veteran Owned Small Business (SDVOSB) determined responsible in accordance with the Federal Acquisition Regulation (FAR), whose proposal conforms to all the requirements in this solicitation and is further determined to meet or exceed the standards of acceptability at the lowest offered price. The Government intends to evaluate proposals and award a contract without discussions with Offerors. Therefore, the Offeror’s initial proposal should contain the Offeror’s best terms from both a technical and cost standpoint.
The evaluation of offers submitted in response to this Request for Proposal (RFP) solicitation will be conducted utilizing the Lowest Price Technically Acceptable (LPTA) selection process. Utilization of this source selection process may result in not all offers being evaluated. The Contracting Officer upon receipt of offers, will determine eligibility and compliance to the solicitation requirements. The Vendor Information Pages (VetBiz registry) will be checked to ensure that any offeror submitting a proposal to perform the work is both listed and verified. All proposals received will also be checked for an active registration in the System for Award Management (SAM). Thereafter, the Contracting Officer will review all proposals to ensure that the minimum proposal submission requirements have been met. Once these requirements have been satisfied, the Contracting Officer will select and submit for review to the Technical Evaluation Board (TEB) the technical proposal of the lowest priced offeror for consideration. Initially, the TEB will not receive any pricing information, only the technical portion of the offeror’s proposal. The offeror’s proposal will be rated against each evaluation factor as set forth in this solicitation.
If the selected offeror’s proposal is determined to be acceptable based on the standards of acceptability, and that offeror’s price is the lowest of all offers submitted, then no further evaluation of offers shall occur, and the Contracting Officer will document these findings and proceed with the responsibility determination of the offeror. Pricing information will only be provided to the TEB upon notification to the Contracting Officer that the technical proposal as submitted meets or exceeds the acceptability standard necessary to fulfill the objective of the requirement.
Should the initial offeror’s proposal be determined to be unacceptable according to the standards of acceptability, then the TEB will be required to provide to the Contracting Officer a summary evaluation sheet that documents how the offeror’s proposal fails to meet the standards of acceptability, and request to the Contracting Officer that another selection be made for consideration of award. This process shall continue until such time that an award is made.
Offerors shall respond in writing to the evaluation factors listed below, in the same order as they appear in this solicitation document. Failure to provide all information will adversely affect the evaluation of an offer. The information contained in the technical proposal should be complete, concise, and address each factor. If information is applicable to more than one evaluation factor, it must be repeated for each factor, unless stated otherwise.
Proposals are to be submitted via email to the Contracting Officer, Robert Pritchard. Offerors shall submit two (2) copies of complete proposal (a. Technical & b. Price) to the email address shown below.
DEPARTMENT OF VETERANS AFFAIRS, SOLICITATION # 36C24921R0091
NETWORK CONTRACTING OFFICE 09
ATTN: CONTRACTING OFFICER, ROBERT R. PRITCHARD
1639 MEDICAL CENTER PARKWAY
SUITE 400
MURFREESBORO, TENNESSEE 37129
EMAIL: Robert.pritchard2@va.gov FAR 52.209-7 Information regarding responsibility Matters (b) shall be marked. If not marked, the proposal is technically unacceptable and cannot be considered for award.
Technical and Price sections of an Offeror’s proposal will be evaluated independently. Offeror shall separately bind each section. All pages containing text shall be consecutively numbered, type-written on 8-1/2x11 inch paper with margins of at least once inch and created using a Times New Roman 12-point font. The submitted package should contain two (2) sections, separately bind: a.) Technical Proposal b.) Price Proposal. The Offeror’s Technical proposal shall be no more than 50 pages’ total, which is not inclusive of the solicitation and any amendments issued thereof. The Offeror’s Price Proposal shall be no more than 25 pages inclusive of the bid bonds required. The Offeror is hereby advised that the attached “Pricing Schedule” worksheet shall be considered as 20 pages, regardless of the overall total. Each section must therefore be labeled with the following:
1. Construction Company Name
2. Physical Address of the Company
3. Telephone Number
4. Email address
5. VA Project Number (Project 614-20-115)
6. VA Project Name (COVID-19 Emergency Generator)
7. Solicitation number (36C24921R0091) The Technical Evaluation Board (TEB) shall evaluate the offeror’s proposal against all non-price factors/sub-factors using “ACCEPTABLE” or “UNACCEPTABLE” ratings based upon the standard of acceptability that follows each factor/sub-factor below. To obtain an “ACCEPTABLE” rating, an offeror must meet the standard of acceptability that is listed for each factor/sub-factor.
The evaluation process and criteria stated in this section will be strictly adhered to. Evaluators will make no assumptions regarding an offeror’s proposal. Therefore, an Offeror must demonstrate understanding by the thoroughness, soundness, comprehensiveness, and price reasonableness of technical approach. There will be no public opening of offers.
The following evaluation factors and sub-factors will apply to this procurement:
FACTOR 1 – Hospital/Healthcare Construction Management The offeror shall provide a narrative that describes the Offeror’s overall organization, organizational chart, as well as number of personnel and the duties of proposed technical staff to determine if offeror can manage multi-discipline projects without significant difficulty. The proposal narrative must adequately address functions, responsibilities, and authorities for performing such duties as overall project management, site superintendence, quality control, safety, administration, and in-house trade capabilities.
Sub-Factor 1a – Relevant Experience: The Prime Contractor shall provide demonstrated experience in new construction or the addition of a hospital/medical center and/or health care facility for two (2) completed projects within the past five (5) years with a contract value equal to or greater than $3,000,000.00. The subject project must have consisted of multiple trades to demonstrate the management and coordination of trades by the Prime Contractor.
Standard for Acceptability: This factor will be considered acceptable if the information provided reflects adequate experience in new construction or the addition of a hospital/medical center and/or health care facility meeting the criteria as stated above and demonstrates successful management and coordination of multiple trades by the Prime Contractor.
Sub-Factor 1b - Key Personnel: Provide the names of the Prime Contractor’s project manager and on-site superintendent, including name with title, years with prime contractor, and total work experience as it relates to the new construction or the addition of a hospital/medical center and/or health care facility. Both Project Manager and Site Superintendent must demonstrate (by way of professional resume) experience in managing and providing oversight with new hospital construction or construction additions with a project magnitude equal to or greater than $3,000,000.00 or more over the past five (5) years.
Standard for Acceptability: Project manager and the on-site superintendent must have a minimum of five (5) or more years of experience managing new hospital construction and/or construction additions in a hospital or medical center environment.
FACTOR 2 - Technical Management Approach: The offeror shall provide a narrative that outlines the proposed technical approach for this project, including assumptions and rationale for choosing the preferred approach.
Sub-Factor 2a-Project & Construction Quality Control: Include a discussion of how the duration of project time was achieved; provide a Gantt chart of contract times broken into schedule of values by trade discipline and by General Wage Decision (formerly Davis-Bacon Act). Offeror must include identification of proposed personnel for project management, site superintendence, and quality control, including role in commissioning, safety during construction, and in-house trade capabilities.
Standard for Acceptability: Gantt chart achieving successful project completion in 270 calendar days, with all requirements met for contract. Technical narrative always demonstrates sound logic with minimal disruption to medical center operations.
Sub-Factor 2b-Change Order Management: Explain methods for identifying changes along with company procedures for managing changes, regardless if unforeseen site conditions or owner-initiated changes. Methods and procedures for handling changes are to be based on your experience in hospital construction of a project of this magnitude and scope, involving multiple trades and the coordination of trades. Discuss any potential changes or unforeseen conditions that could result from this project along with how those would be handled both internally as a company and with the VA.
Standard for Acceptability: This factor will be considered acceptable if the information provided demonstrates adequate procedures for identifying and handling changes as stated above.
FACTOR 3 - Past Performance: Offeror shall list three (3) only prior clients for completed projects of new construction or new addition of hospital/healthcare facility, medical clinics where the projects dollar magnitude equal to or greater than $3,000,000.00 within the last five (5) years on the VA Past Performance questionnaire and ask the client to forward directly to the Contracting Officer via email at Robert.pritchard2@va.gov no later than June 29, 2021 4:00PM CST.
Standard for Acceptability: This factor is met when up to three (3) past performance questionnaires that the offeror has worked with in the past five (5) years are submitted, along with any other relevant past performance documentation reflecting acceptable performance, and are determined to be relevant relative to the subject procurement, and recent in regard to the timeframe-within the past five (5) years. The Government will evaluate the relative merits of each project listed under past performance as well as verify the information provided through direct contact, as well as other government websites. This factor will be found ACCEPTABLE if, based on the Offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the Offeror’s performance record is unknown. This factor will be found UNACCEPTABLE if, based on the Offeror’s performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.
NOTE: The past performance evaluation results is an assessment of the Offeror’s probability of meeting the minimum past performance solicitation requirements. This assessment is based on the Offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. The government may also obtain past performance information through the Past Performance Information Retrieval System (PPIRS) other sources known to the Government.
Price: The offeror shall provide pricing for the stated offer item. The Government will evaluate offers for award purposes.
The price proposal must include the S02-Attachment 4 - Price Schedule Worksheet, the signed SF 1442, with acknowledgment of any amendments, plus the Offeror’s Bid Guarantee documents.
The proposed price will be analyzed for reasonableness. It may also be analyzed for the different divisions of work to be performed, reflects a clear understanding of the requirement; and is consistent with the Offeror’s Technical Proposal. A detailed price breakdown will be required, and Offerors shall provide a detailed breakout of pricing on the Pricing Schedule worksheet provided with the solicitation.
If a detailed price breakdown is not included in the Offeror’s price proposal, the contractor may be excluded from further consideration of contract award. Pricing will be evaluated in accordance with FAR 15.4 to determine reasonableness and evaluate potential performance risks. In this context, reasonableness will be determined by comparing offered prices with the government estimate. Price will be evaluated as either reasonable or unreasonable. The Government reserves the right to cancel subject RFP and re-solicit via another mechanism should a fair and reasonable price not be achieved, or reasonableness of price cannot be determined.
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 10.8 % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
(End of Provision)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be Twenty Percent (20%) percent of the bid price or $3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Robert Pritchard Contracting Officer Hand-Carried Address:
Department of Veterans Affairs Network Contracting Office (NCO) 9 1639 Medical Center Parkway, Ste 400 Murfreesboro TN 37129 Mailing Address:
Same Address as Above
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded because of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— Monday, June 14, 2021 at 1:00pm CST
(c) Participants will meet at— Memphis VA Medical Center, Building 1A, Room F102.
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/ https://www.wdol.gov/dba.aspx#0 (End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| JUL 2016 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
| 52.215-1 |
| INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION |
| JAN 2017 |
| 52.236-28 |
| PREPARATION OF PROPOSALS—CONSTRUCTION |
| OCT 1997 |
2.9 VAAR 852.223-70 INSTRUCTIONS TO OFFERORS—SUSTAINABLE ACQUISITION PLAN (SEP 2019) Offerors shall include a Sustainable Acquisition Plan in their technical proposals. The plan must describe the approach and quality assurance mechanisms for applying FAR subpart 23.1, Sustainable Acquisition Policy and other Federal laws, regulations and Executive Orders governing sustainable acquisition. The plan shall clearly identify those products and services included in the proposal.
(End of Provision)
2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)
(a) Any protest filed by an interested party shall—
(1) Include the name, address, fax number, email and telephone number of the protester;
(2) Identify the solicitation and/or contract number;
(3) Include an original signed by the protester or the protester’s representative and at least one copy;
(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;
(5) Specifically request a ruling of the individual upon whom the protest is served;
(6) State the form of relief requested; and
(7) Provide all information establishing the timeliness of the protest.
(b) Failure to comply with the above may result in dismissal of the protest without further consideration.
(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.
(End of Provision)
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.
(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $36.5 Million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xiv…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .