01-01-21
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements
01 33 23 Shop Drawings, Product Data, and Samples
01 35 26 Safety Requirements
01 42 19 Reference Standards
01 57 19 Temporary Environmental Controls
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition
DIVISION 03 – CONCRETE
DIVISION 04 – MASONRY
DIVISION 05 – METALS
05 12 00 Structural Steel Framing
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping
DIVISION 08 - OPENINGS
DIVISION 09 – FINISHES
09 29 00 Gypsum Board
09 51 00 Acoustical Ceilings
09 65 13 Resilient Base and Accessories
09 91 00 Painting
DIVISION 10 – SPECIALTIES
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 49 00 Radiation Protection
DIVISION 14– CONVEYING EQUIPEMENT
DIVISION 21- FIRE SUPPRESSION
DIVISION 22 – PLUMBING
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC
23 31 00 HVAC Ducts and Casings
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations
26 05 19 Low-Voltage Electrical Power Conductors and Cables
26 05 26 Grounding and Bonding for Electrical Systems
26 05 33 Raceway and Boxes for Electrical Systems
26 09 23 Lighting Controls
26 27 26 Wiring Devices
26 51 00 Interior Lighting
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security
28 05 13 Conductors and Cables for Electronic Safety and
Security
28 31 00 Fire Detection and Alarm
DIVISION 31 – EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
DIVISION 33 – UTILITIES
DIVISION 34 – TRANSPORTATION
DIVISION 48 – Electrical Power Generation
07-01-15
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Mt. Home VA Medical Center, Renovate Rooms 103 & 104 Bldg. 214 PET Waiting
Area.
Drawing No. Title
G001 Cover Sheet
G101 Existing Conditions
AD101 Demolition
A101 Radiation Shielding Plan
A102 New Work Plan
S101 Framing Plan
S102 Sections & Details
- - - END - - -
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structure/materials, and furnish labor and materials and perform work for the renovation of the Quite Room and Hot Toilet/Vestibule to provide adequate radiation shielding via lead as prescribed by the
Medical Health Physicist as indicated by drawings and specifications.
B. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection.
Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
C. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: James H. Quillen VAMC, Install
Radiation Shielding for Quiet Room and Hot Toilet for Building
214. This work includes modifications to the existing area including demolition of existing structures and materials as designated. Areas of work include metal framing, electrical, HVAC, gypsum wallboard, finishes, specialty items, and other items as indicated or specified.
01 00 00 -2
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at
Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the
Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of
01 00 00 -3 project including tool boxes and parked machines and take any emergency action.
D. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted
24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for
General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center
Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the
Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of
01 00 00 -4 the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of the Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
01 00 00 -5
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. Work will be required on nights and weekends. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center
Director, COR and Contractor.
H. Building No.214 will be occupied during performance of work but immediate areas of alterations will be vacated.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical
Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Vestibule 101 work shall be completed on a weekend.
3. Room 104 and Corridor 102 work shall be completed during normal business hours, Monday – Friday 7am until 4:30pm.
I. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall always maintain a minimum temperature of 4 degrees C (40 degrees F), except as otherwise specified.
01 00 00 -6
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company
(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
J. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
K. Coordinate the work for this contract with other construction operations as directed by COR.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both to the Contracting
Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
01 00 00 -7
B. Protection: Provide the following protective measures:
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
2. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by
COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on
01 00 00 -8 adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems
(including telephone) which are not scheduled for discontinuance or abandonment.
01 00 00 -9
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain one set of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver approved completed as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on
Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense.
When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.13 RELOCATED ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all items indicated to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR.
C. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
1.14 CONSTRUCTION SIGN
A. Provide a Construction Sign if directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm
01 00 00 -10
(24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the COR.
1.15 SAFETY SIGN
A. Provide a Safety Sign if directed by COR. Face of sign shall be
19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at
1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by COR.
D. Post the number of accident free days on a daily basis.
1.16 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide daily digital photographic documentation of construction progress.
- - - E N D - - -
05-01-17
01 33 23 - 1
SECTION 01 33 23
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
PART 1 – GENERAL
1.1 DESCRIPTION
A. This specification defines the general requirements and procedures for submittals. A submittal is information submitted for VA review to establish compliance with the contract documents.
B. Detailed submittal requirements are found in the technical sections of the contract specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective technical specifications at no additional cost to the government.
C. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.
Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.
1.2 DEFINITIONS
A. Preconstruction Submittals: Submittals which are required prior to issuing contract notice to proceed or starting construction. For example, Certificates of insurance; Surety bonds; Site-specific safety plan; Construction progress schedule; Schedule of values; Submittal register; List of proposed subcontractors.
B. Shop Drawings: Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be integrated and coordinated.
C. Product Data: Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions, and brochures, which describe and illustrate size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work. Samples of warranty language when the contract requires extended product warranties.
01 33 23 - 2
D. Samples: Physical examples of materials, equipment, or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged. Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project. Field samples and mock-ups constructed to establish standards by which the ensuing work can be judged.
E. Design Data: Calculations, mix designs, analyses, or other data pertaining to a part of work.
F. Test Reports: Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work. Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
G. Certificates: Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor. The purpose is to document procedures, acceptability of methods, or personnel qualifications for a portion of the work.
H. Manufacturer's Instructions: Pre-printed material describing installation of a product, system, or material, including special notices and MSDS concerning impedances, hazards, and safety precautions.
I. Manufacturer's Field Reports: Documentation of the testing and verification actions taken by manufacturer's representative at the job site on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must indicate whether the material, product, or system has passed or failed the test.
J. Operation and Maintenance Data: Manufacturer data that is required to operate, maintain, troubleshoot, and repair equipment, including manufacturer's help, parts list, and product line documentation. This data shall be incorporated in an operations and maintenance manual.
K. Closeout Submittals: Documentation necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a phase of construction on a multi-phase contract.
1.3 SUBMITTAL SCHEDULING
A. Submittals are to be scheduled, submitted, reviewed, and approved prior to the acquisition of the material or equipment.
01 33 23 - 3
B. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow time for potential resubmittal.
C. No delay costs or time extensions will be allowed for time lost in late submittals or resubmittals.
D. All submittals are required to be approved prior to the start of the specified work activity.
1.4 SUBMITTAL PREPARATION
A. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
B. Collect required data for each specific material, product, unit of work, or system into a single submittal. Prominently mark choices, options, and portions applicable to the submittal. Partial submittals will not be accepted for expedition of construction effort. Submittal will be returned without review if incomplete.
C. If available product data is incomplete, provide Contractor-prepared documentation to supplement product data and satisfy submittal requirements.
D. All irrelevant or unnecessary data shall be removed from the submittal to facilitate accuracy and timely processing. Submittals that contain the excessive amount of irrelevant or unnecessary data will be returned with review.
E. Provide a transmittal form for each submittal with the following information:
1. Project title, location and number.
2. Construction contract number.
3. Date of the drawings and revisions.
4. Name, address, and telephone number of subcontractor, supplier, manufacturer, and any other subcontractor associated with the submittal.
5. List paragraph number of the specification section and sheet number of the contract drawings by which the submittal is required.
6. When a resubmission, add alphabetic suffix on submittal description.
For example, submittal 18 would become 18A, to indicate resubmission.
7. Product identification and location in project.
01 33 23 - 4
F. The Contractor is responsible for reviewing and certifying that all submittals are in compliance with contract requirements before submitting for VA review. Proposed deviations from the contract requirements are to be clearly identified. All deviations submitted must include a side by side comparison of item being proposed against item specified. Failure to point out deviations will result in the VA requiring removal and replacement of such work at the Contractor's expense.
G. Stamp, sign, and date each submittal transmittal form indicating action taken.
H. Stamp used by the Contractor on the submittal transmittal form to certify that the submittal meets contract requirements is to be similar to the following:
01 33 23 - 5
| CONTRACTOR |
| (Firm Name) |
| Approved |
| Approved with corrections as noted on submittal data and/or |
| attached sheets(s) |
| SIGNATURE: |
| TITLE: |
| DATE: |
1.6 SUBMITTAL FORMAT AND TRANSMISSION
A. Provide submittals in electronic format, with the exception of material samples. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer.
B. Compile the electronic submittal file as a single, complete document.
Name the electronic submittal file specifically according to its contents.
C. Electronic files must be of sufficient quality that all information is legible. Generate PDF files from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required.
01 33 23 - 6
D. E-mail electronic submittal documents smaller than 5MB in size to e-mail addresses as directed by the Contracting Officer.
E. Provide electronic documents over 5MB through an electronic FTP file sharing system. Confirm that the electronic FTP file sharing system can be accessed from the VA computer network. The Contractor is responsible for setting up, providing, and maintaining the electronic
FTP file sharing system for the construction contract period of performance.
F. Provide hard copies of submittals when requested by the Contracting
Officer. Up to 3 additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the VA.
1.7 SAMPLES
A. Submit two sets of physical samples showing range of variation, for each required item.
B. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified.
C. When color, texture, or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
D. Before submitting samples, the Contractor is to ensure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
E. The VA reserves the right to disapprove any material or equipment which previously has proven unsatisfactory in service.
F. Physical samples supplied maybe requested back for use in the project after reviewed and approved.
1.8 OPERATION AND MAINTENANCE DATA
A. Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.
B. In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.
01 33 23 - 7
1.9 TEST REPORTS
SRE may require specific test after work has been installed or completed which could require contractor to repair test area at no additional cost to contract.
1.10 VA REVIEW OF SUBMITTALS AND RFIS
A. The VA will review all submittals for compliance with the technical requirements of the contract documents. The Architect-Engineer for this project will assist the VA in reviewing all submittals and determining contractual compliance. Review will be only for conformance with the applicable codes, standards and contract requirements.
B. Period of review for submittals begins when the VA COR receives submittal from the Contractor.
C. Period of review for each resubmittal is the same as for initial submittal.
D. VA review period is 15 working days for submittals.
E. VA review period is 10 working days for RFIs.
F. The VA will return submittals to the Contractor with the following notations:
1. "Approved": authorizes the Contractor to proceed with the work covered.
2. "Approved as noted": authorizes the Contractor to proceed with the work covered provided the Contractor incorporates the noted comments and makes the noted corrections.
3. "Disapproved, revise and resubmit": indicates noncompliance with the contract requirements or that submittal is incomplete. Resubmit with appropriate changes and corrections. No work shall proceed for this item until resubmittal is approved.
4. "Not reviewed": indicates submittal does not have evidence of being reviewed and approved by Contractor or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals after taking appropriate action.
1.11 APPROVED SUBMITTALS
A. The VA approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.
01 33 23 - 8
B. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.
Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.
C. After submittals have been approved, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
D. Retain a copy of all approved submittals at project site, including approved samples.
1.12 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
07-01-20
01 35 26 -1
SECTION 01 35 26
SAFETY REQUIREMENTS
TABLE OF CONTENTS
1.1 APPLICABLE PUBLICATIONS
1.2 DEFINITIONS
1.3 REGULATORY REQUIREMENTS
1.4 ACCIDENT PREVENTION PLAN (APP)
1.5 ACTIVITY HAZARD ANALYSES (AHAs)
1.6 PRECONSTRUCTION CONFERENCE
1.7 “SITE SAFETY AND HEALTH OFFICER” and “COMPETENT PERSON”
1.8 TRAINING
1.9 INSPECTIONS
1.10 ACCIDENTS, OSHA 300 LOGS, AND MAN-HOURS
1.11 PERSONAL PROTECTIVE EQUIPMENT (PPE)
1.12 INFECTION CONTROL
1.13 TUBERCULOSIS SCREENING
1.14 FIRE SAFETY
1.15 ELECTRICAL
1.16 FALL PROTECTION
1.17 SCAFFOLDS AND OTHER WORK PLATFORMS
1.18 WELDING AND CUTTING
1.19 LADDERS
1.20 FLOOR & WALL OPENINGS
01 35 26 -2
SECTION 01 35 26
SAFETY REQUIREMENTS
1.1 APPLICABLE PUBLICATIONS:
A. Latest publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
B. American Society of Safety Engineers (ASSE):
A10.1-2011 ..........Pre-Project & Pre-Task Safety and Health
Planning
A10.34-2012 .........Protection of the Public on or Adjacent to
Construction Sites
A10.38-2013 .........Basic Elements of an Employer’s Program to
Provide a Safe and Healthful Work Environment
American National Standard Construction and
Demolition Operations
C. American Society for Testing and Materials (ASTM):
E84-2013 ............Surface Burning Characteristics of Building
Materials
D. The Facilities Guidelines Institute (FGI):
FGI Guidelines-2010Guidelines for Design and Construction of
Healthcare Facilities
E. National Fire Protection Association (NFPA):
10-2018 .............Standard for Portable Fire Extinguishers
30-2018 .............Flammable and Combustible Liquids Code
51B-2019 ............Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2020 .............National Electrical Code
70B-2019 ............Recommended Practice for Electrical Equipment
Maintenance
70E-2018 ...........Standard for Electrical Safety in the Workplace
01 35 26 -3
99-2018 .............Health Care Facilities Code
241-2019 ............Standard for Safeguarding Construction, Alteration, and Demolition Operations
F. The Joint Commission (TJC)
TJC Manual .........Comprehensive Accreditation and Certification
Manual
G. U.S. Nuclear Regulatory Commission
10 CFR 20 ..........Standards for Protection Against Radiation
H. U.S. Occupational Safety and Health Administration (OSHA):
29 CFR 1910 ........Safety and Health Regulations for General
Industry
29 CFR 1926 ........Safety and Health Regulations for Construction
Industry
I. VHA Directive 2005-007
1.2 DEFINITIONS:
A. Critical Lift. A lift with the hoisted load exceeding 75% of the crane’s maximum capacity; lifts made out of the view of the operator
(blind picks); lifts involving two or more cranes; personnel being hoisted; and special hazards such as lifts over occupied facilities, loads lifted close to power-lines, and lifts in high winds or where other adverse environmental conditions exist; and any lift which the crane operator believes is critical.
B. OSHA “Competent Person” (CP). One who is capable of identifying existing and predictable hazards in the surroundings and working conditions which are unsanitary, hazardous or dangerous to employees, and who has the authorization to take prompt corrective measures to eliminate them (see 29
CFR 1926.32(f)).
C. "Qualified Person" means one who, by possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training and experience, has successfully demonstrated his ability to solve or resolve problems relating to the subject matter, the work, or the project.
01 35 26 -4
D. High Visibility Accident. Any mishap which may generate publicity or high visibility.
E. Accident/Incident Criticality Categories:
1. No impact – near miss incidents that should be investigated but are not required to be reported to the VA;
2. Minor incident/impact – incidents that require first aid or result in minor equipment damage (less than $5000). These incidents must be investigated but are not required to be reported to the VA;
3. Moderate incident/impact – Any work-related injury or illness that results in:
a. Days away from work (any time lost after day of injury/illness onset);
b. Restricted work;
c. Transfer to another job;
d. Medical treatment beyond first aid;
e. Loss of consciousness;
4. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (5) above or,
5. ny incident that leads to major equipment damage (greater than
$5000).
F. These incidents must be investigated and are required to be reported to the VA;
1 Major incident/impact – Any mishap that leads to fatalities, hospitalizations, amputations, and losses of an eye as a result of contractors’ activities. Or any incident which leads to major property damage (greater than $20,000) and/or may generate publicity or high visibility. These incidents must be investigated and are required to be reported to the VA as soon as practical, but not later than 2 hours after the incident.
01 35 26 -5
G. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by physician or registered personnel.
1.3 REGULATORY REQUIREMENTS:
A. In addition to the detailed requirements included in the provisions of this contract, comply with 29 CFR 1926, comply with 29 CFR 1910 as incorporated by reference within 29 CFR 1926, comply with ASSE A10.34, and all applicable [federal, state, and local] laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern except with specific approval and acceptance by the
Facility Safety Officer or Contracting Officer Representative.
1.4 ACCIDENT PREVENTION PLAN (APP):
A. The APP (aka Construction Safety & Health Plan) shall interface with the Contractor's overall safety and health program. Include any portions of the Contractor's overall safety and health program referenced in the APP in the applicable APP element and ensure it is site-specific. The Government considers the Prime Contractor to be the
"controlling authority" for all worksite safety and health of each subcontractor(s). Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
B. The APP shall be prepared as follows:
1. Written in English by a qualified person who is employed by the
Prime Contractor articulating the specific work and hazards pertaining to the contract (model language can be found in ASSE
A10.33). Specifically articulating the safety requirements found within these VA contract safety specifications.
01 35 26 -6
2. Address both the Prime Contractors and the subcontractors work operations.
3. State measures to be taken to control hazards associated with materials, services, or equipment provided by suppliers.
4. Address all the elements/sub-elements and in order as follows:
a. SIGNATURE SHEET. Title, signature, and phone number of the following:
1) Plan preparer (Qualified Person such as corporate safety staff person or contracted Certified Safety Professional with construction safety experience);
2) Plan approver (company/corporate officers authorized to obligate the company);
3) Plan concurrence (e.g., Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional). Provide concurrence of other applicable corporate and project personnel (Contractor).
b. BACKGROUND INFORMATION. List the following:
1) Contractor;
2) Contract number;
3) Project name;
4) Brief project description, description of work to be performed, and location; phases of work anticipated (these will require an AHA).
c. STATEMENT OF SAFETY AND HEALTH POLICY. Provide a copy of current corporate/company Safety and Health Policy Statement, detailing commitment to providing a safe and healthful workplace for all employees. The Contractor’s written safety program goals, objectives, and accident experience goals for this contract should be provided.
d. RESPONSIBILITIES AND LINES OF AUTHORITIES. Provide the following:
01 35 26 -7
1) A statement of the employer’s ultimate responsibility for the implementation of his SOH program;
2) Identification and accountability of personnel responsible for safety at both corporate and project level. Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes.
3) The names of Competent and/or Qualified Person(s) and proof of competency/qualification to meet specific OSHA
Competent/Qualified Person(s) requirements must be attached.;
4) Requirements that no work shall be performed unless a designated competent person is present on the job site;
5) Requirements for pre-task Activity Hazard Analysis (AHAs);
6) Lines of authority;
7) Policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements) should be identified;
e. SUBCONTRACTORS AND SUPPLIERS. If applicable, provide procedures for coordinating SOH activities with other employers on the job site:
1) Identification of subcontractors and suppliers (if known);
2) Safety responsibilities of subcontractors and suppliers.
f. TRAINING.
1) Site-specific SOH orientation training at the time of initial hire or assignment to the project for every employee before working on the project site is required.
2) Mandatory training and certifications that are applicable to this project (e.g., explosive actuated tools, crane operator, rigger, crane signal person, fall protection, electrical lockout/NFPA 70E, machine/equipment lockout, confined space, etc…) and any requirements for periodic retraining/recertification are required.
01 35 26 -8
3) Procedures for ongoing safety and health training for supervisors and employees shall be established to address changes in site hazards/conditions.
4) OSHA 10-hour training is required for all workers on site and the OSHA 30-hour training is required for Trade Competent
Persons (CPs)
g. SAFETY AND HEALTH INSPECTIONS.
1) Specific assignment of responsibilities for a minimum daily job site safety and health inspection during periods of work activity: Who will conduct (e.g., “Site Safety and Health
CP”), proof of inspector’s training/qualifications, when inspections will be conducted, procedures for documentation, deficiency tracking system, and follow-up procedures.
2) Any external inspections/certifications that may be required
(e.g., contracted CSP or CSHT)
h. ACCIDENT/INCIDENT INVESTIGATION & REPORTING. The Contractor shall conduct mishap investigations of all Moderate and Major as well as all High Visibility Incidents. The APP shall include accident/incident investigation procedure and identify person(s) responsible to provide the following to the Facility Safety
Officer or Contracting Officer Representative:
1) Exposure data (man-hours worked);
2) Accident investigationreports;
3) Project site injury and illness logs.
i. PLANS (PROGRAMS, PROCEDURES) REQUIRED. Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable occupational, patient, and public safety risks in site-specific compliance and accident prevention plans. These Plans shall include but are not be limited to procedures for addressing the risks associates with the following:
1) Emergency response;
2) Contingency for severe weather;
01 35 26 -9
3) Fire Prevention;
4) Medical Support;
5) Posting of emergency telephone numbers;
6) Prevention of alcohol and drug abuse;
7) Site sanitation (housekeeping, drinking water, toilets);
8) Night operations and lighting;
9) Hazard communication program;
10) Welding/Cutting “Hot” work;
11) Electrical Safe Work Practices (Electrical LOTO/NFPA 70E);
12) General Electrical Safety;
13) Hazardous energy control (Machine LOTO);
14) Site-Specific Fall Protection & Prevention;
15) Excavation/trenching;
16) Asbestos abatement;
17) Lead abatement;
18) Crane Critical lift;
19) Respiratory protection;
20) Health hazard control program;
21) Radiation Safety Program;
22) Abrasive blasting;
23) Heat/Cold Stress Monitoring;
24) Crystalline Silica Monitoring (Assessment);
25) Demolition plan (to include engineering survey);
26) Formwork and shoring erection and removal;
27) PreCast Concrete;
28) Public (Mandatory compliance with ANSI/ASSE A10.34-2012).
01 35 26 -10
C. Submit the APP to the Facility Safety Officer or Contracting Officer
Representative (COR) for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP.
D. Once accepted by the Facility Safety Officer Contracting Officer
Representative, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted
APP will be cause for stopping of work, at the discretion of the
Contracting Officer in accordance with FAR Clause 52.236-13, Accident
Prevention, until the matter has been rectified.
E. Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the Facility Safety Officer or Contracting
Officer Representative. Should any severe hazard exposure, i.e.
imminent danger, become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard.
Notify the Contracting Officer within 24 hours of discovery.
Eliminate/remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions to safeguard onsite personnel, visitors, the public and the environment.
1.5 ACTIVITY HAZARD ANALYSES (AHAS):
A. AHAs are also known as Job Hazard Analyses, Job Safety Analyses, and
Activity Safety Analyses. Before beginning each work activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or sub-contractor is to perform the work, the Contractor(s) performing that work activity shall prepare an AHA (Example electronic AHA forms can be found on the US
Army Corps of Engineers web site)
B. AHAs shall define the activities being performed and identify the work sequences, the specific anticipated hazards, site conditions, equipment, materials, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level of risk.
C. Work shall not begin until the AHA for the work activity has been accepted by the Facility Safety Officer or Contracting Officer
Representative and discussed with all engaged in the activity, 01 35 26 -11 including the Contractor, subcontractor(s), and Government on-site representatives at preparatory and initial control phase meetings.
1. The names of the Competent/Qualified Person(s) required for a particular activity (for example, excavations, scaffolding, fall protection, other activities as specified by OSHA and/or other State and Local agencies) shall be identified and included in the AHA.
Certification of their competency/qualification shall be submitted to the Government Designated Authority (GDA) for acceptance prior to the start of that work activity.
2. The AHA shall be reviewed and modified as necessary to address changing site conditions, operations, or change of competent/qualified person(s).
a. If more than one Competent/Qualified Person is used on the AHA activity, a list of names shall be submitted as an attachment to the AHA. Those listed must be Competent/Qualified for the type of work involved in the AHA and familiar with current site safety issues.
b. If a new Competent/Qualified Person (not on the original list) is added, the list shall be updated (an administrative action not requiring an updated AHA). The new person shall acknowledge in writing that he or she has reviewed the AHA and is familiar with current site safety issues.
3. Submit AHAs to the Facility Safety Officer or Contracting Officer
Representative for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND
SAMPLES for review at least 15 calendar days prior to the start of each phase. Subsequent AHAs as shall be formatted as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.
4. The AHA list will be reviewed periodically (at least monthly) at the
Contractor supervisory safety meeting and updated as necessary when procedures, scheduling, or hazards change.
5. Develop the activity hazard analyses using the project schedule as the basis for the activities performed.