S06 - AMENDMENT - 0002.docx
DOCX document 151 KB Posted
- Solicitation number
- 36C24827Q0084
About this file
This is an Amendment No. 0002 to Solicitation 36C24827Q0084 issued by the Department of Veterans Affairs Network Contracting Office 8 for the C.W. Bill Young VA Medical Center in Bay Pines, Florida. The amendment extends the question deadline from November 10, 2026 at 2:00 PM EST to November 13, 2026 at 2:00 PM EST, and extends the Request for Quote close date from November 13, 2026 at 2:00 PM EST to November 18, 2026 at 2:00 PM EST. The amendment provides answers to vendor questions, revised Statement of Work, and blueprints for the project.
The project scope, titled Project Lighthouse, requires installation of a C-CURE 9000 access control system upgrade on the third floor of Building 111. Contractors must supply two complete LifeSafety Power E12S Software House unified controller assemblies containing one GCM and four ACMs each, migrate 46 existing reader positions from three legacy controllers, install 13 new card-only readers at nine openings using OSDP Secure Channel protocol with Identiv uTrust as the preferred basis of design, provide four complete new Grade 1 strike/door position switch/request-to-exit hardware packages, install composite access control cabling and pathways, supply six total FPO250 power supplies (three per assembly) with supervised battery backup for minimum four-hour standby plus fifteen minutes of operation, and provide all labor, engineering, integration, testing, and closeout documentation. The work must be completed within 120 calendar days after notice to proceed, with routine work performed 7:30 AM to 4:30 PM Eastern Time Monday through Friday. Contractors must hold current manufacturer authorization for CCURE 9000 installation, employ a named programmer with AC9001 CCURE 9000 Installer/Maintainer certification, submit a comprehensive work plan and H1 design package within 10 business days of notice to proceed, obtain written VA Engineering technical acceptance before ordering materials, and provide 12 months warranty from final acceptance. The NAICS code is 561621 (Security System Services) with a $25 million small business size standard, and all vendors must be registered in SAM and provide UEI and SDVOSB certification information with their quotes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S06 - AMENDMENT 0003.docx | DOCX document | |
| Building_111_Phase_1_Technical_Scope_Schedule.docx | DOCX document | |
| P09_Updated_SOW.docx | DOCX document | |
| 3B Side.png | PNG image | |
| 111-3A BUILDING 111 THIRD FLOOR PLAN.pdf | ||
| BLUEPRINTS.docx | DOCX document | |
| 3A side.png | PNG image | |
| 36C24827Q0084.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
11-10-2026
516-27-1-5105-0102
36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8)
10,000 Bay Pines Blvd Bay Pines FL 33744
36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) C.W. Bill Young VA Medical Center 10000 Bay Pines Blvd.
Bay Pines FL 33744 To all Offerors/Bidders
36C24827Q0084 11-04-2026
X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 11-18-2026 2:00pm EST
516-3670162-5105-854100-2580 010050192 x
A- The purpose of this amendment is to provide answers to questions received. See continuation page.
B- Provide a revised SOW.
C- Provide blueprints as requested.
D- Extend questions due date from 11/10/2026 at 2:00pm EST to 11/13/2026 at 2:00pm EST.
E- Extend RFQ close date from 11/13/2026 at 2:00pm EST to 11/18/2026 at 2:00pm EST.
William Penhallegon Contracting Officer
CONTINUATION PAGE
Questions and Answers
1. Could you please provide the blueprints referenced in the scope, any available floor plans, and the common door/reader schedule showing the installation locations if possible please. See attachment.
2. The common door/reader schedule identifying locations, hardware requirements, and final quantities.
The scope is 13 new card-only reader positions at nine openings. Preferred readers are Identiv uTrust with terminal-block connections, with narrow mullion readers at 3B-149 and 3A-171. All new readers use OSDP.
The controller scope is two fully equipped 32-reader iSTAR Ultra G2 assemblies, with consolidation authorized. Migrate 46 existing reader positions and add 13 new positions, for 59 active positions and five spare positions total.
The four complete new hardware packages are at 3B-149, 3B-165, 3A-171 and 3A-155. REX is required at those four openings and 3A-107. No REX is included at the four dual-reader openings.
SPR-76 and first-floor door 1B-178 are excluded. The attachment schedule provides the corrected quantities and hardware assignments for the solicitation amendment.
Revised SOW Statement of Work C CURE upgrades for Project Lighthouse Draft for review Revision 3 10 November 2026 36C24827Q0084 Provide two complete 32-reader iSTAR Ultra G2 assemblies, replace all three existing controllers and migrate their 46 existing reader positions, and install 13 new card-only readers at nine openings. The total is 59 active reader positions and five spare positions across 64 fully provisioned positions. Include four complete new-door hardware packages, composite cable and contractor-provided pathways for new work, DPS, and documented ward and life-safety operation. Identiv uTrust with terminal-block connections is the preferred basis of design; compliant APL-listed compatible alternatives remain acceptable. Equip and wire the 13 new readers for future High Assurance (HA) activation, while commissioning them in the existing VA-approved card-only access mode. New-reader certificate authentication, HA enrollment/validation services and HA licensing are outside this phase.
Technical requirements and the common door schedule are defined below. This draft is for review and is not an issued solicitation amendment. Contractor verifies actual conditions and submits supported implementation details before ordering. The issued solicitation and written CO amendments establish contractual scope and final priced quantities.
1 Scope quantities and substitutions R01 Complete integrated scope. Provide all labor, supervision, engineering detailing, materials, delivery, staging, pathways, composite cabling, removal, installation, programming, integration, testing and closeout for Phase 1 on the third floor of Building 111 at C.W. Bill Young VA Medical Center. Install 13 new card-only readers at the nine openings in Attachment 1, including four complete new lock/DPS/REX packages at 3B-149, 3B-165, 3A-171 and 3A-155. Replace all three existing controller assemblies and migrate their 46 existing reader positions and associated functions to two fully provisioned 32-reader iSTAR Ultra G2 assemblies. None of the three legacy controllers shall remain in service as an active, standby or expansion controller. Compatible existing field devices and wiring may remain as specified under R22. Provide 64 positions total, with 59 active and five spare, and integrate with the existing VISN 8 C•CURE system. Future HA readiness for the 13 new readers is defined in R27; live HA activation is not part of this phase. Preserve any established authentication functions on the migrated readers. SPR-76 and first-floor door 1B-178 are excluded.
R02 Phase 1 quantities and pre bid verification. Base pricing includes 13 new reader positions at nine openings: five single-reader openings and four dual-reader openings. Each side of a dual-reader opening consumes one reader position. The four complete new-door hardware packages are included within this scope. Attachment 1 identifies each opening separately; the corridor connection 3B-C3-26 / 3A-C3-25 is one opening. Migrate 46 existing reader positions, for 59 active positions total. The CO shall issue the same schedule, marked locations and any scope changes to all bidders before final quotations. Bidders shall attend announced site access and identify discrepancies; each bidder is not required to create a separate engineered door schedule. After award, the contractor verifies measurements and develops detailed implementation drawings before ordering. Report scope-changing discrepancies for written resolution before proceeding.
R03 Controlled scope and substitutions. Identiv uTrust Series card-only readers with terminal-block connections are the preferred Bay Pines basis of design. Any currently GSA APL-listed PACS reader meeting the stated C•CURE compatibility, current card-only operation and future HA readiness under R27, OSDP Secure Channel, form-factor and functional requirements is acceptable; do not reject an otherwise compliant alternative solely for brand. Submit the exact model, firmware, APL approval letter and applicable tested-solution restrictions, compatibility evidence and equal-performance comparison with the quotation. VA Engineering reviews technical compliance; only the CO authorizes contractual substitutions, quantity changes, price/time changes or waiver of a requirement. After award, obtain written technical acceptance and any necessary CO action before ordering a changed configuration.
2 Contractor qualifications R04 Manufacturer authorization. The prime or identified specialist subcontractor performing C•CURE work shall hold current manufacturer authorization applicable to installation, configuration and support of the offered C•CURE 9000 system. Submit manufacturer-verifiable authorization, scope, limitations, support entitlement and verification contact. Maintain authorization during specialized work and warranty support. A reseller invoice alone is insufficient.
R05 Named programmer and commissioning lead. Identify actual programming and commissioning personnel, employer, role, onsite tasks and qualifications. The lead C•CURE programmer shall hold current AC9001 C•CURE 9000 Installer/Maintainer certification or a manufacturer-confirmed equivalent appropriate to the installed release, together with documented iSTAR Ultra G2 installation/configuration training. Submit certificates, issue dates, status and manufacturer confirmation where applicability is unclear. Qualified personnel shall personally execute specialized work; supervision or borrowed credentials alone does not satisfy this requirement.
R06 High Assurance readiness competence. Identify the personnel responsible for the future-HA readiness submittal. Demonstrate their competence with the proposed C•CURE, iSTAR Ultra G2 and reader combination through relevant manufacturer training, manufacturer-confirmed equivalent competence, or verifiable comparable installation work supported by the proposed manufacturer-backed method. For personnel actually migrating, configuring or regression-testing an existing HA function, provide AC9202 C•CURE 9000 High Assurance with Innometriks training or a manufacturer-confirmed equivalent applicable to that work. Live HA enrollment or certificate-validation commissioning for the 13 new readers is not required. Do not require an unrelated HA integration reference or an unsupported separately named HA installation certification. R04, R05 and R07 remain applicable to the work performed.
R07 Specialist skills and subcontractors. Demonstrate assigned staff competence in OSDP Secure Channel key provisioning and diagnostics, supported integrated power/lock-control assemblies, load calculations and fault isolation through training records or comparable project records and the proposed method. If MAS/SAS architecture itself is modified, the responsible specialist shall hold AC9444 Enterprise Architecture certification or manufacturer-confirmed equivalent; ordinary door programming alone does not trigger that condition. Qualified approved subcontractors may satisfy specialist requirements. Replace personnel only with equally qualified staff accepted before specialized work.
3 Work plan and hold points R08 Work plan timing. Within 10 business days after notice to proceed, submit the complete work plan and H1 design package. Within 5 business days of receiving VA comments, submit a correction or a documented corrective schedule to the COR. Allow 10 business days for each VA technical review cycle in the proposed schedule. These periods do not guarantee VA approval or change the contract completion date. Identify delays promptly to the CO.
R09 Procurement hold point H1. Do not order configuration-dependent materials or start installation until the COR transmits written VA Engineering technical acceptance of the complete H1 package and necessary CO authorizations are issued. Submit named staff/authorization evidence, complete exact BOM, dimensioned layouts for both complete cabinet assemblies and any required listed battery enclosures, with manufacturer mounting and listing support, common issued and contractor field-verified door/reader schedule, controller/port/I/O allocation identifying all 46 migrated and 13 new reader positions and five spare positions, point-to-point diagrams and contractor-surveyed composite cable/pathway routes, power/battery calculations for 32-reader capacity per assembly and the actual 59-position operating allocation, existing Phase 1 entitlement verification, C•CURE compatibility and the future-HA readiness evidence under R27, network integration, ward/life-safety door sequences, outage/rollback plan and T01–T18 procedures. Contractor shall supply these engineering details to implement the defined requirements. Silence is not approval.
R10 Field verification. Before H1, verify the specified C•CURE 9000 3.10.1 CU02 baseline and any later VA-authorized release actually in use, patch level, SAS/MAS relationship, controller and reader firmware, any existing authentication/HA functions that must be preserved, 200-bit format mapping and licenses required for Phase 1. Record the VA-approved current card-only mode for the 13 new readers; this verification does not authorize HA activation. Use signal closet 3A-107 as the designated location for both new controller assemblies, and measure the equipment area, wall anchorage, both cabinet door swings and service clearances; trace all affected reader/lock/DPS/REX circuits, network and AC sources, cable routes, lock loads, fire interfaces and ward operation. Use the final marked door-location drawings provided to the CO. Cable-route drawings are not Government-furnished; survey actual routes and provide the dimensioned pathway and cable-routing drawings with H1 and final as-builts. Resolve manufacturer compatibility and ordinary fit details as contractor design obligations; promptly report concealed conditions or a scope-changing conflict to the CO before proceeding. Do not assume a software upgrade is authorized. Confirm the door/frame supply scope and the original heading “UPS #1” during pre-bid site access; the CO shall publish common clarification before final quotations. Do not infer an additional UPS procurement requirement from that heading.
4 Cabinet and controller installation R11 Consolidated equipment cabinets. Provide two consolidated access-control cabinet assemblies, each containing one GCM, four ACMs, required auxiliary modules, DC supplies/chargers, lock-power distribution and relays, protective devices, with an associated battery system. Battery placement shall follow the manufacturer-supported listed enclosure/layout accepted under H1. All three existing controller assemblies shall be replaced and their functions consolidated into these two new assemblies. The basis of design for each is a LifeSafety Power E12S Software House unified enclosure, nominal 48 H × 36 W × 8 D inches, with the exact current manufacturer-supported G2 backplate and full internal assembly. Separate control, power or relay boxes beyond the two specified assemblies require documented technical necessity, written VA Engineering concurrence and any required CO authorization. Provide manufacturer-supported listed battery enclosure(s) where the calculated battery system cannot be accommodated within the E12S listing, fit and service requirements; submit their location, mounting, connections and clearances under H1 before ordering. Do not reduce either assembly’s 32-reader capacity or omit batteries to obtain fit. Field readers, lock hardware and building fire equipment remain at their required locations. Install both new controller assemblies in signal closet 3A-107, using the final marked door-location drawings provided to the CO. Record drawing identifiers and revisions in H1. Verify fit, anchorage, service access and manufacturer location restrictions, including patient-care-area restrictions. Refer conflicts for technical review before installation.
R12 Supported assembly and fit. Install one Software House GSTAR-GCM and four GSTAR-ACM boards in each assembly, for two GCMs and eight ACMs total, using the manufacturer-supported unified mounting arrangement, standoffs, brackets, harnesses, partitions and service clearances. All four ACMs in each assembly shall be installed, powered, recognized by their GCM and available at Phase 1 acceptance; an empty board position does not comply. Obtain written enclosure/assembly manufacturer confirmation of the exact G2 board revisions and the entire power/battery arrangement, including any separate listed battery enclosure. Do not assume the calculated batteries fit in an E12S enclosure. No improvised stacking, adhesive-only mounting or listing-defeating field alteration is permitted. E12M Mercury backplates and smaller sixteen-reader assemblies do not satisfy this project.
R13 Dimensioned serviceable layout. For each controller assembly and any separate battery enclosure, show cabinet H/W/D, wall footprint, door swing, conduit entries, mounting surface/anchors, loaded weight, battery locations and removal paths, AC/DC separation, required working space, component clearances, wire duct and ventilation. Maintain each manufacturer’s thermal, electrical and service clearances; terminals and fuses shall remain accessible with the assembly installed. Do not place a cabinet where service obstructs required egress or equipment working space.
R14 Safety and listing. Comply with NFPA 70, NFPA 101, NFPA 80, applicable accessibility, VA installation/safety requirements and manufacturer/listing conditions in the editions governing this facility and project. Contractor shall identify those editions and applicable door-locking provisions in H1 for VA fire-safety review; publication of a newer edition alone does not establish its adoption. Provide applicable UL 294 access-control/power listing evidence and listed fire-rated hardware where required. Maintain required AC/DC and power-limited/non-power-limited separation, bonding and clearances. A cabinet or component listing alone does not validate an altered assembly. Refer conflicts to VA fire safety/AHJ before installation; ward policy cannot waive life-safety obligations.
R15 Wiring quality and labels. Provide durable machine-printed labels at both ends of every cable and conductor group identifying door, controller, module, port, input/output and power circuit. Label fuses, disconnects, voltages, battery polarity and fire interface. Use protected entries, strain relief, manufacturer-compliant terminations, bend radii, shielding/grounding and organized service loops. Place supervision resistors at monitored field devices as prescribed; do not defeat field supervision at the panel. Document all terminal numbers and interconnections.
5 Power and battery backup R16 Power supply design. Provide three manufacturer-supported LifeSafety Power FPO250 supplies in each E12S cabinet: one 12 VDC logic/reader supply and two separate 24 VDC lock-power groups, for six supplies total. Submit manufacturer confirmation of both complete assemblies. Provide 32-reader power capacity per assembly with minimum design allowances of 0.25 A at 12 VDC per reader and 0.50 A at 24 VDC per lock-output position, using actual device loads when higher, plus all controller, auxiliary, monitoring and charger demand. These are load-sizing minimums, not measured device currents or a requirement for 64 physical door locks. Calculate normal, worst simultaneous, inrush, voltage drop, branch limits, charging, thermal and applicable listing derating for each supply and each complete assembly. Do not parallel outputs without manufacturer support. Do not reduce the three-supply-per-assembly requirement or capacity to resolve a shortfall; submit any incompatibility or fit conflict for written technical review before ordering.
R17 Protected lock outputs. Provide 32 individually controlled and protected lock-output positions per assembly, 64 total, using supported G2 ACM wet/dry outputs and integrated supply/distribution arrangements. Each assembly’s 32 primary lock-output positions are distinct from auxiliary relay outputs. Use integrated onboard protection/relays where adequate; add only manufacturer-required supported distribution/relays inside the associated cabinet. Rate contacts and protection for actual voltage, steady/inrush and inductive loading and use required suppression. For each assembly, map its two 24 VDC supplies to defined branch groups; do not assume aggregate current is available on every branch or bus. Preserve hardware fire-interlock behavior and separation of lock and logic power.
R18 Battery sizing and accommodation. Provide appropriately configured supervised batteries for each supply in a manufacturer-supported listed enclosure arrangement. Contractor shall calculate capacity from the manufacturer’s required load basis, discharge curves, end voltage, aging/temperature derating, conversion losses and charger/recharge limits. Provide at least four hours of battery standby, followed by fifteen minutes of required access-control and lock operation. Use the full-load basis required by the applicable manufacturer instructions and listing, not less than the assigned approved worst-case installed load; provide any greater duration required by governing life-safety requirements. Collectively, the batteries shall support all 46 migrated and 13 new reader positions with their associated loads and all eight ACMs across both assemblies. The building UPS does not reduce or replace this local battery requirement. Submit load calculations and a dimensioned, manufacturer-supported listed battery layout under H1; use appropriate listed battery enclosure(s) where necessary rather than assuming the required batteries fit inside E12S cabinets. Maintain required ward and egress behavior. Use new batteries within manufacturer date/shelf-life limits, fully charged before testing. Demonstrate service/removal access; do not add series battery Ah. Prove runtime by witnessed full-duration T09 testing. During testing and recovery maintain approved temporary protection. Restore required standby capacity through recharge or equivalent fully charged replacement batteries, verify normal charging and no battery faults, and document restoration before final acceptance. Calculations or nameplate life alone do not prove runtime or guarantee service life.
R19 Fault supervision. Report cabinet tamper and manufacturer-supported AC failure, supply/system fault, low-battery and battery-disconnect conditions to the existing C•CURE system. Use supported contacts/interfaces and supervised inputs with clear event and restoration text. Manufacturer-supported combined fault alarms are acceptable when the point schedule clearly identifies every represented condition and any limitations. Do not require separate alarms for conditions combined by the supported manufacturer interface. Include required fire-interface monitoring. Safely demonstrate supported fault and restoration reporting at acceptance.
6 Equipment and capacity R20 Equipment reconciliation. Furnish Attachment 2 equipment: two GCMs, eight ACMs, two complete E12S unified controller/power assemblies with manufacturer-supported listed battery systems, 13 new card-only readers at nine openings, four new complete-door packages, required DPS/REX, existing VA-provided enterprise entitlements for current operation, composite cable and contractor-provided pathways. Replace all three existing controller assemblies, migrate their 46 existing reader positions, and preserve all associated required supported functions. Reconcile the issued equipment schedule and retained equipment in the H1 BOM. The historical list of fourteen G2-RM-4E boards and two ambiguous OSDP 18 modules is not a mandatory new-purchase quantity. Use onboard ACM functions for new work. Retain compatible field devices and wiring as specified under R22, not legacy controller assemblies; furnish additional in-cabinet modules only for a documented supported point/function need. Obtain written technical acceptance before ordering such modules and mount them within the associated specified assembly; do not omit required functions or add an unapproved external enclosure.
R21 Reader and controller capacity. Provide two 32-reader assemblies, each with one GSTAR-GCM and four eight-reader GSTAR-ACM boards, all installed, powered, recognized and functional at acceptance. The total is 64 logical wired-reader positions. Provide manufacturer-backed confirmation of this installed capacity in the Phase 1 operating configuration. Provide separate manufacturer-backed evidence of the specified future 32-reader HA capacity per assembly, identifying the exact supported configuration and deferred software, licenses, services and other dependencies under R27. Ordinary reader capacity alone does not prove HA capability. Live HA operation at 32 readers per assembly is not a Phase 1 acceptance requirement. This capacity requirement does not mandate replacement or protocol conversion of the 46 existing readers. Refer any unsupported installed or future HA capacity for VA technical review and required CO resolution before ordering; do not reduce the specified capacity without written authorization. Allocate 46 migrated and 13 new reader positions, for 59 active and five spare positions total. No assembly may exceed its 32-reader limit. Entry/exit readers consume separate positions; document physical openings, actual onboard inputs, primary lock outputs and auxiliary outputs without double-counting.
R22 Door and input modules. Use centralized home-run wiring to ACM ports and supervised I/O/lock outputs for the 13 new readers at the nine scheduled openings. Provide one new OSDP reader per dedicated RS-485 port; no mixed RM/Wiegand segment or undocumented daisy-chain is permitted on a new OSDP link. For the 46 migrated existing reader positions, retain manufacturer-supported existing reader protocols, compatible field devices and serviceable field wiring while preserving required functions; migration does not require blanket reader replacement or OSDP conversion. Remove all three legacy controller assemblies from service after successful migration; no legacy controller hardware is retained in service. Document supported field-interface requirements, compatibility, termination changes and every controller/port/I/O assignment at H1. Allocate the actual available inputs and primary/auxiliary outputs without double-counting. Do not purchase historical RM-4E or OSDP-I8 quantities by default. If an additional module is needed, identify its required points, manufacturer support and mounting inside the associated assembly.
R23 Reader selection and door hardware. Furnish 13 new card-only readers with terminal-block connections, preferably Identiv uTrust Series, or acceptable APL-listed compatible readers under R03. Provide narrow mullion-style readers at 3B-149 and 3A-171; the remaining 11 readers shall fit the scheduled door and mounting conditions. Submit exact model, hardware/firmware, current approval, C•CURE compatibility and future-HA readiness evidence under R27 for the offered form factor; do not assume that a wall or keypad model establishes mullion compatibility. All 13 new readers shall use OSDP Secure Channel and be installed, configured and accepted in place, not delivered as loose spares. Commission the 13 new readers in the VA-approved current card-only mode under R27. No new keypad readers, PIN-entry mode or live certificate-authentication commissioning are included. Furnish four complete new Grade 1 strike/DPS/REX hardware packages at 3B-149, 3B-165, 3A-171 and 3A-155, including required power transfer, mounting and interfaces. Provide the strike, DPS and REX functions at 3A-107. Provide strike and DPS functions at both 3B nurses-station openings and 3A-C3-2A, and an electrified handle/lockset and DPS at the 3B-C3-26 / 3A-C3-25 corridor opening. Serviceable compatible existing hardware outside the four complete new packages may be retained after verification; furnish missing or unsuitable components for complete scheduled operation. REX is required at the five single-reader openings, including free-egress doors, and is not included at the four dual-reader openings. Preserve independent required staff/emergency and life-safety release under R47. For ordinary free-egress latch doors, the strike basis is HES 1006 fail-secure 24 VDC or equal with the correct listed faceplate and compatible mechanical egress. Furnish listed functionally suitable hardware where actual construction or approved ward operation requires it.
R24 Software and license scope. Use existing VA enterprise license capacity and entitlements for Phase 1 current operation. Verify available capacity for both assemblies and all 59 active reader positions with authorized VA administrators. Do not purchase or activate new HA licenses, HA enrollment/validation services or certificate-authentication services for the 13 new readers in this phase. Document any future HA software, firmware, license, service and configuration dependencies under R27 without procuring or activating them. Preserve existing licensed functions needed for migrated readers. Do not include automatic purchases of generic or additional reader licenses. Refer any unexpected Phase 1 entitlement conflict to VA technical reviewers before ordering or making changes; additional purchases or system upgrades require written authorization.
R46 Door position switches. Provide working supervised DPS at all nine new-work openings in Attachment 1, including every monitored leaf of a pair. Include new DPS with each of the four complete packages and furnish or replace contacts at the other five scheduled openings where absent or unsuitable. Preserve and commission existing DPS functions associated with the 46 migrated reader positions; report discovered absent or unsuitable existing contacts for written resolution before scope-changing replacement. Contacts shall be listed for the application, suitable for actual metal/wood door and frame construction, protected from casual tampering and connected to dedicated supervised C•CURE inputs with field end-of-line devices. Use concealed magnetic contacts where compatible with the door rating/construction; use supported protected surface/armored arrangements where concealed installation would compromise the assembly. A strike latch monitor or software lock command does not substitute for actual door-open/closed sensing. Show each leaf’s status and aggregate door alarms correctly; no bypassed or panel-located resistor may mask a field wiring fault.
R48 Required reader capacity. Provide both complete 32-reader cabinet/controller assemblies and rated power provision required by R11–R22. Label all active and spare reader, input and output positions and provide supported wire management and cable entries. The combined allocation is 59 active reader positions and five spare positions, with no more than 32 positions assigned to either assembly. Demonstrate 32-reader installed capacity per assembly under T17 and provide manufacturer-backed evidence of future 32-reader HA capacity per assembly under R21/R27/T03. Live HA operation is not required at the 13 new readers for Phase 1 acceptance. Spare positions do not substitute for any of the 13 new or 46 migrated active reader positions.
7 Integration and door functions R25 Supported enterprise integration. Integrate with the existing VISN 8 C•CURE 9000 3.10.1 CU02 system, or a later manufacturer-supported release already authorized by VA. This work does not authorize the contractor to upgrade production software. Provide exact manufacturer support evidence for the Phase 1 reader/firmware/G2 configuration and separately document the future HA path under R27. Preserve any existing HA service required by the migrated-reader baseline. Apply current GSA approval restrictions. GSA APL status and C•CURE version compatibility are separate checks. Preserve existing server/SAS, partitions, naming, groups, credentials and monitoring. No new server, production database, MAS/SAS architecture change or global-object change is authorized without a reviewed technical plan and required CO action.
R26 200 bit identifier preservation. Preserve and test the established full 200-bit credential format at every affected reader for which the existing credential population uses it. Record exact site fields and mapping rather than truncating to a card number. Test approved identities differing in relevant high-order fields for correct distinct mapping and authorization. The 13 new readers do not require cryptographic PIV/CAC authentication testing in this phase. Preserve and regression-test any cryptographic authentication already required by the migrated-reader baseline. Identifier transport, an APL logo or a reader family name alone is not proof of future HA compatibility; provide the R27 evidence.
R27 Future High Assurance readiness. Install the 13 new readers and their wiring with a documented manufacturer-supported path to future C•CURE High Assurance certificate authentication, including the applicable contactless PKI-CAK capability. Commission them now in the VA-approved current card-only access mode, using OSDP Secure Channel, with correct credential mapping and access permissions. Do not activate new HA enrollment, certificate validation, cryptographic certificate authentication or associated HA licensing/services in this phase. Before ordering, submit exact reader models/form factors, firmware, controller/interface versions and manufacturer compatibility evidence showing that the installed reader hardware and cabling support the future HA path. Identify future software, firmware, licenses, validation/trust services, configuration steps, supported capacity and other dependencies; do not procure or implement those future items under this scope. A generic HA-ready label is insufficient. Preserve and regression-test the established authentication mechanisms, required PIN or other factors and offline/cached-status policy of the 46 migrated readers, including existing HA functions where actually in use. No new keypad/contact reader, biometrics or change to an existing authentication policy is authorized. If applicable VA policy requires certificate authentication at a new opening now, refer that conflict for VA technical and CO resolution before H1; do not silently lower a required assurance level. Future HA activation requires separate written authorization and scope.
R28 OSDP Secure Channel. Use OSDP Secure Channel on all 13 new reader links. Ordinary OSDP without Secure Channel, RM or Wiegand does not satisfy the new-reader requirement. Provide one new reader per dedicated port, manufacturer-compliant RS-485 data pairs, supported speed/address/termination and cable distance. Protect keys, use non-default production keys as supported, disable installation/default-key mode after commissioning and prove encryption per new link. Preserve supported existing protocols for the 46 migrated reader positions under R22; maintain and test Secure Channel on existing links where already required by their approved configuration. Disclose and resolve any reader/controller/firmware limitation before ordering. Migration alone does not authorize a blanket protocol conversion or replacement of existing readers.
R29 Permissions and offline operation. Preserve existing authorized access groups, schedules, holidays, keypad commands, door alarms and ward-specific staff/clinical functions. Contractor shall capture baseline sequences with Electronics Shop, ward leadership, VA Police and VA fire safety, then submit the complete normal/fire/power/network-loss/staff-release/reset matrix under R47. Local controller operation shall follow the approved current access policy and any existing migrated-reader HA cache/status policy, and queue/reconcile events after reconnection. Future HA status validation is not required at the 13 new readers in this phase. No network outage may silently bypass a credential factor, defeat an emergency-release path or unilaterally change a ward locking rule.
R47 Life safety and ward operating sequence. For each affected door, deliver a documented sequence meeting applicable life-safety/fire/accessibility requirements and established ward rules. Contractor shall field-verify clinical use with ward leadership and locking classification with VA fire safety/AHJ; these reviews confirm lawful operational constraints and do not ask Contracting to design hardware. Sequence shall identify authorized entry, patient/staff egress, staff override/emergency release, any nurse-station interface, required fire/smoke/sprinkler release, loss of AC/battery/controller/network, tamper/forced/held alarms, fail state and reset/relock. Ordinary egress shall operate without software/network or credential dependency where required. Clinical/special locking is permitted only when its actual code conditions and VA approval are documented; do not add delayed egress, blanket-unlock all ward doors or let a motion REX defeat approved patient-security controls. Where sensor-released electric locking requires independent manual/hardware release, provide it; a controller command is not a substitute. Preserve fire-door latching and approved staff rescue access, and provide required tamper/ligature-resistant hardware where the ward’s documented risk conditions require it. Conflicting ward/code instructions are resolved before H1; no approval may waive applicable law.
8 Security cable and pathways R30 Personnel and facility access. Before applicable access, submit personnel roster, role/access duration and required vetting/badging paperwork through the COR by VA-approved channels. Each employee/subcontractor shall satisfy the VA personnel-vetting/credentialing clauses, VA-assigned position designation and applicable escort/access conditions. Obtain required screening and access authorization before beginning applicable work; wear issued identification and follow check-in/escort procedures. VA security/ISO determines role-based requirements under current policy, including applicable VAAR 852.204-70 and 852.204-72 deviations. No blanket investigation tier or security clearance is invented by this SOW. Revoke and return access credentials on reassignment/completion.
R31 Information and system access. Before system access complete applicable VA privacy/security training, Rules of Behavior and privileged-access approvals. Use named least-privilege accounts, VA-approved devices, network settings and storage; protect credential, key and configuration data. No unapproved remote access, cloud transfer, personal-media copies or shared administrator accounts. Report suspected incidents immediately to the COR and designated VA security contact, following contract reporting requirements. Transfer sensitive closeout files through VA-approved secure channels. For new equipment and its integration, implement manufacturer-supported encrypted controller-to-C•CURE communications, replace default credentials, hand over credentials securely, use VA-approved supported firmware, and disable unnecessary services, diagnostics and ports where compatible with required operation. Document and verify these settings before acceptance. Enterprise-wide software, architecture or security changes require separate authorization.
R32 Occupied facility installation. Coordinate with VA Engineering, Electronics Shop, IT, VA Police and affected occupants. Protect occupied areas, utilities and existing equipment; implement the VA-approved infection-control, dust/noise, life-safety and work-area protection measures. Keep required egress open. Repair project-caused damage and restore finishes; firestop each disturbed rated penetration with a listed system appropriate to the actual assembly, recording system and location. Remove installation debris daily, perform a final sweep, remove abandoned wiring and conduits only where identified for removal and VA authorizes, and leave the work area clean and undamaged. Do not disturb retained shared infrastructure.
R44 Contractor furnished pathways. Provide all required conduit, raceways, sleeves, pull/junction boxes, reader/device boxes, supports, fittings, bonding, penetrations, pull strings, identification, firestopping and restoration for the Phase 1 system, including required AC/network connections from available VA-authorized sources to both cabinet assemblies. Include their installation in the fixed price; do not assume Government-furnished pathways. Existing usable pathways may be reused only after verifying capacity, condition, permitted use and written technical concurrence; contractor remains responsible for required new routes and continuity. Use minimum 3/4-inch EMT for accessible indoor door home-run routes, larger where fill/bend limits require; concealed flexible final connections and wet/corrosive-location raceways shall be listed and appropriate to the actual environment. No unsupported ceiling-grid attachment or exposed unprotected cable in occupied/service areas. Keep power/communications separation and rated assemblies intact. Contractor shall provide AC wiring from the VA-designated suitable source, required disconnect/protection and labeling, and network cabling/pathway/termination to the VA-designated connection. VA IT or authorized administrators provide network authorization, VLAN/IP and switch-port configuration and system access. Contractor coordinates these interfaces. Four new hardware packages include necessary door/frame preparation and listed modifications. Confirm supply of door leaves/frames and the meaning of “UPS #1” at site access; issue common clarification before final quotes.
R45 Composite door cable. Wire each of the nine new-work openings in Attachment 1 using new factory-assembled access-control composite combo cable with individually identified reader data/power, lock power, DPS and REX components. A spare REX cable element at a dual-reader opening does not require installation of a REX device. Provide a dedicated additional reader data/power element for the second reader at each dual-reader opening, with each new reader on its own port. Provide genuine low-capacitance shielded twisted data pairs suitable for RS-485/OSDP; generic untwisted Wiegand cable is insufficient. Minimum composite construction: reader element with two shielded low-capacitance twisted pairs of 22 AWG or heavier plus a power pair of 18 AWG or heavier; DPS and REX elements of at least four conductors each, 22 AWG or heavier; lock element of at least two conductors, 16 AWG or heavier. Equivalent construction requires technical acceptance and shall meet or exceed these minimums and all device-specific requirements. Use stranded copper, no copper-clad aluminum; CMP in plenums and the required listed rating elsewhere. Verify impedance, capacitance, shielding, gauge, pair usage, terminations and supported distance against both controller and reader instructions. Upsize power conductors or provide an approved supported cable arrangement where voltage-drop/inrush requires; do not use spare random conductors as specified data pairs. Home-run new circuits to their assigned assembly, label both ends, use accessible junctions only and document continuity/polarity/shield and operating-voltage tests. Retain serviceable compatible existing wiring for the 46 migrated positions; provide supported reconnection and routing needed for consolidation. Report discovered unsuitable existing circuits for written resolution before scope-changing replacement.
9 Outages and completion R33 Outage hold point H2. Request each service interruption at least five business days in advance with affected doors, maximum window, contacts, temporary ward/security measures, egress protection, backup/rollback and restoration checks. Obtain written COR operational release after coordination with Electronics Shop, ward leadership, VA Police, fire safety and enterprise administrators. Plan no more than one affected door at a time unless a reviewed common-controller outage requires a specifically approved protected sequence. No outage may extend beyond its released window or leave an unsecured or unlawfully locked door. On unexpected failure, secure the area and immediately notify the COR; only the CO authorizes contract changes.
R34 Migration and restoration. Before changes capture VA-approved backups of affected database/configuration, controller settings and any existing HA configuration that must be preserved and document a viable restoration method with VA administrators. Replace all three existing controller assemblies and migrate all 46 existing reader positions and their associated functions to the two new assemblies in bounded door groups, pretest where feasible and provide approved temporary security while a door is impaired. Restore scheduled functionality or execute rollback by the approved window end; secure and notify VA immediately if restoration fails. Do not remove safeguards until VA verifies normal operation. After successful migration and verification, decommission all three legacy controller assemblies and handle removed Government equipment under R39; do not retain any in service.
R35 Working hours and fixed price. Routine work is 7:30 AM–4:30 PM Eastern Time Monday–Friday, excluding Federal and observed holidays. Submit after-hours requests through the COR at least five business days in advance for operational approval. Include all required planned after-hours cutovers, witness testing, travel, staging and support in the firm-fixed-price quotation; scheduling concurrence alone does not authorize extra compensation. Complete all Phase 1 work, tests, deficiency correction and closeout within 120 calendar days after notice to proceed. Bidders shall identify lead-time or scheduling conflicts before award; identify long-lead items and access constraints in the initial schedule; only the CO may change contractual completion, scope or price.
10 Commissioning and acceptance R36 Acceptance test plan. Submit detailed T01–T18 procedures with H1, including each affected door/leaf, all 13 new and 46 migrated readers, the nine new-work openings, four new packages, every installed controller/ACM/supply and all reserved hardware positions. Use the approved actual ward settings and emergency sequences as pass/fail values; do not invent operational delays to make a test pass. At least five business days before witnessed tests, submit contractor pretest/readiness records, intended witnesses and safe fault-test methods. The plan shall distinguish new-reader future-HA readiness checks from operational regression tests of existing HA functions. New-reader HA activation is outside scope, not a waiver of a required installed function. Explain other test applicability in advance; N/A may not waive a required installed function. Unused reader positions shall be tested under T17 using compatible supported test equipment.
R37 Witnessed pass fail results. Witness tests with COR-designated Engineering/Electronics Shop/enterprise staff, ward representative and VA Police/fire safety for applicable sequences. Record test/requirement ID, door/reader/leaf or spare port, expected/actual behavior, timing and measurements, configuration, tester, witness and pass/fail. All required outcomes must pass; N/A requires a valid approved basis. Apply the readiness-only criteria in T03 to the 13 new readers and the existing-function criteria to migrated readers. Submit results within five business days after testing. Demonstrate all 13 new and 46 migrated readers in place; loose-reader bench testing does not satisfy installed-reader acceptance.
R38 Deficiencies and acceptance. Correct and retest all nonconforming functions and dependent regression functions within the contract period at no added cost for nonconforming work. Final acceptance requires 13 new installed operational readers and 46 successfully migrated operational reader positions, replacement and decommissioning of all three legacy controller assemblies, four complete new-door packages, required DPS/ward/life-safety operation, full 32-reader hardware and power-capacity evidence for each of the two assemblies, successful applicable T01–T18 results, closed deficiencies, Phase 1 entitlement confirmation, accepted future-HA readiness evidence under R27/T03, restored battery standby capacity and complete closeout. Do not condition acceptance of the 13 new readers on live HA authentication, certificate validation or HA license activation. Acceptance is written by the authorized Government official; partial use or a contractor certificate alone is not final acceptance.
11 Property and documentation R39 Removed Government equipment. Inventory and label removed equipment by asset/serial number and source location.
This is the start of the file's text. The full file is on GovTribe.