D.4 Drawings.pdf
PDF 856 KB Posted
- Attached to
- 6835--Tampa Bulk Oxygen and Medical Gas
- Solicitation number
- 36C24826Q0759
About this file
This document is a Statement of Work for a construction project to build a reinforced concrete pad for an oxygen tank system at the James A. Haley Veterans' Hospital in Tampa, Florida (Project #673-14-858). The project involves removing the existing 6-inch reinforced concrete pad and chain-link fence from the oxygen and nitrous oxide gas storage area, then constructing a new 12-inch reinforced concrete pad with a 7-foot-0-inch chain-link fence topped with 1-foot barbwire. The contractor must temporarily relocate the nitrous oxide manifold cylinders off the existing pad during demolition and later secure the existing nitrous oxide manifold to the new pad.
The work scope includes coordination with the VA for removal of the existing oxygen system and temporary oxygen supply provisions prior to demolition. The contractor is responsible for verifying all existing conditions and dimensions, with any deviations from contract documents requiring immediate written notification to the Contracting Officer Representative (COR). The new concrete pad will measure 36 feet by 30 feet with an 8-foot extension, incorporating #6 rebar at 18-inch spacing both longitudinally and transversely, positioned over 4 inches of crushed stone and a compacted subgrade. The project documentation includes detailed site plans, existing and new site conditions drawings, dimensions, cross-sectional details, and specifications for materials and construction standards that the contractor must follow in accordance with all applicable codes and industry standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24826Q0759 0005.docx | DOCX document | |
| D.3 Medical Gas by Location - updated Copy.xlsx | XLSX spreadsheet | |
| D.5 9000 Gallon main tank label.jpeg | JPEG file | |
| D.6 NARA RM Contract Language Clause.docx | DOCX document | |
| D.7 Questions and Answers.pdf | ||
| 36C24826Q0759 0004.docx | DOCX document | |
| 36C24826Q0759 0003.docx | DOCX document | |
| 36C24826Q0759 0002.docx | DOCX document | |
| 36C24826Q0759 0001.docx | DOCX document | |
| D.1 James Haley Map.pdf | ||
| D.3 Medical Gas by Location.pdf | ||
| 36C24826Q0759 Tampa Bulk Oxygen and Medical Gas.pdf | ||
| D.2 Attachment A. Manufacturing Facilites.pdf | ||
| 36C24826Q0759_1.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
t h
S
T R
E E
T h.
R
E E
T
R E
E T
L I
V I
N G
S T
O N
A V
E N
U E
R O
WHARTLINE BUS
UNIVERSITY
NORTH TRANSFER
STATION
CONVENIENCE
STORE
POND
POND WOODED
AREA
DRAINAGE CANAL/DITCH
131st AVENUE th
S T
R E
E T
JAMES A. HALEY VETERANS' HOSPITAL
TAMPA, FLORIDA
CONSTRUCT PAD FOR OXYGEN TANK
PROJECT #673-14-858
CONSTRUCT PAD FOR
OXYGEN TANK
COVER, STATEMENT OF
WORK, SITE MAP, AND
INDEX
STATEMENT OF WORK:
INDEX OF DRAWINGS:
PROJECT AREA
SITE MAP:
CONSTRUCT PAD FOR
OXYGEN TANK
EXISTING SITE CONDITIONS
AND DEMO
GENERAL DEMOLITION NOTES
1. THE CONTRACTOR SHALL VERIFY ALL CONDITIONS AND
DIMENSIONS WITHIN THE CONTRACT LIMITS AND NOTIFY
THE COR IMMEDIATELY IN WRITING OF ANY DEVIATION
FROM CONTRACT DOCUMENTS NECESSITATED BY FIELD
CONDITIONS OR ITEMS NOT COVERED.
2. ALL MATERIALS AND ITEMS REMOVED BY CONTRACTOR,
UNLESS OTHERWISE NOTED, BECOME HIS PROPERTY AND
ARE TO TO BE REMOVED FROM THE SITE.
3. REBUILD ANY AREAS TO REMAIN THAT HAVE BEEN
DISTURBED BY DEMOLITION.
4. VA SHALL COORDINATE WITH VENDOR FOR EXISTING
OXYGEN SYSTEM REMOVAL, AND TEMPORARY OXYGEN
SUPPLY, PRIOR TO DEMOLITION.
DEMOLITION KEY NOTES
CONTRACTOR SHALL COORDINATE WITH THE VA FOR
REMOVAL PRIOR TO DEMOLITION.
CONTRACTOR SHALL RELOCATE NITROGEN CYLINDERS OFF
PAD PRIOR TO PAD DEMOLITION. COR SHALL PROVIDE
DIRECTIONS ON LOCATION.
SITE PLAN TEMPORARY
PAD
KEY NOTES
CONTRACTOR SHALL LOCATE THE OXYGEN ALARM PANEL
IN BUILDING 2, AND PROVIDE WIRING FROM THE PANEL TO
THE TEMPORARY PAD, SUSPENDED ABOVE THE ALLEY.
CONTRACTOR SHALL LOCATE AVAILABLE POWER SOURCES
TO INSTALL 120V RECEPTACLE.
NEW SITE PLAN
GENERAL DEMOLITION NOTES
1. THE CONTRACTOR SHALL VERIFY ALL CONDITIONS AND
DIMENSIONS WITHIN THE CONTRACT LIMITS AND NOTIFY
THE COR IMMEDIATELY IN WRITING OF ANY DEVIATION
FROM CONTRACT DOCUMENTS NECESSITATED BY FIELD
CONDITIONS OR ITEMS NOT COVERED.
2. CONTRACTOR SHALL REVIEW ALL ITEMS TO BE
DEMOLISHED WITH THE COR TO IDENTIFY ANY ITEMS TO
BE SALVAGED PRIOR TO START OF DEMOLITION.
3. ALL MATERIALS AND ITEMS REMOVED BY CONTRACTOR,
UNLESS OTHERWISE NOTED, BECOME HIS PROPERTY AND
ARE TO TO BE REMOVED FROM THE SITE.
4. REBUILD ANY AREAS TO REMAIN THAT HAVE BEEN
DISTURBED BY DEMOLITION.
CONSTRUCTION KEY NOTES
CONSTRUCT NEW 12" REINFORCED CONCRETE PAD,
REFER TO DETAILS ON AS-102.
CONSTRUCT NEW 7'-0" CHAIN LINK FENCE WITH 1'-0"
BARBWIRE AT TOP.
SECURE EXISTING NITROUS OXIDE MANIFOLD TO NEW
PAD.
NEW PAD DIMENSIONS
AND DETAIL
GENERAL CONSTRUCTION NOTES: