This document is a Statement of Work (SOW) for a federal contract opportunity to perform structural and water intrusion repairs at the Lake Baldwin VA Clinic in Orlando, Florida. The project includes repairs to the Domiciliary and Building 500, as detailed in the SOW. Key requirements include applying water-resistant coatings, creating new weep holes, installing new flashing, repairing drywall and painting, and rerouting condensate drains. The contractor must be a State of Florida certified/licensed general contractor. The project has a 240-day construction phase and requires the contractor to submit a Critical Path Method (CPM) schedule and comply with VA construction standards and policies. The contract opportunity, Solicitation Number 36C24824R0147, is being issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8. An organized site visit is scheduled for August 24, 2024.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION
Perform Structural and Water Intrusion Repairs Project No. 675-22-814 Orlando VA Medical Center, 5201 Raymond Street Orlando, FL. 32803
I. DEFINITION AND ACRONYMS:
A. Construction: as defined by the Department of Veterans Affairs (DVA) Is the procurement by the Government, under one contract, with one firm for the construction services on a specific project.
B. Contracting Officer (CO): The services to be performed under this contract are subject to the general supervision, direction, control, and approval of the Contracting Officer.
C. Project Manager (PM)/Contracting Officers Representative (COR): The Contracting Officer's representative responsible for administering contracts under the immediate direction of the Contracting Officer.
D. Contractor: This term, as used herein, refers to the contractor under this contract.
E. Pre-Construction Risk Assessment (PRCA): Used to identify potential risks associated with the renovation, construction and some maintenance & repair activities and to develop risk mitigation strategies to minimize these risks. Prior to beginning work this assessment will be completed.
F. Interim Life Safety Measures (ILSM): Measures that are instituted to compensate for significant hazards posed by existing life safety (fire) code deficiencies or construction/renovation activities.
G. Request for Proposal (RFP): Is a solicitation made, often through a bidding process, by an agency or company interested in procurement of a commodity or service, to potential suppliers to submit proposals.
II. SCOPE OF WORK:
Project Overview: This project will repair structural and water intrusion issues at the Domiciliary and 3rd and 4th floors floor Mental Health offices North and South sides Building 500 at the Lake Baldwin VA campus. The second portion of this project is to repair water damage at the Lake Baldwin Dom Building 519 and 522 walkway structures on second and third floor of building. This will also repair water damage to rail structure to properly resecure to floor and wall. The Orlando VAMC has contracted with an A/E team to do an analysis and recommendations for repair. Drawings and specifications are provided.
A. Specific Project Requirements:
a) Building 500
a) Apply water-resistant coating to areas shown on drawings.
b) Create new weep holes on the exterior.
c) Install new flashing at window heads in areas shown.
d) Repair office walls water damage inside the offices in the 3rd and 4th Mental Health offices North and South sides that have been affected by the issue. This will include drywall replacement, patching and paint.
e) Repair walls water damage inside the multipurpose rooms in the 3rd and 4th Mental Health space North and South sides that have been affected by the issue. This will include drywall replacement, patching and paint.
f) Some of the windows next to stairwells in the 3rd and 4th Mental Health space are leaking. Verify, identified and fix water intrusion sources.
2. Domiciliary
a) On every floor, reroute condensate drains to building exterior to new downspout system.
b) Install new handrails on upper floors as shown.
c) Repair topping slab at the top of walkways as shown.
d) Repair beam cracks and joints at the support landings 2nd and 3rd floors.
B. Bid Proposal
1. Base Bid: Include all work as shown on drawings.
2. Deductive Alternate: Remove work associated with Domiciliary.
C. General Requirements:
Provide all labor, materials, tools, and equipment as necessary to construct the project described below and other specific tasks as further defined by this RFP. All proposals are to provide construction services for this project. The contractor shall be a State of Florida Certified/licensed General Contractor.
D. Special Requirements:
1. Badges: Facility Management Services (FMS) will issue identification badges to contractors, employees and subcontractors which must be worn at all times when on VA property.
2. Contractor shall provide a list of all personnel who will participate on the project. Personnel can be subjected to a background investigation prior to commencement of work. Contractor will be issued appropriate quantity of badges per provided list.
3. Contractor shall keep the area cleaned daily and haul away all construction debris. All materials shall be tracked and logged to be reported back to the GEMS coordinator for recycling tracking purposes. When removing construction debris from facility it must be in a covered cart when entering and exiting the building.
III. SCHEDULING, PHASING, AND WORKING HOURS:
A. All work hours MUST be coordinated with the project’s COR to minimize interference with normal clinic functions. All work shall be performed during normal business hours (7:30 am to 4:00 pm) Monday through Friday. However, areas may require work to be completed OUTSIDE normal business hours (4:00 pm to 10:00 pm,) or weekends must be coordinated and approved by project’s COR. Additionally, construction shall be performed (scheduled and phased) to ensure that areas which can be completed ahead of schedule or priority for early acceptance and operation can be rendered back to facility.
B. Length of Project
1. Project’s construction phase MUST be completed in no more than 240 days from Notice to Proceed.
2. Contractor shall submit a Critical Path Method (CPM) schedule for the Construction with estimated dates and itemized cost of work to the Contracting Officer for review and approval before Notice to proceed.
C. Utility shutdowns/Outages: All shutdowns involving temporary impairment of utilities shall be requested by the Contractor at least 14 calendar days in advance.
IV. PROJECT CLASSIFICATION:
A. Contractor shall secure area prior to commencement of work and follow the Orlando VA Medical Center guidelines and policies for Pre-Construction Risk Assessment (PCRA) and Interim Live Safety Measures (ILSM).
B. Risk Assessment: This project has been classified per the Construction Infection Control Risk Assessment as a Type A, Low Risk Group, Class I (ISLM Level 1) project.
V. SAFETY REQUIREMENTS:
A. All Contractor's personal is required to have completed an OSHA-approved 10-hour construction worker course prior to working on the site. The On-site general superintendent/supervisor is required to have completed an OSHA-approved 30-hour construction course prior to working on the site. Every worker must provide the Contracting Officer a copy of current certificates identifying successful completion of the training prior to executing work for the Veterans Administration. In addition, Contractor shall provide submittals for contract construction or renovation work which include the names, qualifications, and training dates for Contractor’s Competent Persons (CP), who has been designated to administer the site-specific safety program, as well as the CP for other activities as required by OSHA regulation 29 CFR 1926.32 (such as scaffolds, cranes, excavations, etc.). Contractor’s CP are required to implement and maintain effective safety programs that identify and control hazards that may cause injury or illness to VA patients, staff, visitors, and contractor employees. The VA CP does not take the place of Contractor’s CP nor acts on their behalf. The VA CP determines if Contractor is meeting VA standards and contractual requirements for safety and OSHA compliance. When these standards and contract requirements are not being met, the VA COR and/or CP will take immediate action to prevent injury, non-compliance, and/or property damage. The Contractor shall submit an Activity Hazard Analysis, and an Accident Prevention Plan as per FAR 52.236-13 prior to commencement of site activities. The Government shall have 21 calendar days to review the AHA and APP.
B. Contractor shall submit documentation proof of OSHA construction safety course for all personnel.
VI. GOVERNMENT FURNISHED INFORMATION:
All available record drawings will be provided upon request to the Contractor. They should not however, be considered “As-Built”. These drawing files are provided without warranty or obligation as to the accuracy or information contained in the files. All information in the files shall be independently verified by the user. Any user shall agree to indemnify and hold the VA harmless from any and all claims, damages, losses, and expenses, including, but not limited to, attorney fees arising out of the use of the Computer Aided Design and Drafting (CADD) drawing files.
VII. RESOURCES:
All designs shall comply with applicable sections of VA standards and publications, and all references therein. Ensure that construction documents comply with the latest edition of these VA construction and design standards. VA standards can be found on the World Wide Web at http://www.cfm.va.gov/TIL/. VA publications and standards shall include but shall not be limited to:
1. Office of Construction & Facilities Management Site Map:
http://www.cfm.va.gov/sitemap.asp
2. The Technical Information Library (TIL): http://www.cfm.va.gov/TIL/
a) Master Construction Specifications Index (PG-18-1)
b) Design and Construction Procedures (PG-18-3)
c) VA Standard Details and CAD Standards (PG-18-4)
d) Equipment Guide List (PG-18-5)
e) Equipment Inspection Manual (Program Guide 7610.2)
f) Equipment Reference Manual (PG-18-6)
g) Space Planning Criteria (PG-18-9)
h) Design Manuals (by discipline) (PG-18-10)
i) Design Guides (graphical, by function) (PG-18-12)
j) Barrier Free Design Guide (PG-18-13)
k) Room Finishes, Door and Hardware Schedules (PG-18-14)
l) Minimum Requirements for A/E Submissions (PG-18-15)
m) Environmental Planning Guidance (PG-18-17)
n) HVAC Design Manual for Hospitals Amendment B
o) Lighting Study
p) Design Alerts
q) Quality Alerts
r) VA Signage Design Guide
s) Fire Protection Design Manual – Latest Edition
t) Cost Estimating
u) Physical Security Design Manuals for VA Facilities – Mission Critical Facilities (VA Handbook 0730)
v) Information Security Handbook VA 6500
w) Sustainable Design and Energy Reduction Manual (First Draft)
3. TIL - Master Construction Specifications: http://www.cfm.va.gov/til/spec.asp
4. Department of Veterans Affair Utilities Design Manual.
B. Office of Construction & Facilities Management: http://www.cfm.va.gov/index.asp
1. VA Office of Facilities Management citations of the AIA design standards found on the world wide web at http://cfm.va.gov.TIL/
2. VA Office of Health and Safety (OHS): http://www1.va.gov/vasafety/
3. Construction Infection Control Risk Assessment Memorandum
C. Other design and construction standards and publications that shall be applied to this work includes, but are not limited to:
1. American Society of Heating, Refrigerating and Air-Conditioning Engineers Manual (ASHRAE)
2. National Fire Protection Association (NFPA) Codes & Standards - www.nfpa.org
3. OSHA Rules and Regulations
4. International Building Code (ICC) latest edition
5. Life Safety Code (NFPA 101) latest edition
6. The Joint Commission (TJC) Accreditation manual (latest edition)
D. Applicable sections of the VA Master Construction Specifications will be prepared by the Architect/Engineer, including all the necessary adaptations.
E. Particular attention is called to CD4, Symbol Identification of Contract Drawings.
F. Equipment symbols shall be in accordance with PG-18-6, Equipment Reference Manual (previously List of Equipment Symbols, H-08-6).
G. Standard Drawing Details, in accordance with PG-18-4, shall be utilized to the greatest extent practicable.
H. Cost estimates shall be developed in strict conformance with VA’s Manual for Preparation of Cost Estimates & Related Documents for VA Facilities (March 8, 2011). http://www.cfm.va.gov/til/dManual/dmCost.pdf I. Guidelines for Design and Construction of Health Care Facilities, Latest Edition, published by The Facilities Guidelines Institute (FGI). http://www.fgiguidelines.org/ J. Physical Security Standard, compliance with Medical Center Policy 138-3 and VHA Handbook 0730/2 dated May 27, 2010 “Space Key Control”.
VIII. SUBMITTALS
A. Contractor shall submit documentation proof of OSHA construction safety course.
B. General Contractor License and Insurance.
C. Submittal as per Construction Documents and Specifications.
D. Warranties
IX. QUALITY ASSURANCE/QUALITY CONTROL:
A. The Construction Contractor shall develop and execute a QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort.
B. Within 2 weeks of receipt of Notice to Proceed, the Construction Contractor will submit a detailed QA/QC plan describing each QA/QC task that will be taken during the construction phase and the name of the Contractor’s team member responsible for QA/QC.
C. Upon its completion each task shall be initialed and dated by the responsible Contractor’s team member.