This document contains the Questions and Answers (Q&A) related to the Request for Information (RFI) for Solicitation Number 36C24824R0147, which is for the project "BB Perform Structural and Water Intrusion Repairs at Lake Baldwin VA Clinic 675-24-814".

The Q&A covers several key details about the project, including:

  • The period of performance has been changed to 240 calendar days.
  • The interior work for Building 500's 2nd and 3rd floors is to be performed at night and on weekends.
  • The concrete work for the Domicile building will be broken into 4 phases.
  • Architectural as-built drawings for the 2nd and 3rd floors are available.
  • Staging area coordination with Grounds personnel will occur at a later date.
  • There is a missing specification 03 64 00, which is not available on the VA TIL List.

The Q&A provides clarification on various aspects of the project requirements in response to questions from interested parties.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

PHASE II RFI's for 36C24824R0147 - Project 675-22-814 BB Perform Structural and Water Intrusion Repairs (Construction)
RFIsResponses
1. Has the period of performance changed to 240 calendar days?Yes. This is reflected in the revised statement of work
2. Is the work building 500 2nd and 3rd floor interior work to be performed nights and weekends?Yes.
3. Domicile bulding, broken into 4 phases for concrete work.Approved.
4. Architectural as-built for 2nd and 3rd floodPlease see attachments
5. Staging areaCoordinate with Grounds personnel at later date.
6. Additional Tuck-Pointing for motar joint repairUnsure of the question, need clarification.
7. Missing specification 03 64 00These specs are not available or existing on the VA TIL List.