This document is a Statement of Need for replacing the physiological monitoring and telemetry system at the Bay Pines VA Healthcare System, including the C.W. Bill Young VA Medical Center and Lee County Healthcare Center.
The key details are:
- The Bay Pines VA Healthcare System requires the replacement of its existing physiological monitoring and telemetry system at the specified locations.
- The solicitation will be set aside for Service-Disabled Veteran Owned Small Businesses only, with proposals due on June 21, 2024.
- The contract will cover the removal of the old system, assembly, equipment, installation, configuration, testing, project management, and training for the new physiological monitoring and telemetry system.
- The new system must be compatible with the existing Picis clinical information system, Philips eICU, Cerner Careware BMDI, and Vocera.
- The Statement of Need provides detailed technical and clinical requirements for the new system, including compatibility, interface, and integration requirements.
- The contract period is for 1 year, from September 1, 2024 to August 31, 2025.
- The associated NAICS code is 334510 (Electromedical and Electrotherapeutic Apparatus Manufacturing) with a small business size standard of 1,250 employees.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24824R0092 0004.docx | DOCX document | |
| 36C24824R0092 0003.docx | DOCX document | |
| 36C24824R0092 0002.docx | DOCX document | |
| 36C24824R0092 0001.docx | DOCX document | |
| Drawing 20220418_LCHCPatientMonitoring_Redacted.pdf | ||
| Drawing 20220418_CWY_ProposedTelemetryCoverage.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24824R0092
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
UEI:
EFT:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
516-24-1-213-0070 36C24824R0092 05-13-2024 Moneque Rodriguez 813-550-9486 06-21-2024
13:00PM
EDT
36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) 10,000 Bay Pines Blvd Bay Pines
FL
33744 X X 334510 1250 Employees NET 30 Days N/A X
MCC: 90D
Department Of Veteran Affairs C.W. Bill Young VA Medical Center Bldg 110 Warehouse 10,000 Bay Pines Blvd.
Bay Pines
FL
33744 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) C.W. Bill Young VA Medical Center 10000 Bay Pines Blvd.
Bay Pines
FL
33744
Department of Veterans Affairs
FMS-VA-2(101)
Financial Services Center PO Box 149971 Austin
TX
78714-9971 See CONTINUATION Page Offeror instructions are provided in provision 52.212-1.
Evaluation factors are provided in provision 52.212-2.
Questions shall be directed in writing to Moneque Rodriguez moneque.rodriguez@va.gov no later than 06/14/2024 This is a 100% Service-Disabled Veteran Owned Small Business Set Aside.
See CONTINUATION Page 516-3640160-213-820100 Medical Service-3131 Medical, Dental and Scien-010040175 X Moneque Rodriguez Contracting Officer Table of Contents
| SECTION A | 1 |
| A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES | 1 |
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 4 |
| B.1 CONTRACT ADMINISTRATION DATA | 4 |
| B.2 STATEMENT OF NEED | 5 |
| B.3 PRICE/COST SCHEDULE | 44 |
| ITEM INFORMATION | 44 |
| B.4 DELIVERY SCHEDULE | 48 |
| SECTION C - CONTRACT CLAUSES | 53 |
| C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023) | 53 |
| C.2 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021) | 58 |
| C.3 52.228-5 INSURANCE—WORK ON A GOVERNMENT INSTALLATION (JAN 1997) | 60 |
| C.4 SUPPLEMENTAL INSURANCE REQUIREMENTS | 61 |
| C.5 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022) | 61 |
| C.6 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 61 |
| C.7 VAAR 852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB 2023) | 61 |
| C.8 VAAR 852.211-70 EQUIPMENT OPERATION AND MAINTENANCE MANUALS (NOV 2018) | 70 |
| C.9 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 71 |
| C.10 VAAR 852.211-76 LIQUIDATED DAMAGES – REIMBURSEMENT FOR DATA BREACH COSTS (FEB 2023) ALTERNATE I (FEB 2023) | 71 |
| C.11 VAAR 852.212-71 GRAY MARKET AND COUNTERFEIT ITEMS (FEB 2023) | 72 |
| C.12 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION) | 73 |
| C.13 VAAR 852.219-76 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SUPPLIES AND PRODUCTS (JAN 2023) (DEVIATION) | 76 |
| C.14 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 78 |
| C.15 VAAR 852.237-75 KEY PERSONNEL (OCT 2019) | 79 |
| C.16 VAAR 852.239-70 SECURITY REQUIREMENTS FOR INFORMATION TECHNOLOGY RESOURCES (FEB 2023) | 79 |
| C.17 VAAR 852.239-71 INFORMATION SYSTEM SECURITY PLAN AND ACCREDITATION (FEB 2023) | 81 |
| C.18 VAAR 852.239-72 INFORMATION SYSTEM DESIGN AND DEVELOPMENT (FEB 2023) | 82 |
| C.19 VAAR 852.239-73 INFORMATION SYSTEM HOSTING, OPERATION, MAINTENANCE, OR USE (FEB 2023) | 82 |
| C.20 VAAR 852.239-74 SECURITY CONTROLS COMPLIANCE TESTING (FEB 2023) | 85 |
| C.21 VAAR 852.239-76 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY (FEB 2023) | 85 |
| C.22 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 86 |
| C.23 VAAR 852.246-71 REJECTED GOODS (OCT 2018) | 86 |
| C.24 VAAR 852.247-71 DELIVERY LOCATION (OCT 2018) | 86 |
| C.25 VAAR 852.247-73 PACKING FOR DOMESTIC SHIPMENT (OCT 2018) | 87 |
| C.26 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 87 |
| C.27 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (FEB 2024) | 88 |
| C.28 MANDATORY WRITTEN DISCLOSURES | 96 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 97 |
| BUSINESS ASSOCIATE AGREEMENT BETWEEN THE DEPARTMENT OF VETERANS AFFAIRS VETERANS HEALTH ADMINISTRATION, , AND | 97 |
| SECTION E - SOLICITATION PROVISIONS | 103 |
| E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (SEP 2023) | 103 |
| E.3 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021) | 112 |
| E.4 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 114 |
| E.5 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023) | 117 |
| E.6 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 118 |
| E.7 52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION (NOV 2021) | 119 |
| E.8 52.216-1 TYPE OF CONTRACT (APR 1984) | 123 |
| E.9 52.225-6 TRADE AGREEMENTS CERTIFICATE (FEB 2021) | 124 |
| E.10 52.233-2 SERVICE OF PROTEST (SEP 2006) | 124 |
| E.11 VAAR 852.209-70 ORGANIZATIONAL CONFLICTS OF INTEREST (OCT 2020) | 125 |
| E.12 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 125 |
| E.13 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 126 |
| E.14 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023) | 126 |
| E.15 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 127 |
| E.16 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (FEB 2024) | 127 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer 36C248 Moneque Rodriguez Department of Veterans Affairs Network Contracting Office 8 (NCO 8)
10,000 Bay Pines Blvd Bay Pines FL 33744
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [X] |
| 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or |
| [] |
| 52.232-36, Payment by Third Party |
3. INVOICES: Invoices shall be submitted in arrears:
| a. Quarterly | [] |
| b. Semi-Annually | [] |
| c. Other | [X] Upon Delivery and Government Acceptance |
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
B.2 STATEMENT OF NEED
Statement of Need Replacement Physiological Monitoring and Telemetry System Bay Pines VA Healthcare System GE CareScape (Brand Name or Equal) Dated: May 06, 2024
1. Introduction
The Bay Pines VA Healthcare System (BPVAHCS) is seeking to replace its existing physiological monitoring and telemetry system at the C.W. Bill Young VA Medical Center at 10000 Bay Pines Blvd., Bay Pines, FL 33744 and Lee County Healthcare Center at 2489 Diplomat Parkway East, Cape Coral, FL 33909.
The salient characteristics listed throughout this Statement of Need have been identified by BPVAHCS clinical and technical staff to provide the most appropriate replacement and to ensure the best possible patient care.
2. Overview
2.1. Locations: All work will be performed at the C.W. Bill Young VA Medical Center Campus located at 10000 Bay Pines Boulevard, Bay Pines, Florida 33744, and Lee County Healthcare Center located at 2489 Diplomat Parkway East, Cape Coral, Florida 33909. All packaging will be delivered to the warehouse (Building 36) located at the C.W. Bill Young VA Medical Center Campus. Additionally, the physiological monitoring system will be installed on multiple floors in multiple buildings (Building 100, Building 106, and Building 2) located on the C.W. Bill Young VA Medical Center Campus.
2.1.1. Physiological monitoring is currently used at the C.W. Bill Young VA Medical Center between adjoining buildings (Building 100 and 106) within the following patient care locations:
· Ambulatory Surgery Unit (ASU)
· Bronchoscopy
· Catheterization (Cath) Labs
· Computerized Tomography (CT) Holding Area
· Emergency Department (ED)
· Gastroenterology (GI)
· Hybrid Operating Room (OR)
· Inpatient Wards
· Main Operating Rooms (OR)
· Medical Intensive Care Unit (MICU)
· Outpatient Surgery Center (OSC) Operating Room
· Outpatient Surgery Center (OSC) Pre and Post Anesthesia Care Unit (PACU)
· Main Post Anesthesia Care Unit (PACU)
· Surgical Intensive Care Unit (SICU)
· Telemetry
2.1.2. Telemetry is currently used to monitor patients at the C.W. Bill Young VA Medical Center on the General Medical Surgical Wards on 3D, 4A, 5A, 5B, 5C, and 5D located in Building 100. The telemetry coverage will be expanded to monitor patients throughout the hospital, including all five (5) occupied floors of Building 100 and 106.
2.1.3. Physiological monitoring is currently used at the Lee County Healthcare Center within the following patient care locations:
· Ambulatory Care Center (ACC)
· Operating Room
· Pre and Post Anesthesia Unit
· Post Anesthesia Care Unit (PACU)
3. General Requirements
3.1. Except for items explicitly identified as government-furnished property and services, the Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, and other items and non-personal services necessary to the work defined in this statement of need (SON), including but not limited to server related hardware, PICIS and any of the clinical systems that will connect to patient monitoring. The Contractor shall perform to the standards in this statement of need. BPVAHCS requires removal of the old system and goods and services to engineer, furnish, install, test a new physiological monitoring system. The solution must include skilled technical personnel and required hardware and software. Inherent in providing these services, the Contractor shall supply the management and operational resources necessary for efficient and effective administration, operation, maintenance, and control of all duties to be performed pursuant to this statement of need.
3.1.1. The Contractor shall provide equipment and middleware compatible with the Picis clinical information system, Phillips eICU system, Cerner Careware BMDI, and Vocera. The Contractor shall ensure adequate resources are dedicated to satisfying the requirements of work assignments.
3.1.2. All equipment offered shall be approved by the Food and Drug Administration (FDA) and listed on the Contractor’s contract at the time of the proposal submission.
3.1.3. Contractor to deliver, install, test, and train staff (all shifts for inpatient locations) on Physiological Patient Monitoring and Telemetry Systems, including hardware and software.
4. Specific Requirements
4.1. The Contractor shall be responsible for the removal of the old system including, but not limited to removal of all cabling and monitors.
4.2. The Contractor shall provide all materials and labor to deliver, assemble, configure, install, and test all physiological monitoring and telemetry hardware, software, and network cabling in their end location.
4.3. Current cabling installed does not meet the latest standards, however, if compatible with the Offeror’s proposed system, the current cabling may be utilized. However, all new cabling must be installed pursuant to the latest VA Telecommunications (data cable) Design Standards - OIT-InfrastrucStdTelecomSpaces-v4-0.pdf (va.gov) standards. Please note, new cabling will be required for any and all required Wireless Access Points (WAPs) as none are currently cabled. Contractor is responsible for installing any necessary conduits in accordance with the National Electric Code. The National Electric Code is also known as NFPA 70. General requirements for wiring materials and methods are covered in Article 300. Chapter 3 covers all wiring materials and methods.
4.4. The end location for each device will be coordinated between the Contractor and the VA Contracting Officer Representative (COR).
5. Onsite Site Assessment:
The Contractor shall provide onsite site assessment within 30 days of award at each location to ensure the VA has sufficient infrastructure (i.e., power, data jacks, bandwidth, HVAC, etc.). The Contractor is not required to provide any changes to the infrastructure or any accessories, however, the assessment shall identify if any infrastructure changes or network equipment are necessary to support the system.
6. Contractor Project Management Plan:
6.1. The Contractor shall submit a Contractor Project Management Plan (CPMP) within 60 days of award for VA approval. VA shall have the sole authority to approve the CPMP, however, such approval will not be unreasonably withheld. The CPMP shall document the Contractor’s approach, timeline, and tools to be used in the execution of the contract. The CPMP should take the form of both a narrative and graphic format that displays the schedule, milestones, risks, and resource support. The CPMP shall provide at minimum the following information:
6.1.1. The Project Manager who shall serve as the single point of contact between the VA and the Contractor to coordinate all aspects of site survey, site preparation, network integration, modality integration, other information system integration, equipment installation, testing, and customer training. The dedicated Project Manager will design and implement the system configuration and installation.
6.1.2. An implementation plan for the removal of the old system, installation, configuration, and validation/ testing of all hardware, software, and network configurations for the physiological monitoring and telemetry system.
· A network diagram for each location, to include ports and protocol communication.
· Complete schedules for each installation location.
· A separate schedule for each location as well as an overall schedule for the entire project.
· Schedules shall include timelines which capture relevant milestones and project sequencing, to include all testing and deployment of equipment.
6.1.3. Proposed frequency and plan to schedule project meetings. Shall include a description of the plan to properly document such meetings, to include meeting minutes and follow-up action items.
6.1.4. List of all documents required for the project and plan for ensuring that all project and VA documentation is completed and delivered to the VA.
6.1.5. Schedule for recurring project meetings.
6.2. The Contractor shall update and maintain the VA-approved CPMP throughout the period of deployment, providing a schedule of downtime to clinical services and delivery of equipment (pallet #’s and shipping lists should be sent out in advance for proper inventory).
6.3. Deliverables
6.3.1. Contractor Project Management Plan (CPMP)
7. Delivery
7.1. The Contractor shall deliver all packaging to C.W. Bill Young VA Medical Center (Building 36, 10000 Bay Pines Boulevard, Bay Pines, Florida 33744) and Lee County Healthcare Center (2489 Diplomat Parkway East, Cape Coral, FL 33909). All deliveries shall be accompanied by a ‘Delivery Document’ which clearly describes all equipment being delivered, including serial number, and other relevant logistical information. Deliveries shall be scheduled between Monday and Friday, 8 AM and 4 PM, excluding Federal Holidays.
7.2. Deliverables
7.2.1. Physical Inventory and Delivery Document
8. Assembly, Configuration, and Deployment:
8.1. The Contractor must define the need for a staging area to accommodate item delivery and processing, if needed. The VA will be informed of the area of space needed, and the VA will provide instructions on where to stage equipment. This information will be confirmed with the Contractor post-award.
8.2. The Contractor must have VA personnel escort in a coordinated effort for installation without disrupting patient care. Anything not impacting patient care would need at least a 1-week notification prior to execution. Anything impacting patient care would need at least a 3-week notification prior to execution. The VA retains sole discretion on what impacts patient care. For example, the inability to monitor a patient heavily impacts patient care and would need at least a 3-week notification.
8.3. The Contractor must provide tools, labor, and materials to complete the assembly and installation of the items detailed in this document.
8.4. The Contractor shall configure all equipment to allow for immediate use by VA staff prior to the removal of old equipment and the deployment of the new equipment.
8.5. The Contractor shall remove all old physiological monitoring or telemetry equipment and transport it to a specific location on campus, identified by VA staff and communicated through the VA COR.
8.6. The Contractor shall deploy all equipment to a specific location identified by VA staff and communicated through the VA COR.
8.7. The Contractor shall dispose of the cardboard and other packing material associated with the physiological monitoring system. VA will not provide a dumpster for disposal.
9. Testing:
9.1. The Contractor shall test all physiological monitors, telemetry transceivers, cabling and all other associated equipment and network configuration to ensure that they are fully functional prior to patient use. Should the equipment fail any test, the Contractor is solely responsible for making adjustments needed to ensure they are fully functional at no additional cost to the Government.
9.2. Proof of full functionality must be provided to the Government. In addition, the Contractor shall provide the VA COR with all documentation completed by the Contractor for testing.
9.3. Deliverables
9.3.1. Cabling Test Certification
9.3.2. Calibration Certification on all patient monitors
10. Warranty:
10.1. The Contractor shall provide a minimum of one (1) year parts, components of the physiological monitoring and telemetry systems and labor warranty for all work performed and equipment provided by the Contractor, including but not limited to cabling and accessories.
10.2. Deliverables
10.2.1. Copy of manufacturer’s warranties for Section 11.1.
11. Training:
11.1. The Contractor shall provide onsite training to all staff specified below using the physiological monitoring system. A separate training session shall be provided for both the day shift and the night shifts. The trainings shall be scheduled during the respective shift times. Contractor shall provide a training plan to sufficiently train all staff at least 90 days prior to the “go-live” date. VA shall have final approval over the training plan.
11.1.1. C.W. Bill Young VA Medical Center
| Department |
| Quantity of staff |
| Ambulatory Surgery Unit (ASU) |
| Twenty-Two (22) nursing staff |
| Bronchoscopy |
| Two (2) nursing staff |
| Catheterization (Cath) Labs |
| Five (5) nursing staff |
| Computerized Tomography (CT) Holding Area |
| Seven (7) nursing staff |
| Emergency Department (ED) |
| Twelve (12) health technicians |
| Gastroenterology (GI) |
| Sixteen (16) nursing staff |
| Hybrid Operating Room (OR) |
| Five (5) anesthesia staff |
| Inpatient Wards |
| Two Hundred Eighty-Eight (288) Nurses |
| Main Operating Rooms (OR) |
| Thirty-Six (36) anesthesia staff |
| Medical Intensive Care Unit (MICU) |
| Included in Inpatient Wards |
| Outpatient Surgery Center (OSC) Operating Room (OR) |
| Included in OR |
| Outpatient Surgery Center (OSC) Pre and Post Anesthesia Care Unit (PACU) |
| Five (5) Nurses |
| Main Post Anesthesia Care Unit (PACU) |
| Five (5) Nurses |
| Surgical Intensive Care Unit (SICU) |
| Included in Inpatient Wards |
| Telemetry |
| Fifteen (15) Medical Instrument Technicians |
Twelve (12) Health Technicians
11.1.2. Lee County Healthcare Center
| Department |
| Quantity of staff |
| Ambulatory Care Center (ACC) |
| Seven (7) Nurses |
| Operating Room (OR) |
| Twenty (20) Nurses |
| Gastroenterology (GI) |
| Eight (8) anesthesia staff |
| Pre and Post Anesthesia Unit |
| Seven (7) nursing staff |
| Post Anesthesia Care Unit (PACU) |
| Eight (8) nursing staff |
11.2. The Contractor shall additionally provide onsite training to two (2) Biomedical Engineering Staff at each location. The training must be equivalent to what original equipment manufacturer (OEM) field service representatives receive. The Contractor shall provide all service manuals, schematics, diagrams, diagnostic software, and hardware keys equivalent to what OEM field service representatives have available to diagnose, troubleshoot, repair, and maintain the equipment.
11.3. The Contractor shall additionally provide in-depth “super user” training to 50 VA Staff Members designated by the BPVAHCS. Super user training should allow staff to understand the Patient Monitoring system and allow them to provide tips and tricks to other staff members.
11.4. All training will be scheduled at least one month prior to the training by the Contractor and VA.
11.5. Deliverables:
11.5.1. Training Plan
11.5.2. Training Sessions
11.5.3. Training Attendance
12. Ongoing Support:
12.1. The Contractor shall be capable of providing technical support 24 hours a day, 7 days a week, 365 days a year over the phone to the hospital for the warranty time frame. The contractor shall install all software patches released during the warranty period to equipment covered under this contract.
12.2. The Contractor shall provide any upgraded service manuals, schematics, diagrams, diagnostic software, and hardware keys free of charge for the warranty time frame. An updated network diagram with any changes shall be provided to the VA (including server, switch, monitor, repeaters names and locations, electrical power source, etc.).
12.3. Any offsite maintenance or support provided by the Contractor can only be done via Virtual Private Network (VPN) access. The contractor shall provide routine patching for the duration of the warranty period. The Contractor shall maintain VPN access from their existing VA Business Associates Agreement (BAA) and Memorandum of Understanding/Interconnection Security Agreement (MOU/ISA). These documents shall be maintained and updated as needed for the life of the system.
12.4. Deliverables:
12.4.1. Any updated service manuals
12.4.2. Any updated schematics
12.4.3. Any updated diagrams
12.4.4. Any updated diagnostic software
12.4.5. Hardware keys
12.4.6. VA Business Associates Agreement (BAA) and Memorandum of Understanding/Interconnection Security Agreement (MOU/ISA)
13. Professional Services:
13.1. The Contractor shall provide a Project Manager, who shall be considered Key Personnel, to perform supervisory services during contract performance. The Project Manager must possess a Project Management certification as well as at least two (2) years of experience providing project management services in a healthcare environment.
14. Deployment and Implementation:
14.1. All deployment shall be completed during regular business hours, local time, Monday through Friday, 7:00 AM EST to 4:00 PM EST. All deliveries will be sent to the C.W. Bill Young VA Medical Center and coordinated with the identified VA site point of contact. The Contractor’s employees shall adhere to the VA site’s physical access policy. No equipment shall be shipped to the VA without prior approval.
15. Salient Characteristics
15.1. Technical Features
15.1.1. Background Information- The servers for the current physiological monitoring system at C.W. Bill Young VA Medical Center are in a separate building from the main hospital. The servers are in the main hospital at Lee County Healthcare Center.
15.1.2. Software
· The operating system for all network components including but not limited to, physiological monitors, transport monitors, telemetry transmitters, central stations, and servers shall be supported by the operating system’s manufacturer
15.1.3. Hardware
· Mounting hardware will be needed to mount equipment, including but not limited to, patient monitors and servers.
· Servers
· Virtual servers capable of residing on our current hosts or additional hosts will be provided.
· The server hardware will include a provision for redundancy or an automatic fail-over server.
· If a physical server is required, it will be mounted in a VA-provided rack.
15.1.4. Configuration
· The Contractor will configure the physiological monitoring and telemetry including but not limited to alarm settings and unit-specific settings, subject to ultimate approval by VA.
· The physiological monitoring system will communicate to the VA medical center’s IT network through a single gateway.
15.1.5. Deliverables
· Completed VA Directive 6550, Appendix A that covers both the physiological monitoring and telemetry systems for all item(s) that may connect to the VA network and medical devices that store sensitive patient information. Any connections to the VA Office of Information Technology network shall comply with VA Directives 6500 and 6550.
· VA Business Associates Agreement (BAA) and Memorandum of Understanding/Interconnection Security Agreement (MOU/ISA).
· Completed Manufacturer Disclosure Statement for Medical Device Security (MDS2) that covers both the physiological monitoring and telemetry systems.
· Technical specifications for all hardware, software, and components of the physiological monitoring and telemetry systems.
15.2. Clinical Features Below are relevant clinical features that must be available in the new physiological monitoring and telemetry system.
15.2.1. Entire Healthcare System
· The system shall be compatible with SpO2 monitoring technology (e.g., Masimo, Nellcor).
· The system shall be able to capture 12-lead electrocardiograms at the bedside in the specified units below.
· End-tidal carbon dioxide (ETCO2) must be Microstream technology.
· The physiological monitoring system must have the ability for a patient to be continuously monitored without modifying the Admit Discharge Transfer (ADT).
· The physiological monitoring system must be able to record and maintain patient vitals data for a 72-hour period (i.e., full disclosure) across all patient care areas within Bay Pines VA Healthcare System, including both C.W. Bill Young VA Medical Center and Lee County Healthcare Center.
15.2.2. Interface/ Integration - The server will be configured to meet all clinical and technical requirements outlined within this document, including interfacing with existing clinical systems.
· Picis Clinical Information System: The physiological monitoring system must be able to send patient vitals to the existing Picis clinical information system in Gastroenterology (GI), Hybrid Operating Room (OR), Main Operating Rooms (OR), Medical Intensive Care Unit (MICU), Outpatient Surgery Center (OSC) Operating Room (OR), Outpatient Surgery Center (OSC) Pre and Post Anesthesia Care Unit (PACU), Main Post Anesthesia Care Unit (PACU), Surgical Intensive Care Unit (SICU), Lee County Healthcare Center Operating Room (OR) and Post Anesthesia Care Unit (PACU). Patient vitals will be communicated to Picis clinical information system through a RS 232 cable.
· Philips eCIU Tele-Critical Care Remote Monitoring System:The physiological monitoring system must interface with Philips eICU Tele-Critical Care remote monitoring system, as all patient beds in the MICU and SICU are configured for the Philips eICU Tele-Critical Care remote monitoring system.
· Anesthesia Machine Integration: The physiological monitoring system must display anesthesia gases from Draeger Perseus anesthesia machines. The monitors must be affixed to the anesthesia machines.
· Cerner Millennium: The physiological monitoring system must have the ability to interface with Cerner Millennium electronic health record.
· Edwards HemoSphere/ Vigilance: The physiological monitoring system must have the ability to interface with Edwards Hemosphere and Edwards Vigilance to monitor Cerebral Oximetry and minimally and invasive continuous cardiac output if the proposed system does not include cerebral oximetry monitoring and continuous cardiac output.
16. Department Specific Characteristics - C.W. Bill Young VA Medical Center
16.1. Ambulatory Surgery Unit (ASU)
16.1.1. Bedside
· Quantity: Thirteen (13) each
· Screen Size: At least 15 inches
· Touchscreen: Yes
· Mounting: Wall mounting with articulating arm
· Recorder/Strip Printer: No
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output (CO)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.1.2. Central Station
· Quantity: One (1) set
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Yes
· Printer: Networked Printer
· Number of Beds to Display: Thirteen (13)
16.2. Bronchoscopy
16.2.1. Beside Portable
· Quantity: Two (2) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s)s: ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output (CO)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.3. Catheterization (Cath) Labs
16.3.1. Bedside Portable
· Quantity: One (1) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s)s: ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output (CO)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.4. Computerized Tomography (CT) Holding Area
16.4.1. Bedside
· Quantity: Two (2) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Wall mounting with articulating arm
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output (CO)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.5. Emergency Department (ED)
16.5.1. ED Specific Characteristics
· Alarms Workflow Background: When responding to alarms that are triggered, nursing staff go to the beside physiological monitor or the satellite station to address the alarm. As much relevant information as possible must be provided at these locations. The existing physiological monitors and satellite stations can only provide up to sixteen (16) patients per monitor, and there is not enough relevant information displayed. There is a new VISN8 requirement for the ED patients to be monitored 24/7 at a central station.
· The physiological monitoring system must provide lights, visual cues, and audible alarms to provide staff with a visual understanding of the alarm.
· Alarms modification per care area is managed by the facility’s alarm committee.
16.5.2. Bedside
· Quantity: Sixteen (16) each
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Mounting: Wall mounting with articulating arm
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Temperature, Four (4) Invasive Blood Pressures (IBP), Continuous Cardiac Output (CO)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.5.3. Bedside Portable
· Quantity: Ten (10) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output (CO)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.5.4. Transport
· Quantity: Four (4) each
· Screen Size: Maximum of 10 inches
· Touchscreen: Yes
· Mounting: Docking
· Wireless: No preference
· Recorder/Strip Printer: No
· 12-Lead: No
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: Not preference
· Alarm Management Integration (Vocera): No
· Weight: Less than 5 lbs.
· Parameters: ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Temperature, Two (2) Invasive Blood Pressures (IBP)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.5.5. Central Station
· Quantity: Seven (7) sets
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Mixed
· Six (6) interactive [two (2) in the front, two (2) in the middle, and (2) in the back.]
· One (1) non-interactive [DocBox]
· Mounting: Seven (7) wall mounted
· Printer: Networked Printer
· Number of Beds to Display: Twenty-Six (26)
16.6. Gastroenterology (GI)
16.6.1. Bedside [Procedure Room]
· Quantity: Four (4) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Cart mount with non-articulating arm
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.6.2. Bedside [Recovery Room]
· Quantity: Eight (8) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.7. Hybrid Operating Room (OR)
16.7.1. Anesthesia
· Quantity: One (1) each
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Mounting: Anesthesia Machine mounting with non-articulating arm
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: No
· Edwards HemoSphere/ Vigilance Interface: Yes
· Anesthesia Agent Integration: Draeger Perseus
· Slave Monitor Capable: Yes
· Full Disclosure: 72-hour
· Alarm Management Integration (Vocera): No
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output (CO), Bilateral measurements
· Consumables: ECG leads (Reusable), SpO2 (Disposable), NIBP (Disposable)
· Neuromuscular Transmission (NMT) Module
· Quantity: One (1) each
· Bispectral Index (BIS) Module
· Quantity: One (1) each
16.8. Inpatient Wards
16.8.1. Ward 3D
· Ward Size: 24 Beds
· Bedside Portable-
· Quantity: Three (3) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.8.2. Ward 3D- Central Station
· Quantity: One (1) set
· Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Yes
· Printer: Networked Printer
· Number of Beds to Display: Twenty-Four (24)
16.8.3. Ward 4A
· Ward Size: 24 Beds
· Bedside Portable-
· Quantity: Ten (10) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.8.4. Ward 4A- Central Station
· Quantity: One (1) set
· Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Yes
· Printer: Networked Printer
· Number of Beds to Display: Twenty-Four (24)
16.8.5. Ward 5A
· Ward Size: 39 Beds
· Bedside Portable-
· Quantity: Three (3) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.8.6. Ward 5A- Central Station
· Quantity: One (1) set
· Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Yes
· Printer: Networked Printer
· Number of Beds to Display: Thirty- Nine (39)
16.8.7. Ward 5B
· Ward Size: 48 Beds
· Bedside Portable-
· Quantity: Three (3) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.8.8. Ward 5B- Central Station
· Quantity: One (1) set
· Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Yes
· Printer: Networked Printer
· Number of Beds to Display: Forty-Eight (48)
16.8.9. Ward 5C
· Ward Size : 16 Beds
· Bedside Portable-
· Quantity: Three (3) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.8.10. Ward 5C- Central Station
· Quantity: One (1) set
· Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Yes
· Printer: Networked Printer
· Number of Beds to Display: Sixteen (16)
16.8.11. Ward 5D
· Ward Size: 24 Beds
· Bedside Portable-
· Quantity: Three (3) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.8.12. Ward 5D- Central Station
· Quantity: One (1) set
· Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Yes
· Printer: Networked Printer
· Number of Beds to Display: Twenty-Four (24)
16.9. Main Operating Rooms (OR)
16.9.1. Anesthesia
· Quantity: Nine (9) each
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Mounting: Anesthesia Cart mounting with non-articulating arm
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: No
· Edwards HemoSphere/ Vigilance Interface: Yes
· Anesthesia Agent Integration: Draeger Perseus
· Slave Monitor Capable: Yes
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): No
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output (CO), Bilateral measurements
· Consumables: ECG leads (Reusable), SpO2 (Disposable), NIBP (Disposable)
· Neuromuscular Transmission (NMT)
· Quantity: Nine (9) each
· Bispectral Index (BIS)
· Quantity: Nine (9) each
16.9.2. Anesthesia Portable
· Quantity: Five (5) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Anesthesia Cart mounting with non-articulating arm
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: No
· Edwards HemoSphere/ Vigilance Interface: Yes
· Slave Monitor Capable: Yes
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output, Bilateral measurements , Gas Output
· Consumables: ECG leads (Reusable), SpO2 (Disposable), NIBP (Disposable)
· Neuromuscular Transmission (NMT)
· Quantity: Five (5) each
· Bispectral Index (BIS)
· Quantity: Five (5) each
16.10. Medical Intensive Care Unit (MICU)
16.10.1. MICU Specific Characteristics
· Background - The highest level of acuity patients in both the MICU and SICU are patients who are ventilated, need Roto-Prone therapy, need continuous renal replacement therapy(CRRT), have arterial lines, are having their central venous pressure monitored, have a Swan-Ganz catheterization (occasionally), or have a need for an intra-aortic balloon pump or Impella device for cardiac support.
· Alarms Workflow Background- When responding to alarms that are triggered, nursing staff go to the beside physiological monitor or the satellite station to address the alarm. As much relevant information as possible must be provided at these locations.
· With respect to combo mode with telemetry monitoring on the unit, the clinical staff must be able to use a smaller transport monitor to utilize when ambulating patients.
· The transport monitor or telemetry box must continue to send patient data to the patient chart without modifying Admit Discharge Transfer (ADT).
· Strips must automatically print when an alarm is triggered to a central monitor laser printer.
· The physiological monitoring system shall provide the ability to digitally capture strips and print them, if needed by staff.
· The physiological monitoring system must provide lights, visual cues, and audible alarms to provide staff with a visual understanding of the alarm.
· Alarms modification per care area is managed by the facility’s alarm committee.
16.10.2. Bedside
· Quantity: Eleven (11) each
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Mounting: Wall mounting with articulating arm
· Recorder/Strip Printer: No
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: Yes
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Temperature, Four (4) Invasive Blood Pressures (IBP), Continuous Cardiac Output (CO), Bilateral measurements
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
· Neuromuscular Transmission (NMT)
· Quantity: Two (2) if portable. If not portable, one (1) for every bedside
· Bispectral Index (BIS)
· Quantity: Two (2) if portable. If not portable, one (1) for every bedside
16.10.3. Bedside Portable
· Quantity: One (1) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Bed Mount
· Wireless: Yes
· Battery Operated: Minimal of one-hour runtime
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Temperature, Four (4) Invasive Blood Pressures (IBP), Continuous Cardiac Output (CO)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.10.4. Transport
· Quantity: Six (6) each
· Screen Size: Maximum of 10 inches
· Touchscreen: Yes
· Mounting: Docking
· Wireless: No preference
· Recorder/Strip Printer: No
· 12-Lead: No
· Picis Clinical Information System Interface: No
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: Not preference
· Alarm Management Integration (Vocera): No
· Weight: Less than 5 lbs.
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Temperature, Two (2) Invasive Blood Pressures (IBP)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.10.5. Central Station
· Quantity: Three (3) sets
· Screen Size: At least 19 inches, dual screen
· Touchscreen: Yes
· Interactive: Yes
· Mounting: Desk mounted
· Printer: Networked Printer
· Number of Beds to Display: Eleven (11)
16.10.6. Satellite Central Station
· Quantity: Six (6) sets
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Yes
· Mounting: Wall mounted
· Printer: No printer
16.11. Outpatient Surgery Center (OSC) Operating Room (OR)
16.11.1. Anesthesia
· Quantity: Four (4) each
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Mounting: Anesthesia Cart mounting with non-articulating arm
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: No
· Anesthesia Agent Integration: Draeger Perseus
· Slave Monitor Capable: Yes
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output (CO), Bilateral measurements, Cerebral Oximetry
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Disposable)
· Neuromuscular Transmission (NMT)
· Quantity: Four (4) each
· Bispectral Index (BIS)
· Quantity: Four (4) each
16.12. Outpatient Surgery Center (OSC) Pre and Post Anesthesia Care Unit (PACU)
16.12.1. Bedside
· Quantity: Thirteen (13) each
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Mounting: Wall mounting with articulating arm
· Recorder/Strip Printer: No
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Temperature, Four (4) Invasive Blood Pressures (IBP), Continuous Cardiac Output (CO)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.12.2. Bedside Portable
· Quantity: One (1) each
· Screen Size: At least 12 inches
· Touchscreen: Yes
· Mounting: Rolling Stand
· Wireless: Yes
· Recorder/Strip Printer: Yes
· 12-Lead: Yes
· Picis Clinical Information System Interface: Yes
· Philips eICU Tele-Critical Care Interface: No
· Full Disclosure: 72-hours
· Alarm Management Integration (Vocera): Yes
· Parameter(s): ECG 5-lead, SpO2, End-tidal carbon dioxide (EtCO2), NIBP, Respiratory Rate (RR), Temperature, Four (4) Invasive Blood Pressures, Continuous Cardiac Output (CO)
· Consumables: ECG leads (Disposable), SpO2 (Disposable), NIBP (Reusable)
16.12.3. Central Station
· Quantity: One (1) set
· Screen Size: At least 19 inches
· Touchscreen: Yes
· Interactive: Yes
· Mounting: One (1) desk mounted
· Printer: Networked…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .