36C24824Q0925_2.docx

DOCX document 19 KB Posted

Attached to
J063--Canceled FY24: GVL Boiler Remote Alarm Panel Install
Solicitation number
36C24824Q0925
Issued by

About this file

This document is an amendment to a previous combined solicitation (Request for Quotations) for a Boiler Remote Alarm Panel Install service contract at the Gainesville VAMC. The key details are:

The solicitation number is 36C24824Q0925, and the service is for the North Florida/South Georgia Veterans Health System. This is a one-time, SDVOSB set-aside contract with a period of performance from 06/28/2024 to 06/27/2025. The amendment extends the response date to 05/31/2024 at 12:00 PM EST and provides answers to several questions, including confirmation that this is a brand new contract with no incumbent, and that the remote panel needs to communicate with the SCADA system. Pricing should include parts, labor, and freight for the installation of the conduit and wiring. The government will use a comparative evaluation process to determine the best value quotation.

View the file

Other files

File Type Posted
36C24824Q0925_5.docx DOCX document
36C24824Q0925_4.docx DOCX document
36C24824Q0925_3.docx DOCX document
36C24824Q0925_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment to a Previous Combined Solicitation

Amendment to a Previous Combined Solicitation

SUBJECT*
FY24: GVL Boiler Remote Alarm Panel Install

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
32601-3460
SOLICITATION NUMBER*
36C24824Q0925
RESPONSE DATE/TIME/ZONE
05-31-2024 12:00 pm EASTERN TIME, NEW YORK, USA
ARCHIVE
60 DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
N
SET-ASIDE
SDVOSBC
PRODUCT SERVICE CODE*
J063
NAICS CODE*
238210
CONTRACTING OFFICE ADDRESS
Department of Veterans Affairs

Network Contracting Office 8 (NCO 8) C/O Yolanda Glover yolanda.glover@va.gov

POINT OF CONTACT*

Contract Specialist Yolanda Glover yolanda.glover@va.gov 352-381-5712

PLACE OF PERFORMANCE

ADDRESS
Malcolm Randall VAMC

1601 SW Archer Road

Gainesville Florida

POSTAL CODE
32608
COUNTRY
USA

ADDITIONAL INFORMATION

AGENCY’S URL

URL DESCRIPTION

AGENCY CONTACT’S EMAIL ADDRESS

EMAIL DESCRIPTION

DESCRIPTION

The Purpose of this Amendment is to:

1) Extend the closing date to 05/31/2024 at 12:00 PM EST.

2) Answer questions for RFQ# 36C24824Q0925.

Question: Is this a brand new contract?

Answer: Yes

Question: Is there an incumbent performing these services?

Answer: No

Question: Provide the current / previous contract number?

Answer: N/A

Question: Is there an actual start date for the project?

Answer: No

Question: DA Steam Relief Valve – Is this the relief valve directly on the DA tank(DASV), or the on the steam line feeding the DA tank, after the PRV (SRFPRV)?

Answer: On the DA Tank Contractor stated-à( Per VHA safety device manual 8th edition, the DASV on the DA tank is required to have a capacity of approximately 1000 lb/hr., and setpoint pressure 5psig higher than normal DA Tank pressure, while the SRFPRV is required to have setpoint 5 psig higher than DASV, which may place it higher than the requested 15psig setpoint).

Question: In absence of project specific plans and specs, will the new remote alarm panel be required to meet Master TIL 23 09 11, pp2.3.J. Annunciator?

Answer: Yes

Question: Is the intent to have the remote panel be a stand-alone unit, or will it need to communicate alarm states back to plant master or SCADA workstation?

Answer: Needs to communicate with the SCADA

Question: Are there additional contacts on the existing, local DA & Surge tank alarms that can be used for the remote panel, or will additional devices be required to be installed?

Answer: No

Question: Does the existing MSA CP Monitoring system have the expansion capability to accept the two new CO sensors, or will it need to be updated with the additional channels?

Answer: Unknown. System is out for repairs. Cannot provide details on it.

Question: What is the manufacturer’s model number of the existing MSA CP Monitoring system? Answer: Unknown. System is out for repairs. Cannot provide details on it.

Contractor stated--à(There are several controllers listed that are discontinued, so support for these older models may not be available.)

Question: Is this CLIN for the wire required for the project, or is it for spares?

Answer: Wire required for the project Contractor stated--à(The CLIN line item 5 requests separate pricing for qty(1) roll of wire. This does not specify the type of wire, number of conductors, length of spool, etc…)

Question: Is this conduit for the installation portion of the project?

Answer: Exact measurements should be taken by contractor. But Qty (10) is in 10’ sections. Therefore the total length is approx. 100’ Contractor stated-à(The CLIN line item 4 requests separate pricing for Qty(10) conduit. This line item does not specify length of each conduit, or size.)

Question: Is the pricing for the wire and conduit to be removed from CLIN 2 & 3, and only include as parts the devices, hangers, fittings, and other misc. parts required for the installation?

Answer: Pricing should include parts required for installation of conduit and wiring.

Contractor stated-à(CLIN line items 2 & 3 requests pricing to include parts, labor and freight. The conduit and wire pricing for CLIN line items 4 & 5, would be included in the “Parts” portion of CLIN 2 & 3.)

*= Required Field
Amendment to a Previous Combined Solicitation

Page 1 of

Amendment to a Previous Combined Solicitation