36C24822R0125 0004_1.docx
DOCX document 36 KB Posted
- Solicitation number
- 36C24822R0125
About this file
This document is a modification to a previous solicitation for corrective work at a Department of Veterans Affairs building in Miami, Florida. The solicitation requests bids to correct NEC deficiencies and infrastructure at Building 44, with a response date of August 23, 2022. The work includes constructing, furnishing and installing all items per the statement of work and specifications. An optional bid alternate is also provided to replace digital protection relays at the building's electrical switchgear. The document provides answers to vendor questions to clarify the scope of work regarding wall construction, louver controls, door and hardware specifications, lighting requirements, conduit and shutdown coordination. Attachments include issued-for-construction drawings and specifications to address the questions. The solicitation number is 36C24822R0125 and is set aside for SDVOSBC. The contracting agency is the Department of Veterans Affairs Network Contracting Office 8 located in Miami, Florida.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ISSUED FOR CONSTRUCTION - Specs 2022 03 23 (1).pdf | ||
| ISSUED FOR CONSTRUCTION - Dwgs 2022 03 23.pdf | ||
| 36C24822R0125 0003_1.docx | DOCX document | |
| 36C24822R0125 0002_1.docx | DOCX document | |
| 36C24822R0125 0001_1.docx | DOCX document | |
| S02 - ATTACHMENT 5 - SPECIALIZED EXPERIENCE FROM.pdf | ||
| S02 Attachment 8 drawings - 546 21 102 Correct NEC Deficiencies Final Submittal.pdf | ||
| S02 Attachment 6 - 546 2 1 102 Site Plan.pdf | ||
| 36C24822R0125_2.docx | DOCX document | |
| S02 - ATTACHMENT 3 - EMR (1 PAGE).docx | DOCX document | |
| Attachment 1 - Wage Determination.pdf | ||
| S02 - ATTACHMENT 4- PAST PERFORMANCE QUESTIONNAIRE.pdf | ||
| S02 ATTACHMENT 2- PRICE MATRIX.xlsx | XLSX spreadsheet | |
| S02 Attachment 7 - 546 21 102 Correct NEC Deficiencies Final Submittal App.pdf | ||
| 36C24822R0125.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUBJECT*
(PROJ: 546-21-102) B/B Correct NEC Deficiencies & Infrastructure at Building 44
GENERAL INFORMATION
| CONTRACTING OFFICE’S ZIP CODE* |
| 33125 |
| SOLICITATION NUMBER* |
| 36C24822R0125 |
BASE NOTICE TYPE
| RESPONSE DATE/TIME/ZONE |
| 08-23-2022 1:00 PM EASTERN TIME, NEW YORK, USA |
| ARCHIVE |
| 60 DAYS AFTER THE RESPONSE DATE |
| RECOVERY ACT FUNDS |
| N |
| SET-ASIDE |
| SDVOSBC |
| PRODUCT SERVICE CODE* |
| Y1DA |
| NAICS CODE* |
| 236220 |
| CONTRACTING OFFICE ADDRESS |
| Department of Veterans Affairs |
Network Contracting Office 8 (NCO 8) Miami VA Healthcare System 1201 NW 16th Street Miami FL 33125
POINT OF CONTACT*
Contracting Officer Duwane B. Snyder Duwane.Snyder@va.gov 305-339-0404
PLACE OF PERFORMANCE
| ADDRESS |
| Department of Veterans Affairs |
Miami VA Healthcare System
Bruce W. Carter Medical Center
1201 NW 16th Street
Miami FL
| POSTAL CODE |
| 33125 |
| COUNTRY |
| USA |
ADDITIONAL INFORMATION
AGENCY’S URL
URL DESCRIPTION
AGENCY CONTACT’S EMAIL ADDRESS
EMAIL DESCRIPTION
DESCRIPTION
Modification to a Previous Notice Modification to a Previous Notice Please see RFI and drawings below.
| *= Required Field |
| Modification to a Previous Notice |
Modification to a Previous Notice
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 546-21-102 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Miami VA Healthcare System 1201 NW 16th Street Miami FL 33125 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Miami VA Healthcare System
1201 NW
16th Street Miami FL 33125 To all Offerors/Bidders
36C24822R0125
X X X
See CONTINUATION Page The purpose of this Amendment is as follows:
1. To add Bid Alternate as Line Item 0002.
2. Provide answers to vendor's RFI.
3. Provide a link for all construction documents
Page 1 of Please see below.
A.1 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Construct, furnish and install all items as per the SOW and the supplied 100% design and specifications to correct NEC Deficiencies in BLDG. 44.
NAICS CODE: 238220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2AA - Repair or Alteration of Office Building.
| 1.00 |
| JB |
| __________________ |
| __________________ |
BID ALTERNATE 1. EXISTING SQUARE D 15KV MASTER CLAD, METAL CLAD SWITCHGEAR, MVSN-3UPA, 3UPB, AND 3UPC. CONSULT MANUFACTURER TO REPLACE THE DIGITAL PROTECTION RELAY SYSTEM, PROGRAM AND COMMISSION THE SYSTEM.
| GRAND TOTAL |
| __________________ |
CONTINUATION PAGE
Answers to RFI
1. Per Sheet A‐101, note #01, please confirm that the existing CMU wall is grouted solid at new door opening locations. If this cannot be confirmed, should we assume the walls are grouted solid and price only filling grout at the new masonry/masonry frames. Assume walls are not grouted and provide as required. Clarification will be provided in “ISSUED FOR CONSTRUCTION” documents.
2. Per head details H1 and H2 on sheet A‐501, the details show two (2) courses of CMU at the header locations stating, "existing 2‐HR CMU wall, grout solid.” Does this statement mean that the existing header conditions are grouted solid already or does the Contractor need to grout them during the project? If contractor must grout them, please advise on how many inches and/or courses will need to be grout filled at these locations. Will be provided in “ISSUED FOR CONSTRUCTION” documents.
3. Per note #02 on sheet A‐101, will controls be required for the louvers. Please advise on the sequencing in addition to the specifications for controls. The existing louver is being relocated. Any existing connections and controls would be relocated with the louver. Will be provided in “ISSUED FOR CONSTRUCTION” documents.
4. Per the Door Schedule as shown on sheet A‐501, the schedule indicates that there are doors, frames, and finish hardware (Door #307 and #308) on this project. Please provide the door and finish hardware specifications along with proposed hardware sets since they are currently not included in the Bid Documents. Will be provided in “ISSUED FOR CONSTRUCTION” documents.
5. Please provide specifications for overhead coiling door shown on sheet A‐501 (Door #301).
Will be provided in “ISSUED FOR CONSTRUCTION” documents.
6. Per General Electrical Note #3 on sheet E‐001, it states "update all panel schedules within the building…" Please confirm that all electrical panels within the building need to be updated or clarify if only the electrical panels affected by this project will require updating. Will be updated in “ISSUED FOR CONSTRUCTION” documents.
7. Please confirm that there are no fire alarm requirements on this project. Specifically, as it relates to the louver controls. The existing louver is being relocated. Any existing connections, alarms and controls would be relocated with the louver.
8. Please confirm that there no modifications necessary to the Fire Sprinkler system on this project. No sprinkler modifications are expected. However, if the contractor notices something in this stage, they need to let COR (VA) know.
9. On the lighting fixtures, can we use an alternative fixture or only what is on the plans?
Lighting fixtures are performance based unless directed otherwise by the VA.
10. On the 1st floor the VA Staff have already done some of the work on the light fixtures, they have used PVC conduit with carapoflex for the whips. The A/E is not familiar with “carapoflex”. Are you referring to “Cabloflex”? If so and the product is acceptable to the VA, the A/E takes no exception.
11. The plans call for liquid tide for all whips but is the conduit staying or Milicon needs to replace with rigid conduit as per plans. Will be provided in “ISSUED FOR CONSTRUCTION” documents.
12. Due to the work performed, are the shutdowns that need to occur for this project to be done at nighttime and/or weekends, please advise? System shutdown will be coordinated during preconstruction. Parameters will be provided in “ISSUED FOR CONSTRUCTION” documents.
13. There is no specification for epoxy floor repairs. If existing floor is epoxy only work is to repair any damaged finishes to match existing. Parameters will be provided in “ISSUED FOR CONSTRUCTION” documents.
14. Who is the Manufacture of the existing epoxy floor supplier? VA direction required for all existing finishes.
15. Contact for local manufacture representative. VA direction required for all existing finishes.
16. The location of new door # 307 has electrical conduits on outside of wall at new door location (see attached picture). Where do you want to relocate door #307? “Attached picture” mentioned above was not provided for review. Door location will be updated in “ISSUED FOR CONSTRUCTION” documents.
17. There are no door & frame specifications & no hardware schedule & specifications or specifications for new man doors. Will be provided in “ISSUED FOR CONSTRUCTION” documents.
18. There are no overhead rolling doors specifications. Will be provided in “ISSUED FOR CONSTRUCTION” documents.
19. For installing new rolling door #301 will smooth rubbed skim patch concrete finish be acceptable for ends of cut block & filled block for widened opening? Will be provided in “ISSUED FOR CONSTRUCTION” documents.
20. There are no paint specifications for new doors & painting block walls? Will be provided in “ISSUED FOR CONSTRUCTION” documents.
Additional Corrections;
Please note revised NOTE 6 on drawing 44‐E103.1 to read:
BID ALTERNATE 1. EXISTING SQUARE D 15KV MASTER CLAD, METAL CLAD SWITCHGEAR, MVSN‐3UPA, 3UPB, AND 3UPC. CONSULT MANUFACTURER TO REPLACE THE DIGITAL PROTECTION RELAY SYSTEM, PROGRAM AND COMMISSION THE SYSTEM. CONTACT THE SCHNEIDER ELECTRIC REPRESENTATIVE, LAZ ECHEVARRIA AT (305)345‐3892, LAZ.ECHEVARRIA@SE.COM FOR PRICING.
See attached document: ISSUED FOR CONSTRUCTION - Dwg's 2022 03 23.
See attached document: ISSUED FOR CONSTRUCTION - Spec's 2022 03 23 (1).
See attached document: ISSUED FOR CONSTRUCTION - Dwgs 2022 03 23.
See attached document: ISSUED FOR CONSTRUCTION - Specs 2022 03 23 (1).