Appendix A - Cost Estimate CPMRS Pricing Sheet.xlsx

XLSX spreadsheet 41 KB Posted

Attached to
R425--West Palm Beach VA Medical Center FY21: Construction Program Management and Related Services New Contract- No Incumbent
Solicitation number
36C24821Q1184
Issued by

View the file

Other files

File Type Posted
36C24821Q1184- Final.docx DOCX document
36C24821Q1184.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Year

West Palm Beach VA Medical Center
Construction Program management and Related Services
First Contracted Year Anticipated Services *
Prepared by: William A. Stueber, PE, CORHours
PositionHourly RateEHRM ProjectESPC ProjectConceptual DesignsVarious StudiesTotal Hours/ Contract YearCost/ Contract Year
Project Consultant11114$0$0.00
Sr Construction/ Project Manager11114$0$0.00
Construction/ Project Manager1001003020250$0
Sr. Engineer1010$0
Engineer7508503001002000$0
Sr. Q/A Representative55$0
Quality Assurance Representative1010$0
Fire Protection Engineer101020$0
Commissioning Engineer8080$0
Specification Writer4040$0
Claims Analyst1010$0
Sr Estimator88824$0
Estimator16164072$0
Sr. Scheduler1010$0
Scheduler4040$0
Construction Project Coordinator404080$0
Sr. Architect88$0
Architect4040$0
Sr. Construction Inspector8816$0
Construction Inspector7508503001002000$0
Sr. Space Planner88$0
Space Planner400400$0
Sr. Cadd88$0
Cadd808010008402000$0
Sr. Project Administrator888832$0
Project Administrator40404040160$0
Clerk/ Word Processor5005005005002000$0
Contract Base Year Total$0

* Project timing and hours are only estimates and subject to change due to changes in VA and WPBVAMC priorities. Estimates are for establishing contractual hourly rates and anticipated expenditures.

Option Year 1

West Palm Beach VA Medical Center
Construction Program management and Related Services
First Option Year Anticipated Services *
Prepared by: William A. Stueber, PE, CORHours
PositionHourly RateEHRM ProjectESPC ProjectConceptual DesignsVarious StudiesTotal Hours/ Contract YearCost/ Contract Year
Project Consultant11114$0$0.00
Sr Construction/ Project Manager11114$0$0.00
Construction/ Project Manager1001003020250$0
Sr. Engineer1010$0
Engineer7508503001002000$0
Sr. Q/A Representative55$0
Quality Assurance Representative1010$0
Fire Protection Engineer101020$0
Commissioning Engineer8080$0
Specification Writer4040$0
Claims Analyst1010$0
Sr Estimator88824$0
Estimator16164072$0
Sr. Scheduler1010$0
Scheduler4040$0
Construction Project Coordinator404080$0
Sr. Architect88$0
Architect4040$0
Sr. Construction Inspector8816$0
Construction Inspector7508503001002000$0
Sr. Space Planner88$0
Space Planner400400$0
Sr. Cadd88$0
Cadd808010008402000$0
Sr. Project Administrator888832$0
Project Administrator40404040160$0
Clerk/ Word Processor5005005005002000$0
First Option Year Total$0

* Project timing and hours are only estimates and subject to change due to changes in VA and WPBVAMC priorities. Estimates are for establishing contractual hourly rates and anticipated expenditures.

Option Year 2

West Palm Beach VA Medical Center
Construction Program management and Related Services
Second Option Year Anticipated Services *
Prepared by: William A. Stueber, PE, CORHours
PositionHourly RateEHRM ProjectESPC ProjectConceptual DesignsVarious StudiesTotal Hours/ Contract YearCost/ Contract Year
Project Consultant11114$0$0.00
Sr Construction/ Project Manager11114$0$0.00
Construction/ Project Manager1001003020250$0
Sr. Engineer1010$0
Engineer7508503001002000$0
Sr. Q/A Representative55$0
Quality Assurance Representative1010$0
Fire Protection Engineer101020$0
Commissioning Engineer8080$0
Specification Writer4040$0
Claims Analyst1010$0
Sr Estimator88824$0
Estimator16164072$0
Sr. Scheduler1010$0
Scheduler4040$0
Construction Project Coordinator404080$0
Sr. Architect88$0
Architect4040$0
Sr. Construction Inspector8816$0
Construction Inspector7508503001002000$0
Sr. Space Planner88$0
Space Planner400400$0
Sr. Cadd88$0
Cadd808010008402000$0
Sr. Project Administrator888832$0
Project Administrator40404040160$0
Clerk/ Word Processor5005005005002000$0
Second Option Year Total$0

* Project timing and hours are only estimates and subject to change due to changes in VA and WPBVAMC priorities. Estimates are for establishing contractual hourly rates and anticipated expenditures.

Option Year 3

West Palm Beach VA Medical Center
Construction Program management and Related Services
Third Option Year Anticipated Services *
Prepared by: William A. Stueber, PE, CORHours
PositionHourly RateEHRM ProjectESPC ProjectConceptual DesignsVarious StudiesTotal Hours/ Contract YearCost/ Contract Year
Project Consultant11114$0$0.00
Sr Construction/ Project Manager11114$0$0.00
Construction/ Project Manager1001003020250$0
Sr. Engineer1010$0
Engineer7508503001002000$0
Sr. Q/A Representative55$0
Quality Assurance Representative1010$0
Fire Protection Engineer101020$0
Commissioning Engineer8080$0
Specification Writer4040$0
Claims Analyst1010$0
Sr Estimator88824$0
Estimator16164072$0
Sr. Scheduler1010$0
Scheduler4040$0
Construction Project Coordinator404080$0
Sr. Architect88$0
Architect4040$0
Sr. Construction Inspector8816$0
Construction Inspector7508503001002000$0
Sr. Space Planner88$0
Space Planner400400$0
Sr. Cadd88$0
Cadd808010008402000$0
Sr. Project Administrator888832$0
Project Administrator40404040160$0
Clerk/ Word Processor5005005005002000$0
Third Option Year Total$0

* Project timing and hours are only estimates and subject to change due to changes in VA and WPBVAMC priorities. Estimates are for establishing contractual hourly rates and anticipated expenditures.

Option Year 4

West Palm Beach VA Medical Center
Construction Program management and Related Services
Forth Option Year Anticipated Services *
Prepared by: William A. Stueber, PE, CORHours
PositionHourly RateEHRM ProjectESPC ProjectConceptual DesignsVarious StudiesTotal Hours/ Contract YearCost/ Contract Year
Project Consultant11114$0$0.00
Sr Construction/ Project Manager11114$0$0.00
Construction/ Project Manager1001003020250$0
Sr. Engineer1010$0
Engineer7508503001002000$0
Sr. Q/A Representative55$0
Quality Assurance Representative1010$0
Fire Protection Engineer101020$0
Commissioning Engineer8080$0
Specification Writer4040$0
Claims Analyst1010$0
Sr Estimator88824$0
Estimator16164072$0
Sr. Scheduler1010$0
Scheduler4040$0
Construction Project Coordinator404080$0
Sr. Architect88$0
Architect4040$0
Sr. Construction Inspector8816$0
Construction Inspector7508503001002000$0
Sr. Space Planner88$0
Space Planner400400$0
Sr. Cadd88$0
Cadd808010008402000$0
Sr. Project Administrator888832$0
Project Administrator40404040160$0
Clerk/ Word Processor5005005005002000$0
Forth Option Year Total$0