36C24818R0588-001.docx

DOCX document 143 KB Posted

Attached to
Renovate Ward 4A, Bldg. 100 Federal contract opportunity
Solicitation number
36C24818R0588
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

About this file

36C24818R0588 36C24818R0588_1.docx

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Ward 4A, Bldg. 100, newest first.
File Type Posted
36C24818R0588-0002000.docx DOCX document
36C24818R0588-0002001.docx DOCX document
36C24818R0588-0002004.docx DOCX document
36C24818R0588-0002003.pdf PDF
36C24818R0588-0002002.docx DOCX document
36C24818R0588-0001001.pdf PDF
36C24818R0588-0001000.docx DOCX document
36C24818R0588-007.docx DOCX document
36C24818R0588-010.pdf PDF
36C24818R0588-006.docx DOCX document
36C24818R0588-012.pdf PDF
36C24818R0588-013.docx DOCX document
36C24818R0588-004.docx DOCX document
36C24818R0588-009.pdf PDF
36C24818R0588-011.pdf PDF
36C24818R0588-002.docx DOCX document
36C24818R0588-003.docx DOCX document
36C24818R0588-008.docx DOCX document
36C24818R0588-005.docx DOCX document
36C24818R0588-000.docx DOCX document
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24818R0588

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (

Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24818R0588 X 06-01-2018

TBD

516-11-134 Department of Veterans Affairs Network Contracting Office 8 ( 248) Room 326, Bldg. 2 10,000 Bay Pines Blvd Bay Pines FL 33744 Department of Veterans Affairs Network Contracting Office 8 ( 248) Room 326, Bldg. 2 10,000 Bay Pines Blvd Bay Pines FL 33744 Rachel Reed 727.399.3308

PROJECT TITLE: RENOVATE WARD 4A, BLDG FOR INPATIENT PRIVACY

PROJECT LOCATION: BAY PINES VA HEALTHCARE SYSTEM, BAY PINES, FL.

NAICS CODE: 236220 with corresponding business size of $36.5M

MAGNITUDE OF CONSSTRUCTION FOR THIS PROJECT IS BETWEEN $5M - $10MILLION

DESCRIPTION: This is a two-phase design-build to renovate approximately 15,000SF in Ward 4A of Blgd 100, to provide a patient privacy compliant, fully handicap accessible, state-of-the-art inpatient facility.

THIS IS A SERVICE DISABLED VETERAN-OWNED SMALL BUSINESS SET ASIDE. PROSPECTIVE CONTRACTORS ARE CAUTIONED THAT ANY PROPOSAL SUBMITTED IN RESPONSE TO THIS SOLICITATION MUSST MEET THE CRITERIA IDENTIFIED BY 38 CFR, PART 74. ANY PERSON, PERSONS, OR BUSINESS ENTITY SUSPECTED OF MISREPRESENTING ITSELF

FOR THE PURPOSE OF

SECURITY A GOVERNMENT CONTRACT, MAY

BE CRIMINALLY INVESTIGATED AND PROSECUTED FOR FRAUD AGAINST THE UNITED STATES OF AMERICA. PARTIES FOUND MIS-

REPRESENTING THEIR STATUS ALSO RISK DEBARMENT FROM FURTHER GOVERNMENT CONTRACT.

ten X X 52.211-10 X Ten One Email CY Only

1:00PM

07-02-2018 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

00516 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) C.W. Bill Young VA Medical Center 10000 Bay Pines Blvd. Room 326, Bldg. 2 Bay Pines FL 33744 Department of Veterans Affairs

FMS-VA-2(101)

Financial Services Center PO Box 149971 Austin TX 78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.1 General Proposal Information6
A.2 Proposal Preparation and Submission Instructions7
A.3 PRICE/COST SCHEDULE15
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS16
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS16
2.1 52.211-3 AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (JUN 1988)16
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)16
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)16
2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)17
2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)18
2.6 52.228-1 BID GUARANTEE (SEP 1996)19
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)19
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)20
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)20
2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)21
2.11 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008)21
2.12 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (JAN 1998)21
2.13 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)22
2.14 PARTNERING22
REPRESENTATIONS AND CERTIFICATIONS23
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)23
3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013)26
GENERAL CONDITIONS28
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)28
4.2 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013)28
4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)29
4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)29
4.5 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)30
4.6 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)31
4.7 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (SEP 2013)32
4.8 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)33
4.9 SUPPLEMENTAL INSURANCE REQUIREMENTS36
4.10 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)36
4.11 VAAR 852.203-70 COMMERCIAL ADVERTISING (JAN 2008)39
4.12 VAAR 852.203-71 DISPLAY OF DEPARTMENT OF VETERAN AFFAIRS HOTLINE POSTER (DEC 1992)39
4.13 VAAR 852.211-73 BRAND NAME OR EQUAL (JAN 2008)39
4.14 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION)40
4.15 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)41
4.16 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012)41
4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (JUL 2002)43
4.18 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (JUL 2002)43
4.19 VAAR 852.236-74 INSPECTION OF CONSTRUCTION (JUL 2002)44
4.20 VAAR 852.236-76 CORRESPONDENCE (APR 1984)44
4.21 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002)44
4.22 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984)44
4.23 VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL (APR 1984)45
4.24 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984) ALTERNATE I (JUL 2002)45
4.25 VAAR 852.236-82 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS) (APR 1984)46
4.26 VAAR 852.236-84 SCHEDULE OF WORK PROGRESS (NOV 1984)49
ADDITIONAL REQUIREMENTS FOR BAR CHART SCHEDULE49
4.27 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984)50
4.28 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008)50
4.29 VAAR 852.236-87 ACCIDENT PREVENTION (SEP 1993)50
4.30 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002)51
4.31 VAAR 852.236-89 BUY AMERICAN ACT (JAN 2008)53
4.32 VAAR 852.236-91 SPECIAL NOTES (JUL 2002)53
4.33 VAAR 852.246-74 SPECIAL WARRANTIES (JAN 2008)54
4.34 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011)54
4.35 MANDATORY WRITTEN DISCLOSURES55
DESIGN BUILD SPECIFICATIONS63
4.36 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES63
4.37 OWNERSHIP OF ORIGINAL DOCUMENTS63
4.38 RETENTION OF REVIEW DOCUMENTS63
4.39 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED PLANNING INFORMATION64
4.40 COORDINATION WITH MEDICAL CENTER64
4.41 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR64
ATTACHMENTS66
ATTACHMENT 1 - RELEASE OF CLAIMS66
4.42 List of Attachments67

A.1 General Proposal Information

GENERAL PROPOSAL INFORMATION – DESIGN BUILD

1. Work Effort: This project is a Design Build Effort: The contractor shall develop project design documentation including drawings, specifications, design analysis, etc. Upon completion of design, and upon acceptance by the Government, construction execution shall commence and be completed in accordance with contract requirements.

2. Question/Answer: Questions shall be emailed to Rachel.Reed@va.gov until 1:00PM Jun 12, 2018. When submitting, questions include “36C24818R0588, Renovate Ward 4A, Bldg. 100, Bay Pines VAHCS, Bay Pines, FL.” in the subject line.

3. Site Visit: Scheduled for Wednesday, June 6, 2018 at 10:00am. Location of site visit is at 10,000 Bay Pines Blvd., Front Lobby entrance of Building 100.

4. Offer Guarantee (Bid Bond): (An offer guarantee is required for offers requested to participate in Phase II only). NOTE: A scanned copy of the original is acceptable with the original sent by mail.

5. Proposal Requirements: The size of your file shall not exceed 5 Meg. If you have multiple documents, please submit as separate emails. Subject Line of the Proposal e-mail should include the following subject line: “Phase I (etc.,) – Technical Proposal (etc.,) - 36C24818R0588 – Your Company Name - TAB “X”, Email “X” of “X (if multiple emails are required to meet the file limitation identified). All material shall be in typeface Time New Roman (10 font size), 1.0-line spacing on 8½” x 11” white paper with one (1) inch margins all around. Tables and illustration may use a reduced font style, but not less than 8 points, and may be single-spaced. Each page must identify the submitting offeror in the header or footer and page number. Proposals received after the due date/ time will not be considered. Proposals are due as follows:

a. PHASE I Proposal: Due Date: Request for Proposals (RFP) offers for furnishing services identified within the schedule shall be submitted electronically to the Contracting officer (CO) at rachel.reed@va.gov not later than Jul 2, 2018, 1:00 PM EST

b. PHASE II Proposal: Due date will be announced by email to those Offerors invited to participate.

WAGE DETERMINATION (WD): For use during PHASE II only.

NOTE: EXISTING 100% DESIGN (2013) WILL ONLY BE PROVIDED TO FIRMS INVITED TO PHASE II

A.2 Proposal Preparation and Submission Instructions

I. Proposal Preparation and Submission Instructions:

a. Phase I and II Technical Proposal Format: Technical Proposal shall address all information requested and will then be evaluated against the stated factors. The following format shall be used:

(1) TAB A. General Information
(2) TAB B: Technical Approach
(3) TAB C: Technical Qualifications
(4) TAB D: Past Performance
(5) TAB E: Construction Safety/Infection Control/Quality Control
(6) TAB F: Phase II – Technical Approach
(7) TAB G: Phase II – Schedule and Impact to Facility
(8) TAB H: Phase II – Price Proposal

b. Phase I Evaluation Factors and Proposal Requirements. Phase I Proposal shall include:

(1) TAB A: GENERAL INFORMATION:

(a) Cover Page with Solicitation Number, Project Title

(b) Table of Contents

(c) Signed offer/Acknowledgement of Amendments (SF1442)

(d) Copy of current vetBiz.gov SDVOSB certification

(e) DUNS Number

(f) Cage Code

(g) Tax ID number

(h) Principle points of contact, address, phone numbers, etc.

(2) TAB B: Factor 1 - TECHNICAL APPROACH:

(a) In a narrative format, describe in detail how the offeror intends to meet or exceed all performance areas stated in the solicitation/statement of work/attachments that are related to Project “516-11-134,”. Provide technical methods and procedures that reflect a design and construction approach unique to the site and facility. NOTE: Vague, general narratives to include the restatement of the Statement of Work will be rated less favorably.

(b) Schedule and minimizing downtime is crucial. Describe a plan to complete the project in a timely manner without causing disruptions to facility during normal business hours. Also describe actions to be taken by the offeror if completion of work is anticipated to fall behind schedule. It is critical to the VA mission that services remain intact with minimal disruption.

(c) Narrative - 15 page maximum

(3) TAB C: Factor 2 - TECHNICAL QUALIFICATIONS:

1. Sub Factor 2a: SPECIALIZED EXPERIENCE AND TECHNICAL COMPETENCE:

i. Describe specialized experience, technical competence, and design expertise in hospital renovations performed by the Prime and Subcontractors.

ii. Describe ability to obtain the necessary resources to perform this project

iii. Provide Offeror’s total bonding capacity, current available bonding capacity and expected available capacity in 2018, 2019 and 2020.

iv. Provide current Florida license for the D/B Architect-Engineer Team Member

v. Narrative – 5 pages maximum.

1. Sub Factor 2b: DESIGN BUILD TEAM/KEY PERSONNEL

i. Submit a narrative or chart outlining the proposed contractor team. Anyproposed “major” subcontractor with a portion of work valued at $150,000.00dollars or greater shall be identified on the contractor team narrative or chart. Inaddition, to identifying the subcontractor, an overall value of the work shall belisted along with their primary work activities for this project.
ii. Submit resumes for proposed project manager and site superintendent.Resumes shall demonstrate qualifications and experience with previousmanagement of hospital renovation projects between $5 to $10 million.

(4) TAB D: Factor 3 - PAST PERFORMANCE:

The Government will survey PPIRS (Past Performance Information Retrieval System) for two (2) completed contracts for each prime contractor. In the event multiple rated contracts exist in PPIRS which meet the definitions of “relevant and recent” below, the most recent will be used. Relevant is defined as similar hospital renovations and/or new construction of similar patient space projects with an award value greater than $2 million and less than $10 million dollars. Recent is defined as a contract completed in the last seven years. The government’s knowledge may be used in past performance evaluations.

Offerors without relevant PPIRS records can provide references for their past performance. Offerors shall use included questionnaire titled “Past Performance Questionnaire”.

Narrative-10 pages maximum, excluding any separate Questionnaires

(5) TAB E: Factor 4 – Construction Safety/Infection Control/ Quality Control
(a) Describe approach to Construction Safety and Infection Control
(b) Submit Quality Control (QC) monitoring procedures that will ensure a high level ofconstruction quality that is applicable to the specific and general requirements of thescope of work.
(c) Narrative – 5 pages maximum

(6) Phase 1 Evaluation and Selection Criteria:

(a) Phase 1 proposals will be evaluated as follows: Factors 1 thru 4, as described above, will be rated using an adjectival rating system. Each factor response will be reviewed and assigned an adjectival rating.

(b) For evaluation purposes, each technical factor is equal in importance.

OFFERORS ARE NOT TO SUBMIT A PHASE 2 PROPOSAL UNLESS INVITED.

The maximum number of offeror’s that will be selected to submit phase-two proposals shall not exceed five, unless the Contracting Office determines that a number greater than five is in the Government’s best interest.

c. PHASE II Evaluation Factors and Proposal Requirements. Phase II Proposal shall include

3. TAB F: Factor 1 – TECHNICAL APPROACH

1. Offeror shall submit a narrative description of how they intend to approach the scope of work to successfully complete design‐build services for this project in accordance with solicitation requirements and VA guidelines.

1. Clearly describe the prime responsible firm (or firms, if a J/V) and individuals, as well as the roles and responsibilities of individuals proposed as consultants and subcontractors. Provide a list of all consultants and all proposed major subcontractors, including telephone number, address and name of contact.

1. Clarify procedures and proposed solutions for contingencies, differing site conditions, power outages, scheduling conflicts and temporary work stoppage requests (interference with Medical Center operations).

1. Demonstrate techniques for management of work coordination with subcontractors and measures/corrective action that will be taken for substandard performance.

1. Provide an approach to ensure cost-savings and minimizing issuance of change orders.

1. Narrative – Ten (10) pages.

(2) TAB G: Factor 2 –SCHEDULE AND IMPACT TO FACILITY – No page limit

(a) Submit a preliminary (CPM) Critical Path Method schedule for the design and construction satisfying the requirements of this project. A practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including design, acquiring materials, plant, and equipment, mobilization, demolition, installation, finalization, etc.). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given point during the period. Most importantly, the schedule should show length of downtime required.

The proposed schedule should include:

1. Design Period – The design sub periods (i.e., review submissions, other meetings, internal quality control plan reviews, etc.)

2. Construction Period – Mobilization, demolition method and sequencing; Procurement and installation of equipment; Provisions for overtime or shift work; etc.

ASSUME A START DATE OF DEC 1, 2018 FOR PROPOSED SCHEDULE

(4) TAB H: Factor 3 – PRICE PROPOSAL: - No page limit

(a) Include copy of the Pricing Schedule from the solicitation. Along with a lump sum price, please provide a detailed cost breakdown that includes, but is not limited to:

(1) Labor (Direct & Indirect),

(2) Materials, Material Markups, Materials overhead,

(3) Equipment

(4) Subcontractor Cost

(5) Other Direct Costs

(6) Overhead expenses

(7) Indirect Cost

(8) General & Administrative (G&A) expenses,

(9) Profit

(b) ***Estimate to include a detailed line item breakdown of all G&A expenses inclusive of all Project Staff and General Requirements OF THE PRIME CONTRACTOR or OTHER SIMILIARLY SITUATED SDVOSB and shall be indicative of the 15% of contract performance that will be incurred for SDVOSB personnel in accordance with FAR 52.219-27 – Limitations on Subcontracting. ***

(5) Phase 2 proposals will be evaluated as follows:

(a) The technical factors consist of the Factors one (1) and two (2), described above, are of equal importance, and when combined, are approximately equal to price or costs.

(b) Price Proposal - Basis of Evaluation: The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

(i) Comparison of proposed prices received in response to the RFP.

(ii) Comparison of proposed prices with the IGCE.

(iii) Comparison of proposed prices with available historical information.

(iv) Comparison of market survey results.

II. Proposal Submission: Each proposal, Phase I, and Phase II if invited, shall be submitted to the address identified at para 5a in General Proposal Information and must be submitted utilizing the format and means identified in this solicitation.

a. Offerors are cautioned to follow instructions fully and carefully, as the Government reserves the right to make an award based on initial proposals received, without discussions. Therefore, each initial proposal should contain the offeror’s best terms from a price and technical standpoint.

b. Understanding the factors/sub-factors and the associated criteria indicated, the excellence of the work offered, and the ability of the contractor to accomplish what is offered in the proposal is the objective. Contractor shall submit in detail adequate information for evaluation purposes on the evaluation criteria.

c. To provide a basis for sound evaluation by the government, offerors shall submit a complete proposal. The information provided shall be concise, factual, and complete. Proposals will be considered only from offerors that are regularly established in the business and in the judgment of the government, are deemed financially responsible, able to show evidence of experience and have submitted the complete documentation requested.

d. Offerors are hereby advised that any imposed terms and conditions which deviate from the Government’s material terms and conditions established in the solicitation may render their proposal unacceptable and ineligible for award.

III. Evaluation and Award Determination: This is a competitive Request for Proposal (RFP) that represents the best value to the Government conducted under FAR Part 15 101-1, Tradeoff Process. In accordance with FAR 15.101-1, all evaluation factors, other than cost or price, when combined, are approximately equal to cost or price. Thus, award will be made to the firm whose Phase I proposal was initially ranked in the competitive range and who now offers a Phase II proposal, which based on both its technical and pricing proposals, offers the overall best value to the Government. This may result in award being made to a higher-rated, higher priced offeror where the Contracting Officer determines that the technical capability and past performance of the higher-priced offer outweighs the cost difference.

IV. Past Safety and Environmental Record

(a) Safety or Environmental Violations and Experience Modification Rate (EMR)
(1)All Offerors shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violations(s) in the past three years.
(2)All Offerors shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
(3)Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.
(4)A Determination of Responsibility will be accomplished for the apparent awardee prior to processing the award. If the apparent awardee fails to provide required documentation, then the matter will be referred to the Small Business Administration (SBA) for a certificate of competency or a determination of responsibility by the SBA.
(5)This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

Past Safety and Environmental Record

(SAMPLE FORM FOR BIDDER/OFFEROR TO COMPLETE & SUBMIT WITH

PHASE I PROPOSAL)

Pre-Award Contractor Evaluation Form Company Name:

Address:

Telephone: Fax:

Email:

Contact:

1. Utilizing your OSHA 300 Forms, please complete the following information:

Category
2015
2016
2017

Number of man hours (jobsite and office).

Number of cases involving days away from work, restricted activity, or both (Column H and I of OSHA 300).

Days away, restricted, or transferred rate (# of days away, restricted, or transferred cases x 200,000/# of man hours) (DART Rate).

Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations. (Four serious, one repeat, or one willful disqualifies the contractor.)

Please attach copies of the following documents: OSHA 300 and 300a Forms. These forms can be accessed through the OSHA publications search page: http://www.osha.gov/pls/publications/publication.html.

Provide your six-digit North American Industrial Classification System (NAICS) Code for this Acquisition: __ Who administers your company’s Safety and Health Program? ____________________________ Company’s Insurance Experience Modification Rate (EMR) for the past 3 years: _____________

Signature / Date

A.3 PRICE/COST SCHEDULE

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
0001
(516-11-134) Provide all design build services to renovate inpatient ward 4A, Bldg. 100., consisting of approximately 15,000 square feet, so as to provide a patient privacy compliant, fully handicap accessible, state-of-the-art inpatient facility.
1.00
JB
__________________
__________________
GRAND TOTAL
__________________

Page 1 of Page 1 of

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.211-3 AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (JUN 1988) The specifications cited in this solicitation may be obtained from:

Activity: VA Office of Construction and Facilities Mgt Complete Address:

425 I Street NW Washington, DC 200001

Telephone Number: N/A Person to be Contacted: www.cfm.va.gov Time(s) for Viewing: N/A The request should identify the solicitation number and the specification requested by date, title, and number, as cited in the solicitation.

(End of Provision)

2.2 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
17.9 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

PINELLAS COUNTY, FL

(End of Provision)

2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.6 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Rachel Reed

Hand-Carried Address:

Department of Veterans Affairs C.W. Bill Young VA Medical Center Room 326, Bldg. 2 10,000 Bay Pines Blvd.

Bay Pines FL 33744 Mailing Address:

Department of Veterans Affairs C.W. Bill Young VA Medical Center Room 326, Bldg. 2 10,000 Bay Pines Blvd.

Bay Pines FL 33744

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— June 6, 2018 at 10:00am (local)

(c) Participants will meet at— Bay Pines VAHCS, Front Lobby Entrance, Bldg 100 (End of Provision)

2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2016
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.211-6
BRAND NAME OR EQUAL
AUG 1999
52.215-1
INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION
JAN 2017
52.236-28
PREPARATION OF PROPOSALS—CONSTRUCTION
OCT 1997

2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.

(End of Clause)

2.11 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008)

(a) Any protest filed by an interested party shall:

(1) Include the name, address, fax number, and telephone number of the protester;

(2) Identify the solicitation and/or contract number;

(3) Include an original signed by the protester or the protester's representative and at least one copy;

(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;

(5) Specifically request a ruling of the individual upon whom the protest is served;

(6) State the form of relief requested; and

(7) Provide all information establishing the timeliness of the protest.

(b) Failure to comply with the above may result in dismissal of the protest without further consideration.

(c) Bidders/offerors and contracting officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.

(End of Provision)

2.12 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (JAN 1998)

As an alternative to filing a protest with the contracting officer, an interested party may file a protest with the Deputy Assistant Secretary for Acquisition and Materiel Management, Acquisition Administration Team, Department of Veterans Affairs, 810 Vermont Avenue, NW., Washington, DC 20420, or for solicitations issued by the Office of Construction and Facilities Management, the Director, Office of Construction and Facilities Management, 810 Vermont Avenue, NW., Washington, DC 20420. The protest will not be considered if the interested party has a protest on the same or similar issues pending with the contracting officer.

(End of Provision) PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:

Deputy Assistant Secretary for Acquisition and Logistics,
Risk Management Team, Department of Veterans Affairs
810 Vermont Avenue, N.W.
Washington, DC 20420

Or for solicitations issued by the Office of Construction and Facilities Management:

Director, Office of Construction and Facilities Management
811 Vermont Avenue, N.W.
Washington, DC 20420

2.13 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)

The contracting officer reserves the right to designate representatives to act for him/her in furnishing technical guidance and advice or generally monitor the work to be performed under this contract. Such designation will be in writing and will define the scope and limitation of the designee's authority. A copy of the designation shall be furnished to the contractor.

(End of Provision)

2.14 PARTNERING

(a) In order to most effectively accomplish this contract, the Government proposes to form a cohesive partnership with the Contractor and its subcontractors. This partnership would strive to draw on the strengths of each organization in an effort to achieve a quality project, done right the first time, within the budget and on schedule.

(b) This partnership will be totally voluntary. The focus of partnering is to build cooperative relationships with the private sector and avoid or minimize disputes and to nurture a more collaborative ethic characterized by trust, cooperation and teamwork. Partnering is defined as the creation of a relationship between the owner and contractor that promotes mutual and beneficial goals. It is a non-contractual, but formally structured agreement between the parties. The ultimate goal is the elimination of the "us" versus "them" thinking, and formation of a "we" mentality for the benefit of the project.

(c) Any cost associated with effectuating this partnership will be agreed to by both parties and will be shared equally with no change in contract price.

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $36.5 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xx) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.

(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.

(xxi) 52.225-6, Trade Agreements Certificate.