36C24818R0581-00001005.docx
DOCX document 23 KB Posted
- Solicitation number
- 36C24818R0581
About this file
36C24818R0581 00001 36C24818R0581 00001.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24818C0176-000.docx | DOCX document | |
| 36C24818R0581-00001011.pdf | ||
| 36C24818R0581-00001010.pdf | ||
| 36C24818R0581-00001007.pdf | ||
| 36C24818R0581-00001006.pdf | ||
| 36C24818R0581-00001009.pdf | ||
| 36C24818R0581-00001008.pdf | ||
| 36C24818R0581-003.pdf | ||
| 36C24818R0581-002.pdf | ||
| 36C24818R0581-001.docx | DOCX document | |
| 36C24818R0581-000.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 00001 05-15-2018 546-16-105 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) 8875 Hidden River Pkwy Suite 525 Tampa
FL
33637 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) 8875 Hidden River Pkwy Tampa
FL
33637 To all Offerors/Bidders
36C24818R0581 05-14-2018
X X X The purpose of this amendment is to provide the RFI responses with attachments, and site visit sign in sheet.
Additional site visit scheduled for 18 May, 2018, 8:00-09:00 AM (EST), Miami VAMC, Bldg 1, Room B110
Note: Asbestos Survey
RFI’S
36C24818R0581
CORRECTION OF SANITARY SEWER MAINS
MIAMI VAMC
Q1: Paragraph A.3.1.A – TAB A: GENERAL INFO; Indicates the Offeror submitting a current “EMR” letter from its Insurer within this part of its Proposal. However, Paragraph A.3.5.f – Safety or Environmental Violations & EMR; Indicates the Offeror also submitting “their past Safety & Environmental record.” I currently assume that because this provision falls under paragraph A.3.5 – Evaluation & Award Determination, that this additional information would only be required to be submitted by the Offeror post-proposal submission / pre-award if being considered, and as requested by the Contracting Officer. Please confirm / advise.
ANSWER: All firms must submit EMR with the original proposal submission.
Q2: Paragraph A.4.3 - Special Requirements, Bullet Point 4; States “Some work will have to be performed during the evening hours… or weekends….” Please indicate specifically what scope / areas of work are required to be performed during these premium time work hours
ANSWER: This will be part of the phasing plan or weekly production schedule. This will fluctuate do hospital operations. That’s is why we like plan shut downs 2 weeks in advance.
Q3: Is this project sales tax exempt? If the project is sales tax exempt can the government provide a sales tax exemption certificate?
ANSWER: NO
Q4: Will the Government provide comprehensive written badging requirements for the project if badging is required?
ANSWER: Yes, the COR will be responsible
Q5: Where will the designated parking area be for workers accessing the construction site?
ANSWER: Yes, contactors have limited parking that provides access to the construction site
Q6: Will the government accept the use of the industry leading Procore Project Management software as the primary submittal and data tracking tool for this project? The software is compatible with the VA’s networks and is currently in use at many VA locations.
ANSWER: Yes
Q7: During construction in an area where the ceilings or fire suppression system will be disrupted, will NFPA 241 apply? Will the government require additional security measures beyond NFPA code such as fire watch, temporary fire alarms, adjustments to sprinkler heads, etc.?
ANSWER: Yes
Q8: Has the work area been checked for asbestos, lead, and mold? How are contractors to address this?
ANSWER: See attached Asbestos Survey
Q9: Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin.
ANSWER: This is all speculation at this point. The contract arrangement is a firm fixed price (FFP) and no adjustments will be allowed.
Q10: Describe any and all tasks that may be required for this project as it relates to infectious control?
ANSWER: SECTION 01 00 00
GENERAL REQUIREMENTS 1.8 infection prevention measures
Q11: For interior areas of work, can we use free circulation with our HEPA filters.
ANSWER: HEP filters SECTION 01 00 00 GENERAL REQUIREMENTS 1.8 infection prevention measures, Q12: The scope of work states to “correct deficiencies” with sewer and sanitary systems. Is the government’s intention to replace the whole sewer system or to do spot repairs on deficient areas?
ANSWER: Replace. Replace IAW design drawings and specifications
Q13: Does the government have an estimate for the cubic yardage of contaminated soils to be removed and replaced?
ANSWER: No
Q14: Please confirm that the alternates are deductive in nature.
ANSWER: Yes. These are Bid Deducts
Q15: Please confirm that this is the replacement of only the main risers, not branch lines or fixtures.
ANSWER: Per Sheet Note 5 & 6 of PD111, piping is to be replaced to just before the slab penetration and all plumbing fixtures are to remain. This would include the replacement of all branch sanitary piping serving fixtures to a point before there penetration of the slab. Sanitary piping that is inaccessible near a singular fixture is to remain (i.e. in a wall). All wall demolition and reconstruction is noted on A-401 to A-407 and is reserved for main risers only.
Q16: Since we are only doing basement to second floor, how does the government want to handle cutting down individual risers?
ANSWER: "Cutting" presumed to mean "shutting". Shut down of individual risers shall be coordinated with the government. Work shall be scheduled in advance and occur during off hours or on weekends to minimize impact.
Q17: Please provide a phasing plan approved by the government and the VA.
ANSWER: The prime contractor will provide phasing plan “part of the cost estimate” Once the prime has completed the plan must be approved by Miami VA staff.
Q18: We would like to state that we believe the government would be better served by a vertical, riser by riser replacement rather than a floor by floor replacement.
ANSWER: This was discussed during design. However, to limit the impact on floors above due to prolonged riser shutdowns, the clinic by clinic approach was chosen.
Q19: Please have the engineers provide drawings that show each of the branch lines that come out of all the risers we are replacing. Without these drawings shutdowns are nearly impossible.
ANSWER: See attached drawings
Q20: Are we to assume we are replacing all carriers at each fixture?
ANSWER: Fixtures and carriers are not to be replaced. Sanitary branch piping serving a fixture is to be replaced on the level below to the penetration of the slab.
Q21: If we come upon an unforeseen condition, will the problem be expedited so we can adhere to our scheduling and shutdown times? ANSWER: yes, handled through the COR
a. Sheet notes – various (PP101 Sheet note 1 - paraphrased) – work shall occur during nights 6pm-6am, unless the riser is determined to be inactive during normal hours. If the outage extends past 6am, it must be planned two weeks in advance.
We expect these outages to last significantly longer than one work day, how is the hospital planning to coordinate that? ANSWER: The is the responsibility of the prime contractor, to ensure there are no disruptions to service.
If we are to make the system usable after every work day, costs and time will increase significantly. ANSWER: The systems have to remain functional, if work last longer temporary system will have to be put in place.
Q22: It seems that the VA is looking to replace the mains in the basement and the riser piping up to the 2nd floor. Please confirm that the fixtures are distribution piping are not to be worked on.
ANSWER: Fixtures and carriers are not to be replaced. "Distribution piping" presumed to mean domestic water piping. No domestic water piping shall be disturbed in this project.
Q23: How are we to handle tying into existing distribution lines and riser piping at the edge of our scope of work? Tying in old degraded piping into the new piping will be challenging and will likely require non-standard fixes.
ANSWER: The contractor will submit a condition found report, work on solution with the A & firm
Q24: There are notes (e.g. PP115 - Sheet note 6) indicating the coordinated removal of duct work along with the replacement of sanitary lines. In other areas in the hospital where we run into unforeseen conditions such as duct work, medical gas, fire sprinkler, etc. how are we to handle the work? ANSWER: Yes submit condition found reports and possible change order to complete unforeseen work
Is there a process for expedited reviews to keep the project moving without significantly interfering with our project schedule?
ANSWER: Yes, this will be handled the COR & CO
Q25: Replacement of Pipe: please confirm that the only pipe to be replaced is that which is mentioned and shown on the drawings?
ANSWER: Yes
Q26: Will service weight No-Hub cast iron pipe and fittings be accepted for the project?
ANSWER:
SECTION 22 66 00
CHEMICAL-WASTE SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES
Q27: Will there be any special procedures for the removal and transportation of any contaminated materials encountered?
ANSWER: Contaminated waste must be removed by a certified waste disposal company.
Q28: Provide location for dumpsters for debris removal.
ANSWER: A location will be provided.
Q29: Requesting additional site visit to access the basement.
ANSWER: Additional site visit scheduled for 18 May, 2018, 8:00-09:00 AM (EST)
See attached document: asbestos survey copy_Redacted.
See attached document: FP-13-Bldg 1 Crawl Space Floor Plan Fire Sprinkler.
See attached document: FP-29-Bldg 1 First Floor Plan Fire Sprinkler Zone A1 A2.
See attached document: 1-FP-0-Bldg 1 Fire Sprinkler Cover Sheet.
See attached document: FA-15-FP-Bldg 1 Fire Alarm Riser.
See attached document: Sign in sheet for project 546-16-105 .
File details come from the government source that posted it.