About this file
36C24818R0186 Attachment 01 - SOW - USP800 Pharmacy.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24818R0186-0006001.docx | DOCX document | |
| 36C24818R0186-0006002.pdf | ||
| 36C24818R0186-0006000.docx | DOCX document | |
| 36C24818R0186-0005005.docx | DOCX document | |
| 36C24818R0186-0005001.pdf | ||
| 36C24818R0186-0005002.docx | DOCX document | |
| 36C24818R0186-0005008.pdf | ||
| 36C24818R0186-0005004.docx | DOCX document | |
| 36C24818R0186-0005006.pdf | ||
| 36C24818R0186-0005003.pdf | ||
| 36C24818R0186-0005007.pdf | ||
| 36C24818R0186-0005000.docx | DOCX document | |
| Drawings_3.pdf | ||
| Drawings_2.pdf | ||
| Drawings_1.pdf | ||
| 36C24818R0186-00003005.docx | DOCX document | |
| 36C24818R0186-00002001.docx | DOCX document | |
| 36C24818R0186-00002000.docx | DOCX document | |
| 36C24818R0186-00001001.pdf | ||
| 36C24818R0186-00001000.docx | DOCX document | |
| 36C24818R0186-003.pdf | ||
| 36C24818R0186-007.pdf | ||
| 36C24818R0186-005.docx | DOCX document | |
| 36C24818R0186-004.docx | DOCX document | |
| 36C24818R0186-001.docx | DOCX document | |
| 36C24818R0186-006.docx | DOCX document | |
| 36C24818R0186-000.docx | DOCX document |
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Renovate Pharmacy to Meet USP800
PROJECT #673-18-109
ARCHITECTURAL / ENGINEERING DESIGN-BUILD SERVICES
I. SCOPE OF WORK:
A. Furnish all necessary professional services, equipment, labor materials, supervision, tools, testing, and specialty services to perform design-build services for the NRM Project #673-18-109, " Renovate Pharmacy to Meet USP800" at the James A. Haley VA Hospital, located at 13000 Bruce B. Downs Boulevard, Tampa, Florida, 33612. The work includes, but is not limited to site investigation, designing and preparing drawings, phase planning, specifications, construction period services, and general construction for all disciplines.
The design development (DD) (preliminary drawings) design phases will take the design to 30% completion. It does not include editing of specifications.
The contract document (working drawing) design phases will include 65%, 95% and 100% review stages. If the documents do not meet all of the requirements of each submission, then the portions of the documents that are not acceptable by the VA according to the design standards and criteria must be updated by the A/E prior to moving on to the next scheduled submission.
The VA will provide requested As-Built drawings (in either AutoCAD, PDF, or JPG form) on a CD-ROM to the A/E for design purposes. The A/E is encouraged to review all drawings with the assigned VA representative COTR to verify what existing drawings are available. The A/E shall coordinate with the VA representative COTR prior to viewing the drawings located at the VA and shall not remove any documents from the files.
The existing drawings on file at the VA may not be 100% accurate and may not exactly reflect the current conditions of the James A. Haley VA Hospital. It is the responsibility of the A/E to review the existing drawings and verify the existing conditions.
B. Project Description: Provide Renovate Pharmacy HVAC and other equipment to meet USP800. This project will renovate 1,500 SF of the main Pharmacy located within Building 1.
Design Services shall review the existing field conditions and perform a survey of building #1 to verify the existing conditions. The A/E shall evaluate this building to determine if utilities or any other objects will need to be relocated or addressed in the design. The A/E shall also review the As–Built drawings and the site drawings for Building #1.
The A/E shall show a detailed containment plan for infection control for this design. This plan shall be detailed showing locations and what infection control requirements are to be used for each area. The HPMs for Safety and Infection Control will be provided to the A/E for their use. Construction barriers will be required for the duration of the construction to isolate patients and staff from dust, debris and construction hazards. The A/E will also have to indicate these construction barriers on their drawings.
New work includes, but is not limited to designing and preparing drawings, phasing planning, specifications, cost estimates for all disciplines, and general construction to renovate the pharmacy to meet USP800 standards for building #1. The A/E will be required to attend phase meetings at 30%, 65% and 95% to discuss progress with the VA staff. The A/E will be required to take meeting minutes and distribute to the VA for approval and as documentation of what was covered in the meeting.
C. Design Tasks:
1. SITE INVESTIGATION: Design Services shall conduct a site survey of the project area to ensure that the design is feasible and without any major obstacles. Available as–built drawings and related other project drawings are available to the A/E, but field verification by the A/E must be completed to verify existing site conditions and to collect data as required for design development work to successful completion of design and construction documents.
2. DEMOLITION: The project demolition work may include structural, architectural, plumbing, mechanical and electrical demolition to clear space for the new systems. The minor demolition of existing landscaping and other items shall be included in this project.
3. CIVIL / STRUCTURAL: Work may include architectural modification and structural work. Structural engineering is expected to be completed by a Florida Licensed Structural Engineer for any needed structural reinforcements. All required borings and structural testing shall be completed by the A/E firm. The A/E firm shall proceed with a structural design that will not impede on pedestrian traffic at the ground level.
4. ARCHITECTURAL: Field verification of elevations and architectural dimensions are crucial to the success of this project, as the existing drawings are best represented. Exterior work must blend into the surrounding buildings and architectural appearances.
5. INTERIOR DESIGN: The VA Interior Designer will perform all interior color and material selections from the Architect’s recommended items. The A/E will coordinate all interior selections with the VA interior design staff.
6. PLUMBING / PIPING: The plumbing systems need to be evaluated and updated to meet the latest Plumbing Codes. Design modifications, additions and relocations to the plumbing systems and fire protection system must follow the VISN 8 policy and Life Safety codes and other applicable code requirements for a complete certified functional system.
7. HEATING, VENTILATION AND AIR CONDITIONING (HVAC): The HVAC systems need to be evaluated and updated to meet the latest HVAC Design Criteria. The A/E must evaluate the Chilled Water System and the Hot Water / Steam System serving the design scope area.
8. ELECTRICAL: The electrical systems need to be evaluated and updated to meet the latest Design Criteria. The A/E must evaluate the electrical systems serving the design scope area to determine if there is enough, and provide modifications and extensions to the existing electrical systems, security system, communications system, fire / safety system, etc. All panels shall be metered before any planned connection to insure available capacity. This required metering will be the responsibility of the A/E firm to complete. This design shall evaluate existing As–Built drawings and all ongoing electrical upgrade projects during the design process.
9. INDUSTRIAL HYGIENIST: An Industrial Hygienist (IH), licensed by the State of Florida as an Asbestos Consultant, may be required due to the existence of asbestos containing materials that may be encountered during the construction project.
10. ASBESTOS: The A/E shall investigate the construction site to verify any asbestos containing materials. Asbestos containing sprayed-on fireproofing, floor tile & mastic, and other asbestos containing / contaminated materials / items may be encountered in buildings 1 and 2. If asbestos is encountered, it is the A/E and their subcontractor’s responsibility to adhere to all VA, OSHA, Federal, and State regulations of ACM procedures. Submittal packages for the Asbestos & IAQ qualifications shall be provided to the VA. The IH shall perform duties as necessary by monitoring, inspecting and testing inside / outside the work area in accordance with OSHA requirements.
a. NOTE: Some site investigation work may be in asbestos contaminated areas, and will require the A/E to have their personnel trained for Class 3 Asbestos Work (Maintenance & Operations within Asbestos Contaminated areas).
b. IAQ: The IH will also have to design IAQ measures for construction work in relevant areas.
11. EQUIPMENT: The A/E shall coordinate the design work directly with the suppliers / manufacturers of the new equipment to produce a completely designed operational project. All drawings, schematics, and other data available from the equipment suppliers shall be incorporated in the A/E drawings and specifications. The A/E is to determine the points of connection between old and new equipment and clearly detail these connections on the drawings.
12. Design the project by using site measurements and verifying site conditions. The A/E shall not rely solely on the As–Built drawings.
13. The A/E shall provide other documentation (i.e., calculations, reports, recommendations, etc.) that is appropriate to support the design effort and to keep the Government fully informed of all issues or potential problems. Provide computations and sizing calculations for any anticipated new loads, altered loads, and existing loads for electrical, mechanical (HVAC, plumbing, medical gas and steam), sanitary, structural and fire protection designs. For computerized calculations, submit complete and clear documentation of computer programs, interpretation of input / output, and description of program procedures. Provide an investigation and explanation of code requirements incorporated into the design. Furnish a copy of each code quoted or used in the design, when necessary to provide additional understanding of design decisions.
14. The A/E shall provide all schedules and tables used on the drawings in MS Excel 2007.
D. Additional Requirements and Information:
1. LIFE SAFETY: Requirement for acquiring and incorporating a Certified Independent Third-Party Safety Professional review of design documents. The A / E shall design the necessary Life Safety and Interim Life Safety provisions for impacted areas, both temporary and permanent measures. The A/E shall provide and coordinate the review of the Life Safety Provisions of the project design with a third party, independent licensed Fire Protection Engineer. The following areas will be reviewed by the third party:
a. NFPA Code Compliance
b. Environmental / EPA Impacts, Permits, etc.
c. OSHA Compliance (i.e., Excavation, Demolition, etc.)
d. Security Property / Infrastructure Management, Homeland Security, etc.
e. Emergency preparedness
f. Disability Accessibility Compliance
g. National and Local Codes. The A/E shall deliver a letter certifying compliance with all Life Safety Codes and Requirements applicable to this project from the third party.
2. CODES, STANDARDS AND EXECUTIVE ORDERS: The Public Buildings Amendment Act of 1988, Public Law (Pub. L.) 100-678 requires Federal agencies to follow national recognized "model" building codes. The VA has adopted the latest edition of the following codes and standards as a minimum for all projects performed in the modernization, alteration, addition, or improvement of its real property and the construction of new structures. The VA design Manuals and Master Specifications specify other codes and standards that VA follows on its projects:
a. VA Directives, Design Manuals, Master Specifications, VA National CAD Standard Application Guide, and other Guidance on the Technical Information Library (TIL) (http://www.cfm.va.gov/til/).
b. International Building Code (IBC) including International Mechanical and Plumbing Codes
c. NFPA 101 Life Safety Code (see notes below)
d. NFPA National Fire Codes with the exception of NFPA 5000 and NFPA 900.
e. Occupational, Safety and Health Administration (OSHA) Standards
f. VA Seismic Design Requirements, H-18-8
g. National Electrical Code (NEC)
h. National Standard Plumbing Code (NSPC)
i. Safety Code for Elevators and Escalators, American Society of Mechanical Engineers (ASME) A 17.1.
j. ASME Boiler and Pressure Vessel Code
k. ASME Code for Pressure Piping
l. Uniform Federal Accessibility Standards (UFAS) including VA Supplement, Barrier Free Design
m. Building Code Requirements for Reinforced Concrete, American Concrete Institute and Commentary (ACI 318)
n. Manual of Steel Construction, Load and Resistance Factor Design Specifications for Structural Steel Buildings, American Institute of Steel Construction (AISC)
o. Energy Policy Act of 2005 (EPAct)
p. American Society of Heating and Refrigeration Engineers (ASHRAE) 90.1, Energy Standards for Buildings Except Low-Rise Residential Buildings
q. Federal Leadership in High Performance and Sustainable Buildings: Memorandum of Understanding (MOU)
r. Executive Order 13423: Strengthening Federal Environmental, Energy, and Transportation Management
s. Executive Order 13514: Federal Leadership in Environmental, Energy, and Economic Performance
t. The Provisions for Construction and Safety Signs. Stated in the General Requirements, Section 01 00 00, of the VA Construction Specifications
u. American Society of Heating and Refrigeration Engineers (ASHRAE), Ventilation for Acceptable Indoor Air Quality – ASHRAE Standard 62.1
v. Safety Standard for Refrigeration Systems – ASHRAE Standard 15
3. NOTES: NFPA 101 primarily addresses life safety and fire protection features while the IBC addresses a wide range of considerations, including, but not limited to, structural strength, stability, sanitation, adequate light and ventilation, and energy conservation. VA buildings must meet the requirements of NFPA 101 and documents referenced by NFPA 101 in order to comply with the accreditation requirements of the joint Commission. Therefore, designs shall comply with the requirements of the latest edition of NFPA 101 and documents referenced therein. Design features not addressed by NFPA 101 or documents referenced therein shall comply with the requirements of the latest edition of the IBC or as otherwise addressed above in this Program Guide. For design features that are addressed by both the IBC as well as NFPA 101 or a document referenced by NFPA 101, the requirements of NFPA 101 or the document referenced by NFPA 101 shall be used exclusively. This applies even if the IBC requirements are different.
4. Conflicts between Nationally Recognized Codes and Standards and VA Requirements: Should a conflict exist between VA requirements and VA adopted nationally recognized codes and standards, the conflict shall be brought to the attention of the VA. The resolution of the conflict shall be made by the authority having jurisdiction for the VA to ensure a consistency system wide.
5. ENERGY & RESOURCE CONSERVATION: Any alterations or new equipment (motors, light fixtures, windows, HVAC equipment, pumps, chillers, water faucets, urinals, toilets, insulation, etc.) shall be energy efficient and resource efficient. This facility’s overall energy usage goal is 142,000 BTU/sq. ft. (142 MBTU/SF). Energy Star, LEEDS and other related criteria shall be utilized. Light bulbs and other equipment shall have very low mercury content or NOT contain mercury at all.
6. DRAWINGS: The A/E shall provide electronic copies of drawings at each review step generated in the latest version of AutoCAD or its companion products (digitally signed DWGs) and PDF format in individual sheet files on CD-ROM. Include all associated support files (i.e. plot styles, external referenced files, etc.). This facility currently uses AutoCAD and Autodesk MEP 2010. The standard drawing size shall be ARCH E1 (30” x 42”). The format to be used in creating the CAD drawings (i.e. layer / level structure, fonts, font sizing, file naming conventions, etc.) is that of the latest edition of the National CAD Standard (www.nationalcadstandard.org).
a. The A/E shall follow these level / layer formats, file – naming conventions, and symbol library.
b. Drawings are to be drawn from the VA’s “As-Built” or construction drawings updated by site verification, not scanned reproductions.
c. The final sets of the new construction drawings, including the film copies, shall be sealed (embossed & ink stamps) and signed by each respective Professional Engineer in their discipline, Industrial Hygienist, Architect and other necessary licensed professional consultants.
7. ESTIMATE SUBMISSION REQUIREMENTS: The A/E shall submit a construction cost estimate from an independent firm for all trade disciplines at each and every project submission. This estimate shall show the cost of construction, most likely to be reflected by the construction contractors' bids, if the bids were submitted on the same date as the estimate. The level of detail for this estimate shall be consistent with the degree of completeness of the drawings being submitted. Therefore, if it is shown, it must be priced. If it is shown in detail, it must be priced in detail. For detailed elements, "lump sum" or "allowance" figures will not be acceptable. Building gross area computations shall be included with each estimate. Estimates shall be broken down by AIA divisions. The first page will be a summary page showing deductive bid items, contractor mark-ups, overhead, profit, special insurance, and bonding to reflect true construction costs. The breakdown shall reflect Bid Items 1, 2, and 3 separately; then in aggregate. Provide an electronic copy of cost estimates with each submittal.
8. SPECIFICATIONS: The A/E firm may obtain the list of the complete VA Construction Specifications from the VA Facilities Management Technical Information Library (TIL), which is located at http://www.cfm.va.gov/TIL/spec.asp#02. The A/E shall provide the final edited specifications on CD-ROM in Microsoft Word. The VA uses MS Word 2007. The format shall be 1.5 spaced, left justified, 2-sided, laser quality, and courier-new size 10 font. The specifications shall be provided in four (4) copies with rubber bands around three (3) of the copies. The remaining copy shall be in a colored, 3-“D”-ring loose-leaf binder, with identification labels on the binding and cover so the project title and number are readily visible and with tabbed dividers between each specification section.
9. DESIGN SCHEDULES: Approximate time frames are presented below. Actual timelines submitted for approval should reflect the project complexity and follow the format presented below:
Design Development “DD”
a. Begin Design Development (Notice to Proceed): NTP
b. Submission of Iterations (DD1): NTP + 14 Days
c. First Submission of Design Development (DD1–15%): NTP + 21 Days
d. First Review Meeting and Return First Submission: NTP + 30 Days
e. Second Submission (Final Design Development) (DD2–30%): NTP + 45 Days
f. Second Review Meeting and Return Second Submission: NTP + 55 Days End of Design Development “DD”
Contract Document Stage “CD”
a. Begin Contract Document Stage: NTP + 55 Days
b. Begin Contract Drawings (Target date for completion of Service Approval Signatures): NTP + 55 Days
c. Third Submission Contract Documents (CD1-65%): NTP + 85 Days
d. Third Review Meeting and Return Third Submission: NTP + 95 Days
e. Fourth Submission Contract Documents (CD2-95%): NTP + 125 Days
f. Fourth Review Meeting and Return Fourth Submission: NTP + 135 Days
g. Fifth Submission (Deliver Final Contract Documents) (CD3-100%): NTP + 155 Days
h. Award Construction Contract: NTP + 170 Days
i. Complete Construction: NTP + 365 Days End of Contract Document Stage “CD”
10. REVIEW MEETINGS: The A/E is required to attend a design review meeting after each submission during the design process and provide meeting minutes to the VA for approval and distribution.
11. The A/E shall design the project in such a manner that the base bid shall include the sum total of the work. However, there must be deducting alternate bid items. The deducting alternative bid items shall have a goal of equaling 20% of the proposed construction budget. The resulting project must still be a viable project if all alternatives are deducted from the construction project. No matter which option is selected, the hospital must continue to function during construction.
12. The VA mandates that all facilities are to be 100% fire sprinkled. The A/E shall review the existing sprinkler system and design any modifications necessary to the existing system to ensure that all areas are 100% sprinkled. Once the design for the modifications has been completed, a Fire Protection Engineer shall review and stamp those necessary drawings for code compliance.
13. Provide a moisture control plan and illustrate the use of an appropriate moisture control strategy to prevent building damage, minimize mold contamination, and reduce health risks related to moisture. For façade renovations, a dew point analysis and a plan for cleanup or infiltration of moisture into the building materials are required.
14. Provide a daylighting and lighting controls plan, including automated lighting controls (occupancy / vacancy sensors with manual-off capability) for appropriate spaces including restrooms, conference and meeting rooms, employee lunch and break rooms, training classrooms, and offices.
15. Storm Water: Per EISA Section 438, where redevelopment affects site hydrology, use site planning, design, construction, and maintenance strategies to maintain hydrologic conditions during development, or to restore hydrologic conditions following development, to the maximum extent that is technically feasible.
II. DESIGN DEVELOPMENT (FOR EACH DESIGN PHASE “DD”):
A. FIRST REVIEW: Design Development (DD1) submission – 15% complete.
1. Submittals: Three (3) copies of preliminary plans (1 full size and 2 half size), three (3) copies of cost estimates furnished by an independent firm, the marked up As-Built drawings, three (3) copies of calculations, computations, and engineering data. Provide electronic copies of the entire submission on one (1) CD-ROM.
2. Specifications: Submit a cover letter and a list of Tampa Specific VA master specifications intended for use on this project.
3. Drawings: The A/E shall provide a full list of project drawings showing the scope and plan for each discipline involved.
a. All Disciplines:
1) Demolition: Show furnishings that will remain during construction. Show means of protection.
2) Provide one drawing to include Interim Life Safety Code Plan, Phasing Plan, Security and environmental barriers.
3) Show and identify existing conditions, sections, elevations, details, dimensions, and capacities. The A/E shall site verify all items.
4) Show extent of asbestos that will be encountered and limits of removal with cost estimate, if applicable.
5) Show items to be removed, all disciplines.
6) Provide symbol sheets and explanation of detail symbols used.
7) Provide a VA Title Sheet for entire set of drawings.
8) Provide layout and equipment options.
b. Architectural:
1) Show location of existing equipment to be removed, remain, or be relocated.
2) Show location of new equipment.
3) Floor plans that include all rooms, door swing, windows, corridors, closets, mechanical, and other spaces.
4) Show reflected ceiling plan, and architectural details, sections, and finishes.
5) Show the structural grid with assumed column sizes, expansion and seismic joint locations, and location of special seismic structural features.
6) Show site survey and connection point locations.
7) All floor to floor heights shall be indicated. Show typical wall sections. Show smoke compartment and fire protection on the Interim Life Safety / Phasing Plan Drawing.
c. Civil / Structural:
1) Show existing conditions and how new work interfaces.
d. Plumbing / Piping:
1) Show basis for design and interface with existing system.
2) Show sizes of pipes and verified locations of valves.
3) Show modifications, old and new.
4) Provide a one-line diagram for all systems.
e. Heating, Ventilation and Air Conditioning (HVAC):
1) Provide preliminary load calculations.
f. Electrical:
1) Show existing including capacities. Furnish preliminary load calculations. Show transformers and panels to scale.
g. Phasing:
1) Present proposed phasing plans that will accomplish the construction work with a minimum amount of disruption to the normal operations of the hospital.
h. Calculations:
1) Submit in triplicate, all preliminary structural, HVAC, electrical, and plumbing calculations.
4. Estimates: Submit six (6) copies of the cost estimate (for all disciplines). See “Estimate Submission Requirements.”
5. Asbestos: Outline area of work expected to disturb asbestos containing fireproofing.
6. Acceptance: If the documents do not meet all of the requirements of this submission, then the portions of the documents that are not acceptable by the VA according to the design standards and criteria must be updated by the A/E prior to moving on to the next scheduled submission.
B. SECOND REVIEW: Final Design Development (DD2) submission – 30% complete. After material of the 15% review has been reviewed, the A/E shall make necessary changes to incorporate the review comments and furnish the following:
1. Submittals: Three (3) complete sets of 30% drawings (1 full size and 2 half size), the original marked-up drawings, the 15% preliminary review mark-up, three (3) sets of complete cost estimates and three (3) sets of calculations, computations and engineering data. Also, provide one (1) electronic copy of the 30% drawings in accordance with section I.D.6.
2. Specifications: Submit three (3) sets of revised lists of specifications to be used for this project.
3. Drawings: The drawings shall be 30% complete, and include the following information:
a. All Disciplines:
1) All demolition work.
2) Environmental controls (dust partitions, signage, etc.).
3) Show and identify existing, verified dimensions, conditions, and interfacing.
4) Show items to be removed.
5) Provide symbol sheets and explanation of symbols used.
6) Provide plans to show Interim Life Safety Plan, Phasing Plan, Security, and Environmental barriers. Submit, as a minimum, a single line layout for all floors and roof areas with double line exterior walls at a scale not less than 1/8" = 1'-0". These drawings should show all rooms, doors, corridors, basic column grid, assumed column sizes, expansion and seismic joint locations, electrical closets and equipment rooms, signal and telephone closets, mechanical shafts and space, and all vertical circulation, e.g., stairs, conveyers, elevators (personnel and service), and automatic conveyances. In schematics, lines between spaces indicate the centerline of the partition. Along the corridor the line represents the corridor side of the partition. Net areas should be clear space and should not include partitions.
b. Site:
1) Ensure that the Contractor is aware of the limited parking and material staging areas at this location.
2) Ensure that the Contractor is aware of the limited working spaces of the project site.
c. Architectural:
1) Submit floor plans and 30% complete details, schedules, and large-scale plans.
2) Draw elevations at a 1/8” scale. As necessary, show heights, fenestration and materials.
3) Show and identify connections of new work to old work.
4) Show general notes, door schedules, and other schedule data.
5) Indicate fire and smoke partitions.
6) Show the location of new equipment.
7) Show the ceiling mounted equipment.
8) Label each room or space with its name and the required program net area over the designed net area. The area figures will appear in fractional form, e.g., 400/390. The designed net area shall exclude such circulation space within the room as is permitted by the space planning criteria.
d. Civil / Structural:
1) Show existing structural and new work, if applicable.
2) Work with the equipment supplier to determine the added floor and ceiling loading, if required. Show structural modifications, if required. Also, show the uni-strut system if required.
e. Plumbing / Piping:
1) Show existing plumbing that will be affected by renovations and modifications. Through site verification, show shut-off valves. Show all areas that will be affected by a shutdown.
2) Show temporary and permanent relocations.
3) Show points of connection.
4) Show all piping, including sizes.
f. Heating, Ventilation and Air Conditioning (HVAC):
1) Provide preliminary load calculations.
2) Provide sketches and schematics and a schedule of points to be monitored by graphic control center.
3) Provide 1/4" scale drawings for equipment, piping, ductwork and other interfacing elements.
4) Show connections between new and old work. Show riser diagrams.
5) Provide demolition drawings and show extent of disruption to areas adjacent to or affected by the modifications.
6) Provide drawings to show the extent that asbestos fireproofing will be encountered.
7) Provide an equipment schedule.
8) Show one-line diagrams of hot, chilled, condenser water, refrigerant and steam piping.
9) Notations for types and sizes of hoods and grease and/or bacteriological filters, when required.
10) Provide a 1/4" scale drawing of equipment and/or fan room arrangement.
11) All heating and steam consuming equipment must be suitably described.
g. Electrical:
1) The electrical drawings shall be 30% complete, showing controls, conduits, wire sizes, points of origination and termination, motor sizes, nomenclature, and all other items necessary for a contractor / estimator to do a take-off.
2) Have one lighting print, one power print, and one signal print.
3) Provide computer terminals, extension of stentophone intercom system, local intercom, nurse call (code blue) system, fire alarm system diagrams and other necessary systems.
4) Provide one-line power and noise diagrams, and signal diagrams.
5) Provide a preliminary panel schedule.
6) Provide an equipment schedule for all equipment (including all medical equipment), showing manufacturer or basis of design, voltage, amperage, phase, conduit size, and conductor size.
h. Phasing:
1) Present revised phasing plans that will accomplish the construction work with a minimum amount of disruption to the normal operations of the hospital.
4. Estimates: See “Estimate Submission Requirements.”
5. Acceptance: If the documents do not meet all of the requirements of this submission, then the portions of the documents that are not acceptable by the VA according to the design standards and criteria must be updated by the A/E prior to moving on to the next scheduled submission.
End of Design Development “DD”
III. CONTRACT DOCUMENTS STAGE (FOR EACH DESIGN PHASE “CD”):
A. THIRD REVIEW: First Contract Document Submission (CD1) submission – 65% complete.
1. Submittals: Three (3) copies of calculations, computations, and engineering data, three (3) copies of drawings (1 full size and two half size), two (2) copies of specifications (one in a loose – leaf binder), updated as – built drawings for each discipline, all marked up documents from the previous submissions and three (3) copies of the cost estimate. Also, provide one (1) electronic copy of the 65% drawings in accordance with section I.D.6.
2. Specifications: Submit two (2) copies of the specification sections to suit the project. All editing and mark - ups shall easily identify modifications, deletions, and insertions through tracking of changes with the Word document. The electronic copy of specifications shall be merged into one document. "Catch-all" terms and generalizations shall be avoided. Items not relative to the project shall be edited out. The specifications shall be substantially complete as to content, checked and coordinated so that only an overall review will be necessary at the final working drawing submission. One copy to be in a loose - leaf binder with one CD electronic copy of the specs.
3. Drawings: The drawings shall be 65% complete.
a. All Disciplines:
1) Demolition work.
2) Environmental controls.
3) Show and identify existing, verified dimensions, conditions, and interfacing.
4) Show items to be removed.
5) Provide symbol sheets and an explanation of the symbols used.
6) Provide plans to show Interim Life Safety Plan, Phasing Plan, Security, and Environmental barriers.
b. Site:
1) Ensure that the Contractor is aware of the limited parking and material staging areas at this location.
c. Architectural:
1) Submit near complete floor plans and 65% complete details, schedules, and large - scale plans.
2) Draw elevations at 1/8" scale. As necessary, show heights, fenestration and materials.
3) Show and clearly identify connections of new work to old work.
4) Show environmental controls, including dust partitions and appropriate signage.
5) Show general notes, door schedules, and other schedule data.
6) Show reflected ceiling plan.
7) Show room finish symbols.
8) Indicate fire and smoke partitions.
9) Show location of new equipment.
10) Show ceiling mounted equipment and mounting details if required.
d. Civil / Structural:
1) Show existing structural and new work, if applicable.
2) Work with the equipment supplier to determine the added floor and ceiling loading, if required. Show structural modifications, if required. Also, show the uni-strut system if required.
e. Plumbing / Piping:
1) Show existing plumbing that will be affected by renovations and modifications. Through site verification, show shut-off valves. Show all areas that will be affected by a shutdown.
2) Show temporary and permanent relocations.
3) Clearly show points of connection.
4) Show all piping, including sizes.
5) The drawings for this submission shall be substantially complete.
f. Heating, Ventilation and Air Conditioning (HVAC):
1) Provide complete load and sizing calculation for all HVAC.
2) Provide drawings and schematics and schedule of points to be monitored by graphic control center.
3) Provide flow and control diagrams for steam and condensate water.
4) Provide a sequence of operations for all HVAC Systems.
5) Provide 1/4" scale drawings for equipment, piping, ductwork and other interfacing elements.
6) Clearly show connections between new and old work. Show riser diagrams.
7) Provide demolition drawings and show extent of disruption to areas adjacent to or affected by the modifications.
8) Provide drawings to show the extent that asbestos fireproofing will be encountered.
9) Show control diagrams.
10) Show equipment schedule.
11) Show major details, elevations, sections and legends, show sections of all critical points.
12) The drawings and calculations for this submission shall be substantially complete.
13) Coordinate with the Controls application system for the facility to show all control points and tie-ins.
14) Plan the layout of all equipment, ductwork and piping, including the following: air handling units, including all components, coils, humidifiers, filters, pumps, heat exchangers, tanks and piping specialties, such as PRV, TCV, traps, etc.
15) Show exhaust fans.
16) Show grill and diffuser locations.
17) Show hot, chilled, condenser water, refrigerant and steam piping.
18) Notations for types and sizes of hoods and grease and / or bacteriological filters, when required.
19) Provide a 1/4" scale drawing of equipment and/or fan room arrangement.
20) All heating and steam consuming equipment must be suitably described.
21) Submit an elementary diagram of additional controls.
22) Provide a one-line diagram of all systems.
g. Electrical:
1) The electrical drawings shall be substantially complete, showing all controls, conduits, wire sizes, points of origination and termination, motor sizes, nomenclature, and all other items necessary for a contractor / estimator to do a take-off.
2) Have one lighting print, one power print, and one signal print.
3) Provide computer terminals, extension of existing stentophone intercom system, local intercom, nurse call (code blue) system, fire alarm system diagrams and other necessary systems.
4) Provide one-line power and noise diagrams, and signal diagrams.
5) Provide the panel schedule, complete with circuit breaker sizes and equipment designation.
6) Provide an equipment schedule for all equipment (including all medical) showing manufacturer or basis of design, voltage, amperage, phase, conduit size, conductor size.
7) The drawings shall be substantially complete.
4. Phasing: Present proposed phasing plans that will accomplish the construction work with a minimum amount of disruption to the normal operations of the hospital.
5. Code: Provide an investigation and explanation of code requirements incorporated into the design. Furnish a copy of each code quoted or used in the design.
6. Estimate: See “Estimate Submission Requirements.”
7. Acceptance: If the documents do not meet all of the requirements of this submission, then the portions of the documents that are not acceptable by the VA according to the design standards and criteria must be updated by the A/E prior to moving on to the next scheduled submission.
B. FOURTH REVIEW: Second Contract Document Submission (CD2) submission – 95% complete.
1. Submittals: Four (4) copies of drawings (2 full size and 2 half size), the marked–up drawings from the third submission, four (4) copies of the updated cost estimates, two (2) copies of the specifications, and the marked–up specifications from the third review. Also, provide one (1) electronic copy of the 95% drawings in accordance with section I.D.6.
2. Specifications: The specifications shall be in final draft, completely edited and checked, per earlier description, and two (2) copies, one in a loose-leaf binder.
3. Drawings: The drawings shall be 95% complete.
a. Architectural:
1) Submit completed plans, elevations, details, and schedules.
2) Completed interior finish schedules and color design.
b. Civil / Structural:
1) Submit complete plans, elevations, sections, details, schedules, and general notes.
c. Plumbing / Piping:
1) Provide complete drawings, elevations, plans, details, and riser diagrams. Show fire sprinkler systems.
d. Heating, Ventilation and Air Conditioning (HVAC):
1) Provide complete coordinated HVAC drawings and calculations. Provide all plans, sections, elevations, details, calculations, flow and control diagrams, and schedules. Provide detailed connection to the Central Energy Plant (CEP).
e. Electrical:
1) Provide all drawings, elevations, plans, details, and schedules. Indicate all circuiting of all systems on drawings. Show details and sections of all areas where possible conflict with other trades exists.
2) Show final sizes, ratings, feeders, and identification of all electrical equipment and outlets.
4. Life Safety: The Certified Independent Third Party Safety Professional Review must be completed and a letter with comments submitted with this submission.
5. Estimate: See "Estimate Submission Requirements." The estimate shall be presented in complete form to reflect quantitative material cost, labor costs, and overhead and profit anticipated on date of bid opening.
6. Acceptance: If the documents do not meet all of the requirements of this submission, then the portions of the documents that are not acceptable by the VA according to the design standards and criteria must be updated by the A/E prior to moving on to the next scheduled submission.
C. FINAL SUBMISSION (100%): After material of the Fourth Review has been reviewed, the A/E shall make necessary changes to incorporate all review comments (VA, CITP Safety Review, etc.) and furnish the following:
1. Specifications: Six (6) copies of the edited specifications double-sided in loose-leaf form ready for photocopying. One copy in a 3-ring binder, labeled. Format to be as stated earlier under “Specifications.” Provide an electronic file of the specifications in MS Word 2007 with all specification files merged into one file.
2. Drawings: The drawings shall be 100% complete in every respect. Provide six (6) complete sets of drawings, three (3) full-size prints and three (3) half-size prints. Also provide two (2) electronic copies of the drawings in accordance with section I.D.6.
3. Provide one sealed set of original film drawings. Each discipline shall be separately sealed.
4. Provide all calculations for the project including, but not limited to, architectural, structural, plumbing, mechanical, and electrical.
5. Provide two (2) CD-ROMs with all project materials, including drawings, specifications, and calculations.
D. CONSTRUCTION PERIOD SERVICES:
1. At project completion, the A/E shall update the As-Built drawings and furnish two (2) updated sets of prints / record drawings (one set to be film), and two (2) electronic copies in accordance with section I.D.6.
2. The A/E firm shall review and answer all RFI’s related to the design within 10 calendar days and review all submittals for the project within 10 calendar days. The A/E shall review and approve the acceptance testing results provided by the Contractor on behalf of the VA for all building and utility systems.
3. A physicist will not need to be used for this project.
4. ASBESTOS – Provide a CIH to monitor construction. Provide close out paperwork as required by OSHA, EPA, and VA Policies.
James A. Haley VA Hospital Renovate Pharmacy to Meet USP800 Project No. 673-18-109
5.
Design-Build Statement of Work, Revised June 2010
SECTION 01 00 00
CONSTRUCTION GENERAL REQUIREMENTS
TABLE OF CONTENTS
| 1.1 GENERAL INTENTION | 23 |
| 1.2 STATEMENT OF BID ITEM(S) | 24 |
| 1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR | 25 |
| 1.4 CONSTRUCTION SECURITY REQUIREMENTS | 25 |
| 1.5 FIRE SAFETY | 28 |
| 1.6 OPERATIONS AND STORAGE AREAS | 31 |
| 1.7 ALTERATIONS | 40 |
| 1.8 INFECTION PREVENTION MEASURES | 42 |
| 1.9 DISPOSAL AND RETENTION | 45 |
| 1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS | 47 |
| 1.11 RESTORATION | 49 |
| 1.12 PHYSICAL DATA | 49 |
| 1.13 PROFESSIONAL SURVEYING SERVICES | 50 |
| 1.14 LAYOUT OF WORK | 50 |
| 1.15 AS-BUILT DRAWINGS | 51 |
| 1.16 USE OF ROADWAYS, PARKING LOTS AND GROUNDS | 52 |
| 1.17 COTR AND CONTRACING OFFICER'S FIELD OFFICES | 53 |
| 1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT | 53 |
| 1.19 TEMPORARY USE OF EXISTING ELEVATORS | 54 |
| 1.20 TEMPORARY TOILETS | 55 |
| 1.21 AVAILABILITY AND USE OF UTILITY SERVICES | 56 |
| 1.22 NEW TELEPHONE EQUIPMENT | 58 |
| 1.23 TESTS / COMMISSIONING | 58 |
| 1.24 INSTRUCTIONS | 59 |
| 1.25 GOVERNMENTFURNISHED PROPERTY | 60 |
| 1.26 RELOCATED EQUIPMENT AND ITEMS | 61 |
| 1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT | 62 |
| 1.28 CONSTRUCTION SIGN | 62 |
| 1.29 SAFETY SIGN | 63 |
| 1.30 CONSTRUCTION DIGITAL IMAGES | 63 |
| 1.31 FINAL ELEVATION DIGITAL IMAGES | 64 |
| 1.32 HISTORIC PRESERVATION | 65 |
| 1.33 EQUIPMENT | 65 |
| 1.34 FINAL PAYMENT | 65 |
| 1.35 WARRANTY CALLS | 65 |
| 1.36 ATTACHMENTS | 66 |
Construction General Requirements, Revised June 2010 Section 01 00 00 – Page 22
1.1 GENERAL INTENTION
| A. | Contractor shall completely prepare site for building operations, including demolition and other items as indicated herein. The Contractor shall furnish all necessary equipment, labor, materials, temporary equipment and items, tools, specialty services, supervision, and perform work for NRM Project No. 673-18-109, “Renovate Pharmacy to meet USP800” at the James A. Haley Veterans Hospital located in Tampa, Florida as required by drawings and specifications. |
| B. | Visits to the site by Bidders are highly recommended and may be made only by appointment with the Project Manager/Contracting Officer’s Technical Representative (COTR), J Johnson at telephone number (813) 972-2000 x5481. All bids will take into consideration of existing site conditions; it is the responsibility of the contractor to review the entire job site footprint and existing site conditions prior to bid submission. All proposals shall include a detailed cost breakdown (materials, labor, and equipment) by trade, specification division and section; lump sum costs are not acceptable. |
| C. | The ArchitectEngineers (A/E) will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative. |
| D. | Before placement and installation of work subject to tests by testing laboratory or other parties retained by Department of Veterans Affairs, the Contractor shall notify the COTR and Contracting Officer (CO) in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than seven (7) calendar days, unless otherwise designated by the COTR and Contracting Officer. |
| E. | All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA Police, be identified by project and employer, and restricted from unauthorized access. |
| F. | Prior to commencing work, general contractor shall provide proof that an OSHA certified “competent person” (CP) [(29 CFR 1926.20(b)(2)] will maintain a presence at the work site whenever the general or subcontractors are present. |
| G. | Training: |
| 1. | Beginning July 31, 2005, all supervisory type personnel and employees of general contractor and subcontractors shall have the 30-hour OSHA certified Construction Safety course and other relevant competency training, as determined by VA CP with input from the ICRA team. |
2. Beginning July 31, 2005, all non-supervisory type personnel and employees of general contractor and subcontractors shall have the 10-hour OSHA certified Construction Safety Course and other relevant competency training, as determined by VA CP with input from the ICRA team.
| 3. | Submit copies of certificates and training records for all such personnel and employees that may be and/or will be on the work site(s) to the COTR and Contracting Officer for approval before the start of any work on-site. |
| H. | Related Work: This specification section applies to ALL Divisions (0 through 34) of work under ALL other specification sections. A partial list of Codes and Standards adopted by the Department of Veterans Affairs is attached in Appendix B. |
| I. | Normal Operation / Construction Hours: Construction operations at the James A. Haley VA Hospital are 7:30 AM to 4:30 PM, Monday through Friday, with the exception of Federal Holidays. Requests to work beyond normal work hours shall be submitted in writing to the Resident Engineer / COTR for approval and will include a description of work to be performed. Approval is subject to availability of the Resident Engineer / COTR, type of work to be performed, and the specific hours requested. Contractors are reminded that patients are generally asleep after 10:00 PM. Approval to work beyond this time will also include an evaluation of the anticipated noise level generated by the contractor. Under no circumstances will the contractor proceed without express, written approval of the Resident Engineer / COTR. |
1.2 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Provide all necessary equipment, labor, materials, specialty services, supervision, and tools to complete NRM Project No. 673-18-109, “Renovate Pharmacy to meet USP800”. All work is to be completed in 365 calendar days.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Additional sets of drawings and specifications may be made by the Contractor, at Contractor's expense, from PDF document copies that can be requested from the COTR’s electronic files.
B. Additional sets of drawings and specifications may be made by the Contractor, at Contractor's expense, from electronic or reproducible hard copy prints furnished by the ISSUING OFFICE. Such media or prints shall be returned to the ISSUING OFFICE immediately after printing is completed.
1.4 construction security requirements
| A. | Security Plan: |
| 1. | The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project. |
| 2. | The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations. |
3. The General Contractor shall furnish to the COTR and Contracting Officer lists of employees that will be or may be on the construction site(s). The List shall be on Company letter head that provides all of the company contact information, shall provide the project number and title, locations of work, names of the employees, their titles, their job types, and personal contact numbers (i.e. cell phone). All sub-contractors, vendors and suppliers for the project shall furnish the same listing on their individual company letter heads to the GC whom will provide the lists to the COTR and Contracting Officer. These lists shall be updated as necessary during the entire duration of the project. These lists may be used to provide a check list record of personnel on-site each day to be provided with the contractors Daily Log reports. These lists may be used to provide a check list record of personnel on-site each day to be provided to the VA Police Department and their Dispatch Office where normal sign in and sign out occurs.
| B. | Security Procedures: |
| 1. | General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site. |
| 2. | For working outside the “regular hours” as defined in the contract, The General Contractor shall provide a request for approval 14 calendar days prior to the requested date, to the Contracting Officer and COTR, so that security, escort and other appropriate arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section. |
| 3. | No photography of VA premises is allowed without written permission of the Contracting Officer. |
| 4. | VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer. |
| C. | Guards: |
| 1. | The General Contractor shall not be required to provide unarmed guards at the project site twenty-four (24) hours a day, seven (7) days a week or after construction hours. |
| 2. | Any guard provided shall have communication devices to report events as directed by VA Police. |
| 3. | The General Contractor is not required to install equipment for recording guard rounds to ensure systematic checking of the premises. |
4. The General Contractor may need to provide a guard as required by the contract drawings and specifications, including specification sections for Asbestos Abatement.
| D. | Key Control: |
| 1. | The General Contractor shall provide duplicate keys and lock combinations to the COTR and Contracting Officer for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action. |