Attachment IV 557-23-104 Construction SOW.docx
DOCX document 18 KB Posted
- Attached to
- Z2DA--FY27 NRM | 557-23-104 | Replace Boiler Plant Steam Boilers | Construction (VA-27-00003633)
- Solicitation number
- 36C24726R0137
About this file
This is a Statement of Work (SOW) for a construction project to replace three steam boilers and associated equipment at Building 27 of the Carl Vinson VA Medical Center in Dublin, Georgia. The base bid requires the contractor to provide management, supervision, materials, tools, and labor for the complete replacement project, including temporary boiler plant and control room setup, hazardous material abatement, demolition of existing equipment and piping, installation of new plant equipment and piping, site work, fuel tank installation and piping, and emergency generator installation. The work will be performed in accordance with all applicable Federal, State, and local regulations and must be completed within 730 days from issuance of the Notice to Proceed. An alternative bid deduct option removes the requirement for the contractor to engage a third-party commissioning agent while maintaining all other commissioning requirements.
Key project requirements include: the prime contractor's superintendent must hold OSHA 30-hour certification and all workers must have minimum OSHA 10-hour certification; a construction schedule must be provided within 30 days of Notice to Proceed and updated with each payment request; normal work hours are 7:00 AM to 5:00 PM unless otherwise approved by the Contracting Officer's Representative (COR); all contractors must provide negative TB test results within 90 days prior to site access and obtain VA contractor badges; utility shutdowns require a minimum of 10 working days' notice and cannot exceed 4 hours; and contractors must comply with all infection control procedures and site-specific health protocols established by Carl Vinson VAMC. On-site parking and a laydown yard on the south side of Building 27 are permitted, and the contractor must submit a debris removal and recycling plan for approval prior to demolition.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Replace Boiler Plant Steam Boilers Project# 557-23-104
SCOPE OF WORK
Contractor will provide management, supervision, materials, tools, and labor to replace three steam boilers in Building 27 at the Carl Vinson VAMC Dublin, Georgia. Work will include but is not limited to temporary boiler plant and control room, hazardous material abatement, demolition of existing plant equipment, piping, and electricity, installation of new plant equipment and piping, site work, fuel tank installation and piping, and emergency generator installation based on provided A/E design drawings and specifications. All work will be done in compliance with Federal, State, and local regulations.
Construction will take place in Building 27 at the Carl Vinson VA Medical Center located at 1826 Veterans Blvd in Dublin, GA 31021.
ITEM I, GENERAL CONSTRUCTION: BASE BID:
Replacement of three steam boilers and all associated equipment and pipework. Work will include but is not limited to temporary boiler plant and control room, hazardous material abatement, demolition of existing plant equipment, piping, and electricity, installation of new plant equipment and piping, site work, fuel tank installation and piping, and emergency generator installation based on provided A/E design drawings and specifications.
Period of Performance: 730 days after issuance of Notice to Proceed.
ITEM II, GENERAL CONSTRUCTION: BASE BID MINUS BID DEDUCT 1: Remove Contractor-hired 3rd Party Commissioning Agent
Replacement of three steam boilers and all associated equipment and pipework. Work will include but is not limited to temporary boiler plant and control room, hazardous material abatement, demolition of existing plant equipment, piping, and electricity, installation of new plant equipment and piping, site work, fuel tank installation and piping, and emergency generator installation based on provided A/E design drawings and specifications.
Deduct requirement for Contractor to engage 3rd Party Commissioning Agent. All other commissioning requirements remain intact.
Period of Performance: 730 days after issuance of Notice to Proceed.
General Conditions
Contractors will be allowed to park on site. Laydown yard for this project will be on the South side of Building 27, adjacent to temporary boiler plant location.
Prime contractor’s Superintendent is required to have an OSHA 30-hour certification and all other contractors regardless of position are required to have at a minimum OSHA 10-hour certification before being allowed to work on construction site. Copies of certification will be kept in superintendent’s office; electronic or hard copies are acceptable.
Prime contractor is required to provide a construction schedule within 30 days of Notice to Proceed. Additionally, an updated construction schedule is required with each payment request. Payments will not be processed unless they are accompanied by an updated construction schedule and Certified Payroll.
Normal work hours will be between 7am and 5pm any deviation to these times will need the approval of the COR. After hours work is allowed with the coordination of the COR.
Contractor will be required to follow the Infection Control procedures identified in the Pre-Construction Risk Assessment and Infection Control Risk Assessment documentation. If conditions arise all contractors will be subject to Carl Vinson VAMC protocols for COVID conditions or any other health matter which may arise. All contractors are required to provide a valid TB test resulting in a negative reading within the past 90 days prior to being allowed access to work site (Ref. Spec 01 35 26 1.13).
All contractors will be required to obtain a contractor badge which will be provided by the VA. Prior to beginning work, badge documents (provided by the VA to the Prime Contractor) will be filled out and given to the Site Superintendent. COR will review and sign badge documents and escort contractors to the badging location. Once issued, badges will be worn at all times while on station and be visible.
Utility shutdowns will be scheduled thru the COR. A minimum of 10 working days are required for any utility shutdown. Some shutdowns are required to be done after hours and with the approval of the COR. No utility outage can last longer than 4 hours. Contractor will provide a detailed Utility Shutdown Work Request identifying what work is to be done, time expected to complete the work, and POC for work being done during shutdown.
Follow guidelines stated in Spec Section 01 74 19 for debris removal. Provide a debris removal/recycle plan to COR for approval through GEMS coordinator prior to demolition of construction area.