Attachment III 557-23-104 - Bid Documents - Specifications REV28Oct2026_.pdf

PDF 7 MB Posted

Attached to
Z2DA--FY27 NRM | 557-23-104 | Replace Boiler Plant Steam Boilers | Construction (VA-27-00003633)
Solicitation number
36C24726R0137
Issued by

About this file

This is a Bid Documents Specifications file for Project 557-23-104, Replace Boiler Plant Steam Boilers, issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7. The solicitation number is 36C24726R0137, and this represents a construction contract opportunity for the replacement of steam boilers at a boiler plant facility. The specifications document, revision dated October 28, 2026, establishes the technical requirements and performance standards that bidders must meet when submitting proposals for the boiler replacement work.

The file contains detailed engineering specifications, equipment requirements, installation standards, and performance criteria necessary for contractors to understand the scope and technical parameters of the boiler plant steam boiler replacement project. As a specifications document, it serves as the technical foundation for the Request for Proposal, defining what products, systems, and construction methods are required to satisfy the government's project objectives. Bidders must comply with all specifications outlined in this document when developing their proposals and cost estimates for the boiler replacement work at the Veterans Affairs facility.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT # 557-23-104

Replace Boiler Plant Steam Boilers

Carl Vinson VA Medical Center 1826 Veterans Boulevard Dublin, GA 31021-3620

SPECIFICATIONS

BID DOCUMENTS 100% REV

07/10/2026

PREPARED BY

Carl Vinson VA Medical Center, Project 557-23-104

08-01-2025

TABLE OF CONTENTS

00 01 10 - 1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24 01 33 23 Shop Drawings, Product Data, and Samples 06-25 01 35 26 Safety Requirements 05-24 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 06-21 01 57 19 Temporary Environmental Controls 01-21 01 74 19 Construction Waste Management 04-22 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 04-22

DIVISION 02 – EXISTING CONDITIONS

02 21 13 Site Surveys 12-23 02 41 20 Selective Building Demolition 02 82 11 Traditional Asbestos Abatement 01-21 02 82 13.13 Glovebag Asbestos Abatement 01-21 02 82 13.21 Asbestos Roofing Abatement 01-21 02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 01-21 04 20 00 Unit Masonry 08-17

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18 05 36 00 Composite Metal Decking 01-21 05 50 00 Metal Fabrications 08-18 05 51 00 Metal Stairs 01-21

08-01-2025

TABLE OF CONTENTS

00 01 10 - 2

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21 08 71 00 Door Hardware 03-24 08 90 00 Louvers and Vents 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 67 23.60 Resinous Urethane and Epoxy Mortar Flooring (RES-6A and

RES 6B)

01-21

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21 10 44 16 Fire Extinguisher

DIVISION 11 – EQUIPMENT

DIVISION 12 – FURNISHINGS

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural Components

01-21

DIVISION 14– CONVEYING EQUIPEMENT

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23 22 05 19 Meters and Gages for Plumbing Piping 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19

08-01-2025

TABLE OF CONTENTS

00 01 10 - 3

SECTION NO DIVISION AND SECTION TITLES DATE

22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20 22 13 23 Sanitary Waste Interceptors 09-20 22 15 00 General Service Compressed-Air Systems 09-20 22 31 11 Water Softeners 09-15 22 40 00 Plumbing Fixtures 05-24

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 10 Common Work Results for Boiler Plant and Steam Generation

06-24

23 05 11 Common Work Results for HVAC 03-23 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 03-23

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

03-23

23 05 51 Noise and Vibration Control for Boiler Plant 03-22 23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-23 23 08 11 Demonstrations and Tests for Boiler Plant 04-20 23 09 11 Instrumentation and Control for Boiler Plant 04-24 23 09 23 Direct-Digital Control System for HVAC 03-23 23 10 00 Facility Fuel Systems 04-20 23 21 11 Boiler Plant Piping Systems 03-24

03-24 23 23 00 Refrigerant Piping 03-24 23 31 00 HVAC Ducts and Casings 03-23 23 34 00 HVAC Fans 03-23 23 37 00 Air Outlets and Inlets 03-23 23 50 11 Boiler Plant Mechanical Equipment 03-22 23 51 00 Breechings, Chimneys, and Stacks 04-20 23 52 39 Fire Tube Boilers 06-25 23 81 00 Decentralized Unitary HVAC Equipment 03-24 23 82 16 Air Coils 03-24

DIVISION 25 – INTEGRATED AUTOMATION

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 05 73 Overcurrent Protective Device Coordination Study 11-22 26 08 00 Commissioning of Electrical Systems 11-22 26 09 23 Lighting Controls 11-22 26 22 00 Low-Voltage Transformers 11-22

08-01-2025

TABLE OF CONTENTS

00 01 10 - 4

SECTION NO DIVISION AND SECTION TITLES DATE

26 24 13 Distribution Switchboards 11-22 26 24 16 Panelboards 11-22 26 27 26 Wiring Devices 11-22 26 29 11 Motor Controllers 11-22 26 29 21 Enclosed Switches and Circuit Breakers 11-22 26 32 13 Engine Generators 11-22 26 36 23 Automatic Transfer Switches 11-22 26 43 13 Surge Protective Devices 11-22

26 51 00 Interior Lighting 03-24

26 56 00 Exterior Lighting 11-22

DIVISION 27 – COMMUNICATIONS

27 05 26i Grounding and Bonding for Communications Systems 06-15

27 05 33i Conduits and Back Boxes for Communications Systems 12-22

27 05 53i Identification for Communications Systems 12-22

27 10 00i Structured Cabling 12-22

27 11 16i Communications Cabinets, Racks, Frames and Enclosures 12-22

27 11 19i Communications Termination Blocks and Patch Panels 12-22

27 13 23.13i

Communications Optical Fiber Splicing and Terminations 12-22

27 13 23i Communications Optical Fiber Backbone Cabling 12-22

27 15 13i Communications Copper Horizontal Cabling 12-22

27 16 19i Communications Patch Cords, Station Cords and Cross Connect Wire

12-22

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and

Security 10-18

28 05 26 Grounding and Bonding for Electronic Safety and Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

09-11

28 13 00 Physical Access Control System 10-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 08-23 31 23 19 Dewatering 10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 12 16 Asphalt Paving 09-15

08-01-2025

TABLE OF CONTENTS

00 01 10 - 5

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 33 – UTILITIES

33 30 00 Sanitary Sewer Utilities 06-13

DIVISION 34 – TRANSPORTATION

DIVISION 48 – Electrical Power Generation

APPENDIX A – Pre-Renovation Asbestos Inspection and Lead Paint Sampling

05-01-20

LIST OF DRAWING SHEETS

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI000 COVER SHEET

GI001 SYMBOLS, ABBREVIATIONS AND ACCESSIBILITY

GI002 WALL TYPES, ACCESSIBILITY REQUIREMENTS

GI003 LIFE SAFETY PLANS

GI004 PHASING PLAN

CIVIL

C100 CIVIL DETAILS

C101 CIVIL DETAILS

C102 CIVIL DETAILS

C200 EXISTING SITE PLAN - NORTH

C201 EXISTING SITE PLAN - SOUTH

C210 SITE DEMOLITION PLAN - NORTH

C211 SITE DEMOLITION PLAN - SOUTH

C300 CONSTRUCTION PHASE SITE PLAN - NORTH

C301 CONSTRUCTION PHASE SITE PLAN - SOUTH

C400 SITE LAYOUT PLAN - NORTH

C401 SITE LAYOUT PLAN - SOUTH

C500 SITE UTILITY PLAN - NORTH

C501 SITE UTILITY PLAN - SOUTH

C600 SITE GRADING PLAN - NORTH

C601 SITE GRADING PLAN - SOUTH

STRUCTURAL

S001 STRUCTURAL GENERAL NOTES

SD101 FOUNDATION AND SLAB DEMOLITION PLANS

SD102 FRAMING DEMOLITION PLANS

SB101 FOUNDATION AND SLAB PLANS

SB501 FOUNDATION SECTIONS AND DETAILS

SF101 MEZZANINE, CATWALK, AND ROOF FRAMING PLANS

SF201 EXTERIOR ELEVATIONS

05-01-20

LIST OF DRAWING SHEETS

00 01 15 - 2

Drawing No. Title

SF401 ENLARGED FRAMING PLANS

SF402 ENLARGED FRAMING PLANS

SF501 FRAMING SECTIONS AND DETAILS

ARCHITECTURE

AD101 DEMOLITION PLANS

AE101 FIRST FLOOR

AE102 MEZZANINE PLANS

AE131 MEZZANINE AND ROOF PLAN

AE141 REFLECTED CEILING PLANS

AE201 EXTERIOR ELEVATIONS

AE202 EXTERIOR ELEVATIONS

AE301 BUILDING SECTIONS

AE311 WALL SECTIONS

AE312 WALL SECTIONS

AE401 ENLARGED DETAILS

AE402 ENLARGED DETAILS

AE601 SCHEDULES

FIRE SUPPRESSION

F001 FIRE SUPPRESSION ABBREVIATIONS, LEGEND AND DESIGN NOTES

FX101 FIRE SUPPRESSION FIRST FLOOR PLAN

FX102 FIRE SUPPRESSION MEZZANINE PLAN

PLUMBING

P001 PLUMBING ABBREVIATIONS, LEGEND, & GENERAL NOTES

PD100 PLUMBING UNDERSLAB PLAN - DEMO

PD101 PLUMBING FIRST FLOOR PLAN - DEMO

PD102 PLUMBING MEZZANINE PLAN - DEMO

PP100 PLUMBING UNDERSLAB PLAN - DRAINAGE

PP101 PLUMBING FIRST FLOOR PLAN

PP102 PLUMBING MEZZANINE PLAN

P500 PLUMBING SCHEDULES & DETAILS

P901 ISOMETRIC - DRAINAGE

P902 ISOMETRIC - DISTRIBUTION

05-01-20

LIST OF DRAWING SHEETS

00 01 15 - 3

Drawing No. Title

MECHANICAL

M001 MECHANICAL LEGEND

MD101 MECHANICAL - DEMOLITION FIRST FLOOR PLAN

MH101 MECHANICAL - FIRST FLOOR PLAN

MH102 MECHANICAL - MEZZANINE LEVEL 1 PLAN

MH103 MECHANICAL - MEZZANINE LEVEL 2 PLAN

MH104 MECHANICAL - PENTHOUSE PLAN

MPH101 MECHANICAL - FIRST FLOOR PLAN - PIPING

MPH102 MECHANICAL - MEZZANINE LEVEL 1 PLAN - PIPING

MPH103 MECHANICAL - MEZZANINE LEVEL 2 PLAN - PIPING

MPH104 MECHANICAL - PENTHOUSE PLAN - PIPING

M401 MECHANICAL - ELEVATIONS

M402 MECHANICAL - ELEVATIONS

M403 MECHANICAL - 3D VIEWS

M501 MECHANICAL - DETAILS

M502 MECHANICAL - DETAILS

M601 MECHANICAL - SCHEDULES

M602 MECHANICAL - SCHEDULES

M701 MECHANICAL - HVAC CONTROLS

MP001 BOILER PLANT NOTES, LEGENDS, AND ABBREVIATIONS

MP101 TRENCH LEVEL DEMOLITION

MP102 OPERATING FLOOR DEMOLITION

MP103 MEZZANINE DEMOLITION

MP104 ROOF DEMOLITION

MP105 PLANT EXTERIOR DEMOLITION

MP201 TRENCH LEVEL NEW WORK

MP202 OPERATING FLOOR NEW WORK

MP203 MEZZANINE NEW WORK

MP204 ROOF NEW WORK

MP205 PLANT EXTERIOR NEW WORK

MP301 BOILER - MECHANICAL VIEWS - NEW WORK

MP302 FEEDWATER - MECHANICAL VIEWS - NEW WORK

MP303 CST - MECHANICAL VIEWS - NEW WORK

MP304 STEAM HEADER - MECHANICAL VIEWS - NEW WORK

MP305 SAMPLE COOLERS - MECHANICAL VIEWS - NEW WORK

MP306 FUEL OIL - MECHANICAL VIEWS - NEW WORK

05-01-20

LIST OF DRAWING SHEETS

00 01 15 - 4

Drawing No. Title

MP307 PRV STATIONS - MECHANICAL VIEWS - NEW WORK

MP401 BOILERS 1 & 2 FUEL P&ID SCHEMATICS - DEMOLITION

MP402 BOILERS 1 & 2 TRIM P&ID SCHEMATICS - DEMOLITION

MP403 BOILER 3 FUEL P&ID SCHEMATIC - DEMOLITION

MP404 BOILER 3 TRIM P&ID SCHEMATIC - DEMOLITION

MP405 STEAM P&ID - DEMOLITION

MP406 CONDENSATE RETURN P&ID - DEMOLITION

MP407 CTT P&ID - DEMOLITION

MP408 DEAERATOR AND FEEDWATER P&ID - DEMOLITION

MP409 FUEL OIL AND NATURAL GAS P&ID - DEMOLITION

MP410 CITY WATER AND SOFT WATER P&ID - DEMOLITION

MP411 BLOWDOWN P&ID - DEMOLITION

MP501 BOILER FUEL TRAINS AND TRIM P&ID - NEW WORK

MP502 BOILER FUEL TRAINS AND TRIM P&ID - NEW WORK

MP503 DEAERATOR AND FEEDWATER P&ID

MP504 CONDENSATE TANK P&ID

MP505 STEAM P&ID

MP506 NATURAL GAS AND PROPANE P&ID

MP507 BOILER BLOWDOWN P&ID

MP508 CHEMICAL FEED SYSTEM

MP509 FUEL OIL P&ID

MP510 TEMPORARY BOILERS

MP601 BOILER DETAILS

MP602 BOILER DETAILS

MP603 BOILER DETAILS

MP604 BOILER DETAILS

MP605 BOILER DETAILS

MP701 BOILER PLANT SCHEDULES

MP702 BOILER PLANT SCHEDULES

MP703 BOILER PLANT PIPING INDEX

MP704 VALVE SCHEDULE

MP705 VALVE SCHEDULE

MP706 HAZARDOUS GAS DETECTION SYSTEM DETAILS

MP707 EMERGENCY STOP DETAILS

MP708 CONTROLS SYSTEM ARCHITECTURE

MP709 TEMPORARY BOILER CONTROLS SYSTEM ARCHITECTURE

05-01-20

LIST OF DRAWING SHEETS

00 01 15 - 5

Drawing No. Title

MP801 BOILER CONTROL POINTS LIST

MP802 BOILER CONTROL POINTS LIST

MP803 BOILER CONTROL POINTS LIST

MP804 BOILER CONTROL POINTS LIST

ELECTRICAL

E001 ELECTRICAL NOTES, SYMBOLS AND ABBREVIATIONS

ES100 ELECTRICAL SITE PLAN

ED100 ELECTRICAL - DEMO

EL100 ELECTRICAL FIRST FLOOR PLAN - LIGHTING

EP100 ELECTRICAL FIRST FLOOR PLAN- POWER

EF100 ELECTRICAL FIRST FLOOR - SPECIAL SYSTEMS

E400 ELECTRICAL ENLARGED PLANS

E600 PANEL SCHEDULES

E700 ELECTRICAL SINGLE-LINE

TECHNOLOGY

T001 TECHNOLOGY LEGEND SHEET

TS100 TECHNOLOGY SITE PLAN

T101 FIRST FLOOR - TECHNOLOGY NEW WORK PLAN

T401 ENLARGED SIGNALS ROOM PLAN

T601 TECHNOLOGY DETAILS

T602 TECHNOLOGY DETAILS

T603 TECHNOLOGY DETAILS

---END---

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work to replace the existing steam boilers and ancillary equipment within the boiler plant as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the

Medical Center Engineering Officer.

C. Offices of FFE-Heapy JV, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

STATEMENT OF BID ITEM(S)

E. ITEM I, BASE BID: Work includes replacement of steam boilers in existing boiler plant, along with general construction, alterations, selective demolition, abatement, installation of equipment, and connections to existing utilities. Period of performance is 730 days.

F. ITEM II, Bid Deduct: Work includes base bid, with deduct to remove requirement for 3rd party commissioning agent hired by Contractor.

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.4 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 2

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 3 information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a) Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b) “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.

1.5 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 4

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 5

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. See Drawing sheet GI004 for Phasing

Plan and Notes.

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR, and Contractor.

J. Building No. 27 will be partially vacated by Government in accordance with above phasing beginning immediately after date of receipt of

Notice to Proceed and only the boiler plant area turned over to

Contractor.

K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet)

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 6 minimum height, around the construction area indicated on the drawings.

Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm

(one inch) above grade. Remove the fence when directed by COR.

L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

M. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR

ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 14 days in advance of proposed interruption.

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 7

Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

O. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 8

1.6 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of flooring, doors, windows, walls and other surfaces not required to be altered throughout the building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.

Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly.

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 9

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.7 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

PROTECTION OF EXISTING VEGETATION,

STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

B. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs

GENERAL REQUIREMENTS

01 00 00 - 10

11-01-21 or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

C. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The

Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

D. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to

Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements. RESTORATION

E. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the

COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

F. Upon completion of contract, deliver work complete and undamaged. Existing work

(walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

G. All lawn and grassed areas disturbed by construction activities, utility installation, equipment access, stockpiling, or restoration work shall be restored upon completion of the Work. Restore disturbed areas by placing topsoil as required, fine grading, fertilizing, seeding, mulching, and watering to establish a healthy, uniform stand of turf matching adjacent existing grass.

Maintain restored areas until a satisfactory stand of grass has been established. Areas exhibiting erosion, bare spots, or unsuccessful germination shall be regraded and reseeded at no additional cost to the Government until accepted by the COR.

GENERAL REQUIREMENTS

01 00 00 - 11

H. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

I. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price.

PROFESSIONAL SURVEYING SERVICES

J. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.

The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

AS-BUILT DRAWINGS

J. K. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

L. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

M. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

N. Paragraphs A, B, & C shall also apply to all shop drawings.

1.8 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the

Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 12 over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 13

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for

Contractor response, and other details deemed necessary by the

Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.

This point of contract will be located within the local service area of

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 14 the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

E. Following oral or written notification by the Contracting Officer, the

Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.

Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the

Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a)Code 1-Life Safety Systems

1) Fire suppression systems.

2) Fire alarm system(s).

b)Code 1-Air Conditioning Systems

1) Air conditioning leak in part of the building, if causing damage.

2) Air conditioning system not cooling properly.

c)Code 1 Doors

1) Overhead doors not operational, causing a security, fire or safety problem.

1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d)Code 3-Doors

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 15

1) Overhead doors not operational.

2) Interior/exterior personnel doors or hardware not functioning properly.

e)Code 1-Electrical

1) Power failure (entire area or any building operational after

1600 hours).

2) Security lights.

3) Smoke detectors.

f)Code 2-Electrical

1) Power failure (no power to a room or part of building).

Receptacle and lights not operational (in a room or part of building).

g)Code 3-Electrical

1) Exterior lights not operational.

h)Code 1-Gas

1) Leaks and pipeline breaks.

i)Code 1-Heat

1) Power failure affecting heat.

j)Code 1-Plumbing

1) Hot water heater failure.

2) Leaking water supply pipes k)Code 2-Plumbing

1) Flush valves not operating properly

2) Fixture drain, supply line or any water pipe leaking.

3) Toilet leaking at base.

l)Code 3- Plumbing

1) Leaky faucets.

m)Code 3-Interior

1) Floors damaged.

2) Paint chipping or peeling.

3) Casework damaged.

n)Code 1-Roof Leaks

1) Damage to property is occurring.

o)Code 2-Water (Exterior)

1) No water to facility.

p)Code 2-Water (Hot)

1) No hot water in portion of building listed.

q)Code 3

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 16

1) All work not listed above.

F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting

Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Contact

Address

Telephone number

Warranty response time priority code

1.9 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.10 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 17 connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

1.11 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:

1. Obtain heat by connecting to Medical Center heating distribution system, if available. Provide supplemental heat if necessary.

D. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. Electricity for all uses is available at no cost to the Contractor.

E. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes

11-01-21

GENERAL REQUIREMENTS

01 00 00 - 18 will be cause for revocation (at COR discretion) of use of water from Medical Center's system.

F. Fuel: Natural and LP gas and burner fuel oil required for boiler cleaning, normal initial boiler-burner setup and adjusting, and for performing the specified boiler tests will be furnished by the

Government. Fuel required for prolonged boiler-burner setup, adjustments, or modifications due to improper design or operation of boiler, burner, or control devices shall be furnished and paid by the

Contractor at Contractor's expense.

1.12 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems…

This is the start of the file's text. The full file is on GovTribe.