Attachment 0003A - RFI answers.pdf
PDF 971 KB Posted
- Attached to
- 508-24-102 | Replace AHUs 2, 3, 5, 17, and 19
- Solicitation number
- 36C24726R0013
About this file
This document is a Request for Information (RFI) Responses for federal contract 36C24726R0013, containing answers to 133 questions submitted by potential offerors regarding an HVAC equipment replacement project at the Atlanta VA Medical Center.
The project involves replacing five air handling units (AHUs), two exhaust recovery units (ERUs), and associated equipment across four mechanical rooms (basement, first floor, fourth floor, and sixth floor penthouse) at a VA facility. The Period of Performance has been extended to 18 months and 550 days from the original 12 months. Work must follow four construction phases, with each phase lasting approximately six weeks, and contractors must adhere to ICRA Level III infection control requirements. The existing electrical infrastructure will be utilized with new circuit breakers installed as needed; new controls must be BACnet-integrated into the Climatech system with JCI as the designated controls integrator. Temporary DX AHUs will provide cooling during construction, with adequate electrical capacity confirmed for their operation. Lead-based paint abatement is required on four AHUs in rooms 1A147 and 6A104, with testing completed September 25, 2024 confirming no asbestos in work areas. Contractors must provide certified industrial hygienists, maintain vibration isolation for new equipment, perform testing and balancing limited to new equipment at design flow rates, and coordinate off-hours work with the Contracting Officer. The VA will provide the commissioning agent; retainage may be held at 10% if necessary. Offerors should verify equipment pad dimensions during site visits, and the VA anticipates a six-month lead time for HVAC equipment procurement and six months for construction execution.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs for 36C24726R0013 – Answers in RED
1. Can the 12-month Period of Performance (POP) be changed to 18 months?
Yes, the Period of Performance is hereby extended to 18 months, 550 days. See the revised SOW attached to this amendment.
2. Can another Site Visit be established?
Yes, a follow-on site visit is available for offerors. It is scheduled for 3/3/26 at 10:00am ET at the same location as the original Site Visit (i.e., meet at the Atlanta, GA VAMC in front of the door of Room 1E115 in building 13, opposite the Emergency Department).
3. Please provide a copy of the Asbestos Survey as it relates to this project.
See Attachments to this amendment.
4. Please advise whether the bond would apply only to the labor portion of the work, given that the equipment is new and being delivered?
Bonds are to apply to the entire scope of the construction work, including both labor and materials.
5. Is it acceptable for the bonding to include a subcontractor for the total bond amount?
The prime contractor is responsible for obtaining the bonds as required by solicitation. It is acceptable for the bonding to include a subcontractor for the total bond amount if the requirements and conditions outlined in the RFO and Solicitation are met. In practice, the Contracting Officer will only accept one (1) bid bond from the offeror and one (1) each Performance and Payment bond from the awardee.
6. Who is the go-to fire alarm contractor that services the Atlanta VA Hospital?
Siemens industry inc Candace Sandusky 770 547-4851 Candace.Sandusky@siemens.com
Or
Joe McNerney, SET SIEMENS Industry Inc.
Smart Infrastructure 770-630-1247 (Mobile) Preferred 770-935-2000 (Office) joseph.mcnerney@siemens.com
7. Who is the Incumbent? There is no incumbent. This is a new construction requirement.
8. Past Contract Award #? N/A
9. Has the budget been approved for this contract? Yes
10. Is there another scheduled site visit day, date and time? No
11. Do you have the pricing template in an Excel, pdf or another form to submit back in a clean format. Please see Attachment 4 to the original solicitation on SAM.gov.
12. Are current electrical as-built drawings for the entire facility available for review, and if so, will they be provided as part of the solicitation or via amendment?
We have the original but not current as-built and will not be available as part of this solicitation.
13. Please clarify whether electrical testing under this project is limited to equipment directly supporting the replaced AHUs and ERUs, or if it includes additional electrical switchgear and switchboards elsewhere in the facility.
Testing will be performed in accordance with Specification Section 01 91 00 – Commissioning and applicable Division 26 requirements and will focus on:
Electrical systems and components that are new, modified, reconnected, or otherwise directly affected by the AHU and ERU replacement work; Verification of proper installation, operation, and integration of electrical systems serving the replaced and temporary HVAC equipment as required by the commissioning plan developed by the Commissioning Agent (CxA).
Testing of existing upstream electrical distribution equipment (including switchgear or switchboards not directly modified by this project) is not required unless:
Such testing is necessary to safely energize or recommission equipment supporting the AHUs/ERUs; or A specific deficiency is identified during functional testing or commissioning that warrants further investigation.
The Contractor remains responsible for all testing, retesting, and documentation associated with the electrical systems within the defined scope, in accordance with the Contract Documents
14. For all electrical switchgear and switchboard equipment included in the testing scope, please provide the quantities, sizing, ratings, and equipment types.
At this time, no existing facility electrical switchgear or switchboards are specifically identified for inclusion in the electrical testing scope beyond those directly serving and required to support the replaced AHUs, ERUs, and associated temporary HVAC equipment.
15. Please confirm the applicable electrical testing standard for switchgear and switchboards (e.g., NETA acceptance testing, NETA maintenance testing, or other).
a. Electrical testing for switchgear and switchboards under this project shall be performed in accordance with the Contract Documents, including Specification Section 01 91 00 – Commissioning, and the applicable Division 26 specifications.
b. The required testing standard is as follows:
i. NETA Acceptance Testing (NETA‑ATS) shall apply to new, modified, or replaced electrical equipment provided under this project, where applicable, to verify proper installation, operation, and readiness for service.
ii. NETA Maintenance Testing (NETA‑MTS) is not required for existing electrical switchgear or switchboards that are not replaced or substantially modified as part of this project.
iii. Testing of existing electrical distribution equipment shall be limited to functional or verification testing necessary to safely energize, reconnect, or commission the AHUs, ERUs, and associated temporary systems, as directed by the Commissioning Agent (CxA).
c. All testing shall be coordinated with the CxA and documented in accordance with the commissioning plan and specification requirements. The Contractor is responsible for all testing and retesting associated with equipment within the defined project scope.
16. Please identify the general locations within the building where the electrical switchgear and switchboards requiring testing are located.
a. Electrical switchgear and switchboards requiring testing under this project are limited to those located within or immediately adjacent to the mechanical rooms and electrical rooms directly serving the replaced AHUs, ERUs, and associated temporary HVAC equipment.
b. Specifically:
i. Testing is anticipated at local electrical distribution equipment (e.g., panels, disconnects, starters, or breakers) that directly supply power to the affected AHUs and ERUs.
ii. No additional upstream or facility‑wide switchgear or switchboards have been identified for testing beyond what is necessary to safely energize, reconnect, and commission the affected HVAC systems.
iii. Exact locations and equipment to be tested will be confirmed during coordination with the Commissioning Agent (CxA) and field verification and shall be limited to equipment directly impacted by the scope of work, in accordance with Specification Section 01 91 00 and applicable Division 26 requirements.
17. Please confirm whether backup and/or standby generators are included in the testing scope for this project.
a. Backup and/or standby generators are not included in the electrical testing scope for this project.
b. Electrical testing is limited to equipment directly supporting the replaced AHUs, ERUs, and associated temporary HVAC systems, as required to safely energize, reconnect, and commission those systems in accordance with the Contract Documents.
c. Testing of existing emergency, standby, or backup generators including associated switchgear, transfer switches, or distribution equipment is not required, unless a generator or related component is new, modified, or directly affected by the scope of work, or unless testing is specifically directed by the
Commissioning Agent (CxA) to support the commissioning of the impacted HVAC systems.
d. All testing shall be performed in accordance with Specification Section 01 91 00 – Commissioning and applicable Division 26 requirements
18. If generator testing is required, please provide the number of generators, generator capacities, associated automatic transfer switches (ATS), and any specific testing requirements.
a. Electrical testing under this project is limited to equipment directly supporting the replaced AHUs, ERUs, and associated temporary HVAC systems. Testing of existing emergency, standby, or backup generators and their associated ATSs or distribution equipment is not required, unless such equipment is new, modified, or directly impacted by the project scope or specifically directed by the Commissioning Agent (CxA) to support commissioning of the affected HVAC systems.
19. Please identify the locations within the facility of the generators and associated ATS equipment included in the scope.
a. Backup and/or standby generators and associated automatic transfer switches (ATS) are not included in the testing scope for this project.
b. Accordingly, no generator or ATS locations within the facility have been identified as part of the project scope. Electrical testing is limited to systems and equipment directly supporting the replaced AHUs, ERUs, and associated temporary HVAC equipment.
c. Existing emergency, standby, or backup generators and their associated ATS equipment located elsewhere within the facility are outside the scope of this project and are not required to be tested, inspected, or commissioned unless such equipment is new, modified, or directly impacted by the scope of work, or unless specifically directed by the Commissioning Agent (CxA) in accordance with the Contract Documents.
20. Please clarify which Fire Alarm System (FAS) devices are included in the scope of testing, relocation, or re-certification.
a. Fire Alarm System (FAS) devices included in the scope of testing, relocation, or re‑certification are limited to those devices directly impacted by the AHU and ERU replacement work.
b. This includes:
i. FAS devices located within mechanical rooms or work areas where AHUs, ERUs, temporary equipment, or associated ductwork are being installed, removed, or modified;
ii. Devices that must be temporarily removed, relocated, or reconnected to accommodate the HVAC work; and
iii. Devices requiring testing or re‑certification as a direct result of construction activities or system integration with the new or temporary HVAC equipment.
c. Fire Alarm System devices outside the immediate areas of work and not directly affected by the AHU or ERU replacement are not included in the scope of testing, relocation, or re‑certification under this project.
d. All FAS work shall be performed in accordance with the Contract Documents, including the applicable Division 28 specifications, and coordinated with the VA‑designated fire alarm service provider. Testing and documentation requirements shall comply with the commissioning and acceptance requirements identified in the specifications.
21. Please confirm whether Fire Alarm System testing is limited to devices directly impacted by the AHU and ERU replacement work or if additional devices beyond the immediate work areas are included.
a. Fire Alarm System (FAS) testing under this project is limited to devices directly impacted by the AHU and ERU replacement work.
b. Testing includes only those FAS devices that are:
i. Located within or immediately adjacent to the construction work areas;
ii. Modified, relocated, disconnected, or reconnected as a result of the
AHU or ERU replacement; or
iii. Otherwise required to be tested or re‑certified due to direct impact from construction activities or system integration with the new or temporary HVAC equipment.
c. Additional Fire Alarm System devices beyond the immediate work areas are not included in the testing scope for this project, unless specifically required to support the work or directed by the Contract Documents.
d. All FAS testing shall be performed in accordance with the Contract Documents, including applicable Division 28 specifications, and coordinated with the VA‑designated fire alarm service provider and commissioning requirements identified in Specification Section 01 91 00.
22. Please identify the general locations of the Fire Alarm System devices included in the testing scope.
a. Fire Alarm System (FAS) devices included in the testing scope are located within or immediately adjacent to the areas impacted by the AHU and ERU replacement work.
b. In general, these locations include:
i. Mechanical rooms housing the AHUs and ERUs being replaced;
ii. Adjacent spaces and ceiling plenums where ductwork modifications or temporary duct connections occur;
iii. Local work areas where FAS devices must be temporarily removed, relocated, reinstalled, or reconnected to accommodate HVAC construction activities.
c. No Fire Alarm System devices located outside the immediate construction work areas have been identified for testing, re‑certification, or relocation under this project.
d. Exact device locations and the extent of required testing will be confirmed through field verification and coordination with the VA‑designated fire alarm service provider and the Commissioning Agent (CxA), in accordance with the Contract Documents and applicable Division 28 specifications.
23. Please confirm the Infection Control Risk Assessment (ICRA) classification applicable to each work zone impacting the electrical scope of work.
ICRA Level III
24. Please clarify responsibility for providing negative air machines, monitoring devices, and infection control consumables associated with electrical work.
Contractor to provide all devices to maintain required ICRA level III as shown on the drawings.
25. Please confirm whether any additional infection control measures beyond those shown in the drawings and specifications are anticipated that would impact the electrical scope.
Contractor to meet all requirements of ICRA Level III as part of all work on the contract. This includes all work areas to ensure veteran safety.
26. Please clarify the expected level of electrical contractor participation during commissioning, including functional testing, integration support, and coordination activities.
Please see specification 01 9100 for specific requirements. Electrical contractor is anticipated to participate in the completion of pre-functional checklists, functional testing of systems as defined by the commissioning plan by the CxA, and participate in issue resolution.
27. Please confirm whether retesting of electrical systems, generators, or fire alarm devices is anticipated as part of commissioning or acceptance.
Please see specification 01 9100 for specific requirements. Contractor is responsible for all retesting costs and functional testing costs.
28. Please clarify the documentation requirements associated with electrical closeout, including testing reports, as-built drawings, and record documentation, beyond what is stated in the specifications.
a. There are no additional electrical closeout documentation requirements beyond those stated in the Contract Documents and Specifications. Electrical closeout shall follow the specifications, including Section 01 91 00 – Commissioning, and applicable Division 26 provisions. The Contractor is responsible for furnishing the required testing documentation and for all retesting as specified.
b. As applicable to the work that is new, modified, reconnected, or otherwise directly affected by the AHU/ERU replacement—the closeout package shall include the documentation already required by the specifications and commissioning plan established by the CxA, such as:
c. Testing/verification documentation for impacted electrical equipment in support of AHU/ERU commissioning, in accordance with the commissioning plan identified in 01 91 00, including any required retesting records.
d. Record documents/as‑built drawings reflecting the final installed conditions of electrical work directly supporting the replaced or temporary HVAC equipment, coordinated with the commissioning deliverables.
e. No facility‑wide electrical documentation (e.g., for distribution equipment not directly impacted by this project) is required unless specifically directed by the CxA to support safe commissioning of the systems in scope.
29. Does Attachment 4 assume a single electrical crew or stacked crews during shutdown, tie-in, and testing phases?
Attachment 4 is the Itemized Cost Breakdown and is a standardized form for recent construction projects in this region. Offerors should refer to the project requirements in the RFP, SOW, Specs, and Drawings to confirm their price accurately reflects the work involved.
30. Are there any restrictions on apprentice ratios or manpower composition during sensitive electrical work or testing periods?
Yes, apprentice restriction to a 1:1 ratio, meaning one apprentice for every one journeyman or master electrician, to ensure proper supervision, particularly for specialized or hazardous tasks.
31. Is electrical manpower sequencing assumed to align directly with AHU shutdown and replacement phasing, or are additional work windows anticipated?
Electrical manpower sequencing assumed to align directly with AHU shutdown and replacement phasing. It is also the contractor’s Means, Methods and responsibility to ensure the project is properly staffed for project execution.
32. Please confirm whether unforeseen infection control measures impacting electrical work are considered contractor responsibility or subject to contract modification. – Please refer to RFO 52.236-2 and RFO 52.236-3, which are incorporated into the RFP.
33. Please clarify how partial completion of electrical work will be validated relative to testing, commissioning, and acceptance requirements.
Electrical testing under this project is limited to equipment directly supporting the replaced AHUs, ERUs, and associated temporary HVAC systems. Partial testing may occur at the direction of the Commissioning Agent (CxA) to support commissioning of the affected HVAC systems. However, equipment acceptance and completion is dependent on final acceptance by the VA.
34. Please confirm whether there is flexibility to rebalance labor categories within the electrical scope should actual field conditions differ from initial assumptions.
Please see the response to RFI- 28. Contractor’s labor mix needs to be able to properly execute the work with applicable qualifications, certifications, and safety training.
35. Spec states HVAC must be tied into FA system, but FA drawings do not show points or devices. Please provide updated FA drawings or point schedule.
Per the Contract Documents, HVAC equipment shall be tied into the Fire Alarm System (FAS). The electrical drawings identify the relevant scope and coordination requirements for these tie‑ins, including the affected AHUs/ERUs and associated power/control interfaces shown on Sheets E‑401, E‑402, E‑403, E‑404, E‑405, and E‑501. Final device locations, point mapping, and sequences will be confirmed through the FA contractor’s shop drawings and the commissioning plan in accordance with Division 28 and Specification Section 01 91 00 – Commissioning.
Updated FA drawings are not required at this time; the FA shop drawings and point list developed by the VA‑designated FA service provider shall govern, limited to devices directly impacted by the AHU/ERU replacement work and associated ductwork modifications.
36. The contract documents include a Lead-Based Paint Removal spec section (02 83 33.13) and drawings HA101/HA102 outlining lead abatement on the 1st floor and penthouse. Please clarify the scope of hazardous material abatement in this project:
Are the highlighted areas on HA101/HA102 the only locations requiring lead paint removal, presumably where equipment or ducts will be disturbed? For instance, HA101 shows a first-floor plan – is that the location of FCU-1/2 or piping where paint will be scraped? We will follow OSHA lead-safe practices regardless but want to confirm if we should include a certified abatement contractor for full removal in those areas or just stabilization.
The only positive LBP results were the white paint on AHUs in rooms 1A147 and 6A104. The rest of the tests were negative:
37. Has an asbestos survey been conducted? None is referenced explicitly, but if any asbestos-containing materials (ACM) (e.g. old pipe insulation or transite panels in mechanical rooms) are present around our work, it would impact our approach.
Please advise if asbestos remediation is required or if the site is clear of ACM in the work zones.
Yes, a total of 33 new samples representing 70 total material samples were taken, none of which was identified to contain asbestos.
38. Demo drawings indicate removal of abandoned ductwork and refrigerant lines, but spec does not confirm scope boundary. Please confirm the exact demo boundary especially for inaccessible ceiling areas.
a. Basement Mechanical room BA101: Scope of demolition is limited to basement mechanical room BA101. Contractor to notify COR of any deficiencies in ductwork exterior to this room, specifically outside air ductwork routed between the exterior louver and the mechanical room.
b. First Floor Mechanical room 1A147: Scope of demolition is limited to first floor mechanical room 1A147.
c. Fourth Floor Mechanical room 4A105: Scope of demolition is limited to fourth floor mechanical room 4A105. Note,
d. Sixth Floor Mechanical room penthouse A6004: Scope of demolition is limited to sixth floor penthouse mechanical room A6004.
39. Specs call for ceiling finish patch-back, but no elevation or material detail shown.
Please provide finish schedule for all affected ceilings.
There is no ceiling in these mechanical spaces, and any patch would be to the structural deck above – no finish schedule for the ceilings are necessary.
40. Can you confirm existing type of FA annunciator panel?
Siemens Desigo CC Management
41. Is new FA annunciator panel required? If so, where?
Fire Alarm System (FAS) devices included in the scope of work includes the testing, relocation, or re‑certification to those devices directly impacted by the AHU and ERU replacement work. These include but are not limited to smoke detectors, supervised relay’s, cabling, and required programing changes within the existing fire alarm system. New panel is not anticipated due to the reuse / replacement of existing detection devices, however, contractor is responsible for ensuring a complete and working system at the completion of the project.
42. For temp units 03A and 03B, the duct is shown penetrating the exterior louver, but there is no direction on how that is to tie-in to the existing ductwork. Is the duct main on the other side of the wall? Are we to run ductwork all the way to the mechanical room?
There is existing outside air ductwork routed from the mechanical room to the louver.
Temporary ductwork will connect to the existing ductwork. See as-built below:
43. Is the contractor able to route ductwork in a manner different than the drawing routing?
Any deviation from the drawings must be generated by the contractor then submitted to be reviewed and approved by the A/E and VA COR.
44. Can temporary ductwork be run using high static flexible ductwork or is it to be routed in metal duct? Please provide a specification for the temporary duct, unless this is at the contractor’s discretion.
No. Rigid ductwork shall be utilized. Any deviation must be reviewed and approved by the A/E and VA COR. Please refer to duct spec for all ductwork: 23 31 00 HVAC DUCTS
45. JCI is listed as the controls system integrator for this project. However, depending on location within the hospital we have seen Hoffman or Trane as the designated integrator. Can you please confirm JCI is to be the designated integrator for this project?
JCI is to be the designated integrator for this project.
46. Is the controls system integrator to be a separate contractor from the controls system installer?
a. Installer and integrator can be separate contractors.
i. Single Source Responsibility of subcontractor: Either the DDC Contractor or the System Integrator shall obtain hardware and software supplied under this Section and delegate the responsibility to a single source controls installation subcontractor. The Integration subcontractor shall be responsible for the complete design, installation, integration, and commissioning of the system. The controls subcontractor shall be in the business of design, installation and service of such building automation control systems similar in size and complexity.
47. Can some units be placed in parallel if they serve different areas, or must we strictly do one phase at a time?
Follow phasing as indicated on drawings, 4 phases, one phase at a time.
48. The RFP notes that existing electrical infrastructure will be utilized for new equipment. We need confirmation that the existing feeders, circuits, and breakers are sufficient for the new AHUs, condensing units, pumps, etc. For example, if a new fan motor has higher horsepower or if a new ACCU requires a larger circuit, will panelboard upgrades or new feeds be required? The electrical demo and new power plans show reuse of circuits, but it’s not explicit if breaker sizes change. Please verify the new equipment electrical loads against existing circuit capacities and indicate any required electrical modifications (wire size, breaker trip, disconnects) beyond simply reconnecting to existing power.
a. The existing electrical infrastructure is intended to be utilized for the new HVAC equipment in accordance with the Contract Documents. Where replacement equipment requires connection to existing electrical systems, new circuit breakers shall be installed to match existing characteristics and type, as required.
b. The electrical drawings identify the required breaker and conductor sizes for the new and replacement HVAC equipment, including any modifications necessary beyond simple reconnection. Refer to the project electrical drawings for equipment loads, breaker sizing, conductor sizing, and disconnect requirements.
49. The plans include a Temporary AHU Power Plan and a temporary panel schedule, implying that power must be provided to the temporary AHUs and exhaust fans during phasing. Please clarify the source and capacity for this temporary power: Are there spare circuits in the existing electrical system to feed the temporary units, or is the intent to use a portable generator or temporary distribution panel? If using existing power, confirm that the added load of temporary DX AHUs and fans (e.g. two 12,000 CFM exhaust fans) won’t trip existing systems or require load shedding. Also, specify if any automatic transfer or backup power is required for these temporary units to protect critical areas in event of normal power loss.
a. Temporary power for the AHUs and exhaust fans shall be provided as shown on the Temporary AHU Power Plan and the temporary panel schedule. The design drawings show the proposed temporary equipment to be used and the existing demand for the temporary equipment; contractors shall utilize the circuits and capacities identified on those drawings. INSTALL NEW CIRCUIT
BREAKERS TO MATCH EXISTING CHARACTERISTICS AND TYPE. DRAWINGS
SHOW BREAKER AND CONDUCTOR SIZE.
b. Source and capacity: Where existing panels/circuits are indicated on the temporary power plan and schedule, those shall be used; no additional temporary distribution panels or portable generators are required unless specifically shown or directed by the Contracting Officer. Loadings shall not exceed the ratings indicated on the drawings and schedules.
c. System impact: The added loads for the temporary DX AHUs and exhaust fans are accounted for in the temporary power plan/schedule. Contractors shall connect and configure per the drawings so as not to exceed indicated capacities and shall coordinate any required outages with VA.
d. Automatic transfer / backup power: No automatic transfer or backup power is required for the temporary units unless specifically indicated on the drawings or in the specifications. Testing/commissioning requirements remain as defined in Specification 01 91 00 – Commissioning and applicable Division 26 provisions.
e. All work shall be performed and documented in accordance with the Contract Documents. Any proposed deviations (e.g., use of portable generation or alternate distribution) shall be submitted for A/E and VA COR review and approval prior to implementation.
50. The RFP and specs indicate that new AHUs will connect to existing chilled water and steam/condensate lines within the mechanical rooms. We seek clarification on the tie-in points and any new appurtenances needed. For chilled water and steam: are there existing isolation valves at each mechanical room entry that we can shut to do our connections? If not, should we install new valves or plan system-wide shutdowns? For condensate drainage from AHU cooling coils or steam humidifiers:
the spec notes we must collect and remove condensate from units, but drawings don’t clearly show where to pipe it. Should we run condensate to the nearest floor drain or hub drain, and are new condensate pumps needed if gravity flow isn’t possible? Please confirm the intended design for these piping connections (valve locations, drain points, etc.), as they are not explicitly detailed.
a. Plan to demo mains back to local main and cap. Provide new valves and appurtenances to new piping. Scoped is limited to the mechanical rooms, but full shutdowns will be necessary to install new valves. Schedule shutdowns with COR as required.
b. Run new condensate piping to nearest floor drain / floor sink / hub drain.
Drains are located adjacent to the existing units.
51. The scope includes “structural modifications” as needed for the new equipment.
We noted Structural drawing S-SK1 provides a sketch for temporary AHU duct support, but we need clarification on permanent support requirements. For example, do the new AHUs, condensing units (ACCU-1 to 4), or pumps require new housekeeping pads, inertia bases, or steel dunnage? If a new rooftop or penthouse unit is heavier than the old, has the structural capacity been verified or should the contractor carry an engineered solution to reinforce beams/slabs? The documents don’t explicitly show any new beams or pad details for the equipment replacements. Please advise if we are expected to design/build any new supports or if existing building structure is confirmed to be adequate for all new loads.
Equipment pads will need to be expanded to accommodate new AHUs. The existing structure has been verified against new equipment loads. No building structural work is anticipated in regards to new permanent air handling units (including exhaust fans).
52. Will the VA’s infection control staff perform routine inspections and air sampling, or does the contractor need to hire an independent ICRA monitor to document compliance? We want to ensure we implement the correct infection control and interim life safety measures at all stages (especially since this is an active hospital).
Contractor to meet all requirements of ICRA Level III as part of all work on the contract. This includes all work areas to ensure veteran safety.
VA engineers or COR will inspect the job site daily. VA’s infection control staff will perform routine inspections weekly since the nature of the work is being done in the mechanical room, penthouse room, roof, and outside patio and not next to inpatient areas.
53. The specifications call for comprehensive Testing, Adjusting, and Balancing (TAB) of HVAC systems. We need to confirm the extent of this work. The project replaces major air-handling equipment but does not otherwise alter terminal devices in the occupied spaces. Are we required to re-balance all air outlets and hydronic terminals throughout the areas served by the new AHUs, or just balance the new equipment to match the design flow rates? For instance, if AHU-2 serves an entire floor, should the TAB agent revisit every room on that floor to verify airflows and adjust VAV boxes, reheat coils, etc.? The spec suggests all systems be balanced in all modes, but we want to clarify if that includes portions of the system not physically modified.
The existing equipment being replaced is to be tested for baseline values. Only new equipment is to be balanced to the design flow rates.
54. We note that normal VA working hours are 7:00 AM to 4:30 PM, Monday through Friday. Please confirm if any work must be performed outside of those hours.
Specifically: will high-noise operations (core drilling, demolition of concrete or ductwork) or system shutdowns (like switching over an AHU or tying into electrical/steam mains) be restricted to evenings or weekends to avoid disrupting hospital operations? Likewise, if any areas served by an AHU cannot be without HVAC during the day, we may need to do the cutover at night when those areas can tolerate an outage (despite temporary units, there may be moments of transition).
Understanding any off-hours or phasing constraints imposed by the medical center (such as “no power shutdowns during clinic hours” or “work in ICU only after 10 PM”) will help us plan labor shifts and communicate with subcontractors.
For any work that impacts on hospital normal operation, contractors will have to coordinate in advance with the project COR/PM for off-hours or weekend work.
55. Please provide contact information for the control systems integrator, as the GC is responsible for getting an integration quote from them.
The control systems integrator is listed below.
Marc Skeen | Hoffman Building Technologies Inc.
Address: 3683 N Peachtree Rd, Chamblee | GA, 30341 Email: Marc.Skeen@hbtech.com Web: www.hbtech.com Mobile: (404) 274-7982 | 24-hour service: (877) 382-9669
NOTE: As with other aspects of this project, there is not a Brand Name requirement.
This information is being provided to assist the GC with compatibility of their work with existing systems and/or equipment.
56. Who is responsible for the network connection between the BACnet IP AHU
Controllers and the nearest network switch? If the controls contractor is responsible for this, please provide the location of the network switch nearest to each AHU.
Controls contractor is responsible for the network connection between the BACnet IP AHU Controllers. Location is in the boiler plant.
57. Are we able to submit previously submitted PPQs?
Yes, but offerors should review the “Proposal Preparation and Evaluation Information” page in the RFP to confirm the appropriate information is included.
58. If there is another government shutdown, what impact, if any, will there be on the Atlanta VA, its personnel, and the bid due date for this opportunity?
Unknown.
59. Will the VA extend the bid due date by two weeks after all RFI responses are provided, allowing time to review RFI answers and provide the best price possible?
If practicable with procurement lead times, the VA will attempt to allow this.
60. Will the VA clarify if there is any asbestos in the areas proposed to be under construction?
The only positive LBP results were the white paint on AHUs in rooms 1A147 and 6A104.
mailto:Marc.Skeen@hbtech.com https://gcc02.safelinks.protection.outlook.com/?url=http%3A%2F%2Fwww.hbtech.com%2F&data=05%7C02%7C%7Cc53c1f77d8eb42fe0fc108dd54de4207%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C638760035763148479%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=UhY%2FkxrMhvKLpaaYXiG8kpIC%2F6ygULmoYVv8bNva0Eg%3D&reserved=0
61. When was the most recent asbestos survey completed?
Testing was performed on September 25, 2024.
62. Will the VA provide the most recent asbestos abatement survey for the affected areas?
Please see the report from September 25, 2024 for the area of work.
63. The specifications call for a dedicated Superintendent, SSHO, and Quality Control Manager. Having all three dedicated to this project for the full period of performance will generate an excessive cost given the scope of work. Will the VA amend the requirements to allow any one person to fill multiple roles?
Yes, this person must be competent and possess a high level of experience to satisfy VA requirements.
64. Will the VA allow the Prime Contractor to delegate an OSHA 30 superintendent and associated responsibilities to a member of the subcontractor's team?
No.
65. Will the Prime Contractor and its subcontractors have access to any on-site restroom facilities?
No. Contractors will have to provide and use their own portable rental restroom.
66. Who is the current fire alarm contractor that services the Atlanta VA?
Siemens industry inc Candace Sandusky 770 547-4851 Candace.Sandusky@siemens.com
Or
Joe McNerney, SET SIEMENS Industry Inc.
Smart Infrastructure 770-630-1247 (Mobile) Preferred 770-935-2000 (Office) joseph.mcnerney@siemens.com
67. Who is the current fire sprinkler contractor that services the Atlanta VA?
No one in particular.
68. Is the contractor responsible for the sprinkler removal and replacement in all mechanical rooms?
Contractor is responsible for all intermediate fire protection needs and means and methods to complete the work. That may involve up turning sprinkler heads, removal and reinstallation of sprinkler heads, and other activities as needed to remove and install systems involved in the project.
69. The VA states that the temporary units must be “monitored and maintained,” but it is unclear if TAB must be performed on the temporary systems. Is the contractor required to TAB the temporary AHUs?
The contractor is required to TAB the temporary AHUs. Balance temporary AHUs to match existing AHU capacities.
70. Will the VA please confirm that all walls listed on the finish drawings require paint? If yes, will the VA provide the existing paint color or color codes for the walls?
Not all walls require paint, architectural finishes for this project are all patch and repair – contractor should color match existing.
71. Will the VA clarify the drywall requirements for this project? Is drywall work limited to patch and repair, or are there specific areas that require full or more extensive gypsum board installation per the specifications?
Drywall work is limited to patch and repair, no new wall or ceiling assemblies are part of this project.
72. Will the VA clarify the requirements for wall-hung items for this project? Specifically, are there designated locations, backing requirements, or mounting details the contractor must follow?
None are defined in the design, contractor to submit any backing and mounting details as part of temporary duct supports.
73. Will the VA provide Specification Section 09 67 23? Epoxy is called out as the floor finish type on Page AE101 of Attachment 8 – Drawings, but there is no correlating specification section in Attachment 7 – Specifications.
No floor work, floor scope includes patch and repair as needed for the existing flooring. Updated sheets can be provided upon request.
74. Will the VA update Specification Section 09 06 00 – Schedule for Finishes to include floor finishes for this project?
No floor work, floor scope includes patch and repair as needed for the existing flooring. Updated sheets can be provided upon request.
75. Will the VA please confirm which epoxy flooring system is required for this project – Urethane Mortar, Aggregate/Flake/Quartz Broadcast, or Urethane Mortar with an anti-slip aggregate?
Existing flooring system is sufficient.
76. Page HA101 from Attachment 8 - Drawings, Abatement Keyed Note 1 States: Abate white lead containing paint on metal exterior of AHUs #2 and #5 in Mechanical Room 1A147. Is it necessary for the contractor to perform lead abatement on these air handlers if they are going to be removed from the space?
Intent is prior to demolition of the equipment all Lead is abatement to allow for safe demolition activities and tracking of the hazardous materials.
77. If lead-based paint is to be removed from existing air handlers that are not to be removed, will the VA provide all warning signs, labels, unit specific stickers, etc. for the units?
No. Contractors will have to be responsible for providing all warning signs, labels, unit specific stickers, etc. for the units.
78. Please confirm whether any lead-based paint is present on the existing ductwork that is to be removed. Is lead-based paint limited to the Air Handling Units, or should the ductwork also be considered for abatement?
Existing ductwork to remain was not tested for Lead, only the air handling units.
Contractor to test prior to demolition.
79. Are vibration isolation bases required for the five air handling units and two exhaust fans?
Yes, vibration isolation is required for the new AHUs and the new exhaust fans.
80. Please confirm the maximum allowable width for new modular equipment to ensure it can be transported through all required doors, hallways, and access pathways from the staging area to the installation location.
Contractors should have obtained this information during the open site walk-through.
81. Will the VA allow any doors, frames, and hardware to be temporarily removed for unit installation?
Yes, and they must be reinstalled immediately after the units are transferred into the mechanical room. However, if there is any damage, the contractors will be responsible for the repair or providing new ones.
82. Sheet Note 4 found on MD103 and MD104 of Attachment 8 – Drawings, states:
Contractor to do full test and balance survey of entire service space from air handling unit to all terminal units and final registers prior to demolition […]. Based on this note, will the VA provide full set of mechanical drawings for the hospital or equipment counts for the areas served by these units? A total count is required to provide the best price possible.
Perform TAB at the AHU. The existing equipment being replaced is to be tested for baseline values. Only new equipment is to be balanced to the design flow rates.
83. Will the entire service space from air handling unit to all terminal units need to be re-tested and balanced (re-TAB) after the air handling units are replaced?
No, AHUs and exhaust fans being replaced will be balanced to match design.
Terminal units and space air devices are outside of the scope of this project.
84. While the temporary units are installed, does the contractor need to do any pressure / air change verification testing for the entire service space from air handing unit to all terminal units?
Contractor to verify the air flow and pressure at the point of connection between the temporary ductwork and existing ductwork. The service space is outside of the scoped of this project.
85. During construction, noise and vibrations will occur within the mechanical rooms.
Are there any adjacent spaces that will require quiet hours or special noise/vibration restrictions during normal working hours? If so, what are the quiet hours for those spaces?
Surrounding the construction job site are non-patient care areas, mostly offices, but excessive noise will impact office meetings and team collaboration, such as core drilling etc. So, the GC needs to coordinate with the COR in advance for after-hours or weekend work. Otherwise, work must be done during normal working hours.
86. Please confirm manufacturer controls mounted at the factory are acceptable.
If the provided controls meet the requirements of the DIV 23 specifications and can perform the sequences as stated on the construction drawings we take no issue.
However, pre-package and pre-programed controls that do not meet the requirements of the specifications, or can perform the required sequence of operation are not acceptable.
87. The existing air handing units have Trane controls. Please confirm the option of the new AHUs to be tied into existing Trane system at the facility for a competitive bid is acceptable.
New controls are to be BACnet and integrated into the head end Climatech control system. Please see General Notes on controls drawings.
88. Has it been verified that there is adequate electrical available in the building now to run the temporary units? They will be DX units (meaning it will require more power than an AHU.)
a. The design drawings and temporary panel schedules indicate that adequate electrical capacity is available to operate the temporary DX units, which have higher electrical demand than the permanent AHUs.
b. The Contractor shall review the panel schedules for the temporary panels to verify that the actual temporary DX units provided are at or below the electrical demand noted on the design drawings. Temporary equipment shall be selected, installed, and operated in accordance with the breaker sizes, conductor sizes, and panel capacities shown in the Contract Documents.
c. If the electrical demand of the proposed temporary DX equipment exceeds the demand shown on the design drawings, the Contractor shall notify the Architect/Engineer (A/E) and the VA Contracting Officer’s Representative (COR) for review and direction prior to installation. No installation of equipment exceeding the design demand shall proceed without written approval.
89. Is there enough power to run more than one temporary unit at a time, in each of the dedicated areas of temporary units?
Yes. The electrical load calculations at the time of design indicate there is sufficient capacity to operate more than one temporary unit at a time within each dedicated temporary equipment area as shown in the design drawings.
90. How many hours of shut down time will the contractor have to make the final connections the temporary unit for the existing duct and turn it on as temporary?
This will have to be done after hours or on weekends to avoid disruption. VA expects it to be done within 8 hours.
91. Materials will be stored offsite in a secure warehouse with Insurance. Please confirm we can bill on and be paid for stored materials.
It cannot be guaranteed, but the VA may accommodate payment for stored materials only if the conditions under RFO 52.232-5(b)(2) and VAAR 852.232-70(d) are met. If approved by the CO, 10% retainage would likely be held IAW 52.232-5(e) until work related to those materials is completed.
92. What if any, will be the retainage amount on this project?
The CO may hold 10% retainage IAW 52.232-5(e) if necessary.
93. SOW page 3 states that the contractor needs to reinsulate all the duct and piping at the AHUs. Please confirm if the contractor will be reinsulating only disturbed, reworked, new work and tie in areas. Please clarify the extent of the re- insulation. Is it everything in the rooms, even pipe and duct that is not touched?
The contractor is required to document any existing deficiencies. The scope of work includes reinsulating all reworked items and replacing insulation on all main ductwork within the mechanical room associated with the AHU replacement.
94. Is there a service elevator that contractors will be able to use?
Yes.
95. The work schedule in the specs is 7:00- 4:30 M-F. Will contractors be able to work additional hours to make ties ins or set equipment if it makes sense to the owner?
Yes, and must be coordinated with the COR in advance notice and approval.
96. Per the sheet AE101 needing epoxy in four mechanical rooms. I could not find demo for these areas. What type of flooring are in these rooms, currently to be removed?
Existing floor should be maintained. Patch and paint as needed.
97. According to the Specs and notes on the drawings, lead and asbestos surveys are supposed to be included. Please provide qtys of lead and asbestos abatement that is required.
Please see Attachments to this amendment for the asbestos testing report dated September 25,2024.
98. Please confirm how long the overall time to obtain a badge should take as described in spec section 01 00 00 form the time the initial paperwork is submitted until the time the badge is in the employees hands.
There are many factors that can affect the total number of days it takes to issue a VA ID badge. It could take 3 weeks, 4 weeks, 5 weeks, 6 weeks, or more. It depends on the completeness of the submitted paperwork and VA personnel that are available to process the paperwork. It is safe to assume that if everything went well, the VA ID badge could be issued within a month. The contractor onboarding flow chart and timeline for security are listed below.
99. Please confirm location of Contractors Job Trailer, Dumpster, and Lay down area on a campus map.
Next to SA3 Office Trailer, see below campus map.
100. Please confirm if FEC as shown on sheets AS102 through AS112 are new or existing.
Existing.
101. Sheet AS101 show several ICRA types with temporary walls or Ante Rooms. These temporary walls and ante rooms are not shown on the corresponding pages of sheets AS102-AS112. Please confirm that Sticky Mats as shown on sheet AS102-AS112 will be the only items are required. If additional work is required for ICRA please indicate ICRA type and barriers required at each location
Scope of work areas are to follow class III, we can provide revised ICRA plans upon request.
102. Please confirm if any phasing is required or if all areas can be completed simultaneously.
Please follow the phasing plan from drawings. ALL AREAS CANNOT be completed simultaneously.
103. Please provide dimensions of all pads. Plansheet G-001 general note 1 states "Do not Scale Drawings"
a. Contractor to field verify existing equipment pad. Existing pads will require patching to accommodate new equipment. Dimensions below are approximate and may not accurately reflect as built conditions.
b. Existing pad dimensions (Approximate):
i. Basement BA101 equipment pad – 12’6” x 26’2”
ii. First floor mechanical room 1A147 –
1. 1A-AH05 equipment pad 12’9” x 33’6”
2. 1A-AH02 equipment pad 9’7” x 20’
iii. Fourth floor mechanical room 4A105 –
1. 4A-AH17 equipment pad 11’8” x 30’3”
2. 4A-AH19 equipment pad 12’6” x 26’9”
3. 4A-AH26 (energy recovery / exhaust unit) equipment pad 11’4” x 15’9”
iv. Sixth floor mechanical room penthouse A6002 – 6A-AH28 (energy recovery / exhaust unit) 10’3” x 13’
104. Sheet HA001 detail E4, keynote 3 indicates a containment barrier is to be construction at all doors on the interior perimeter of the regulated area. The detail shows the containment barrier in the middle of the room. Please confirm if an additional barrier is to be construction by the door or if Containment Barriers are to be constructed where they are shown on the drawing
Room 1A147 will have a containment barrier built around the machines in the interior of the room.