This is an electrical testing and maintenance report for the CAVHCS Veteran's Hospital in Montgomery, Alabama, completed by Suncoast Industrial Testing Services, Inc. in August 2022, representing the tri-annual (three-year interval) inspection cycle required by NFPA 70B standards since 2004.

The report documents comprehensive testing of the facility's electrical infrastructure, including ten high-voltage breakers at 15kV (nine passed; one failed to charge), fifty low-voltage breakers (twelve defective requiring replacement or repair), ten transformers (all showing acceptable dissolved gas analysis but nine with elevated moisture content approaching or exceeding the 35 mg/kg service limit), four generators (two passed load bank testing), and 205 panel checks with grounding resistance measurements. Key findings identify critical maintenance needs: immediate servicing of the main switchgear transformer (TX-1) due to 36 mg/kg moisture content exceeding acceptable limits; replacement of 35 incandescent indicating lights with LED alternatives in the 15kV substation; repair or replacement of 12 defective circuit breakers; installation of air conditioning in the substation to address moisture and dust ingress; investigation of a capacitor bank disconnected for an extended period; and resolution of multiple ground resistance points exceeding the NEC 25-ohm requirement. The automatic transfer scheme was successfully tested and verified operational. The report provides detailed test results, relay settings, and specific recommendations prioritized by urgency and scope.

View the file

Other files

File Type Posted
36C24726Q0469 0005.docx DOCX document
Appendix E - Drawings.pdf PDF
Appendix E - Drawings 2.pdf PDF
36C24726Q0469 0004.docx DOCX document
36C24726Q0469 0003.docx DOCX document
36C24726Q0469 0002.docx DOCX document
Previious Tuskegee Electric Testing Report August 2022.pdf PDF
36C24726Q0469 0001.docx DOCX document
36C24726Q0469_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ELECTRICAL

TESTING

AND

MAINTENANCE

FOR

CAVHCS

VETERAN’S HOSPITAL

MONTGOMERY, ALABAMA

BY

SUNCOAST INDUSTRIAL TESTING SERVICES, INC.

ORANGE PARK, FLORIDA

AUGUST 2022

TABLE OF CONTENTS

I. INTRODUCTION

II. EXECUTIVE SUMMARY

A. SCOPE OF WORK

B. ANALYSIS

1. HIGH VOLTAGE BREAKERS

2. LOW VOLTAGE BREAKERS

3. TRANSFORMERS

4. GENERATORS

5. INFRARED THERMAL SCANS

6. PANEL CHECKS

7. GROUNDING

C. RECOMMENDATIONS

III. LAYOUT & TABLES

III. TEST REPORTS

A. HIGH VOLTAGE BREAKERS (10)

B. LOW VOLTAGE BREAKERS (50)

C. TRANSFORMERS (10)

D. GENERATORS (4)

E. INFRARED THERMAL SCANS (3)

F. PANEL CHECKS (205)

G. GROUNDING (2)

I. INTRODUCTION

This Electrical Testing & Maintenance Report is for the CAVHCS Veteran’s

Hospital in Montgomery, Alabama. Suncoast has performed this work on an every three year basis since 2004. Therefore, the last report was for 2019. Performing this work on an every three year basis satisfies the requirements of NFPA 70B – Recommended

Practice for Electrical Equipment Maintenance.

The report contains the following sections:

- Executive Summary defining the scope of work, provides analysis and gives recommendations,

- High Voltage Breakers with relay settings, test reports and a review of events for 2022,

- Low Voltage Breakers with test reports,

- Transformers with oil sample test reports,

- Generators with load bank testing reports and

- Infrared Thermal Scans with reports for “Hot” spots.

- Panel checks with inspection reports

- Grounding tests

II. EXECUTIVE SUMMARY

A. SCOPE OF WORK

The Scope of Work performed includes:

1. High Voltage Breakers -

a. The relays for the high voltage breakers are all SEL brand. They are hard wired into the 15KV switchgear. The servicing for these relays involves connecting a laptop computer to their front port and downloading their programming of their settings. These relays also have an “HMI” feature to check their on-line status. In addition, a

Sequence of Event report (SER) is retrieved showing the events that the relay has seen in a chronological order.

b. After cleaning and lubrication, the high voltage breakers were tested with an AC VLF tester to verify the vacuum bottles condition. A

“Ductor” tester was used to measure the contact resistance of the vacuum bottles. Finally, a high voltage megger was used to verify the insulation quality of the breakers.

2. Low Voltage Breakers –

a. After cleaning and lubrication, the low voltage breakers were tested with a “Ductor” tester to measure the contact resistance. A low voltage megger was used to verify the insulation quality of the breakers.

b. For breaker 400A and larger, a primary current tester was used to verify the operation of the breakers’ trip units. Long-time, Short-time, Instantaneous and Ground-fault functions were tested has available on the trip units.

3. Transformers –

a. The transformers’ oil samples were sent to a laboratory for a

Dissolved Gas Analysis (DGA) and to measure moisture.

4. Generators –

a. The two (2) generators that have one (1) hour monthly tests at levels above 30% were not load banked. These generators carried the entire hospital load during the 6 hour testing outage on June 29, 2019.

b. The other two (2) generators were resistive load bank tested at 25% for 1 hour, 50% for 1 hour and 75% for 2 hours. The % load was determined by the nameplate KW rating.

5. Infrared Thermal Scanning –

a. Electrical panels were scanned looking for “Hot” spots. A “Hot” spot is considered to be a measurement of 10 degree C above ambient.

b. An IR Panel Inventory for all of the scanned equipment id provided.

6. Panel Checks –

a. The distribution panels were checked for problems.

7. Grounding Tests –

a. Building ground system was measured for resistance.

B. ANALYSIS

1. HIGH VOLTAGE BREAKERS -

a. Attached is Layout 1 which shows which breaker is in which compartment in the 15KV switchgear. This switchgear was installed in

2008. The Primary Main breaker MPF-1 is fed by a utility circuit and is normally closed. The Tie 52T breaker is normally open. The

Alternate Main breaker MPF-2 is fed by a utility circuit and is normally closed. Therefore, the facility’s load is divided between the Main breaker MPF-1 and Main breaker MPF-2. The switchgear has an automatic transfer scheme whereby upon a loss of voltage on either incoming circuit will cause its main breaker to open after 5 seconds and then close the Tie 52T breaker. This scheme was tested on August 21, 2022 and the successful test is outlined on the bottom of Layout 1. The

Auto Transfer selection switch was found in the Auto position. It was moved to the Manual position for testing. Then it was returned to the

Auto position after testing.

b. All of the relays in the 15KV switchgear are SEL type. Table 1 provides the settings for these relays. These relays not only serve as protection devices, but also as control and monitoring devices. The automatic transfer scheme is controlled by the program in the relays for the main breakers. The relays also store the events seen by the relays.

All relays showed an “OK” status with no warning or failure noted.

The three (3) feeder relays saw an overcurrent event for 1 cycle on

August 1, 2022. This event was probably caused by an inrush when the utility power was interrupted. There were two (2) events on MPF-1 –

August 1st and 2nd of 2022. On August 1st, MPF-1 opened and reclosed 75 minutes later, returning the system to Normal configuration. On August 2nd, MPF-1 opened and reclosed 1 minute later, returning the system to Normal configuration. Multiple voltage sags below 90% nominal are routinely experienced. However, these voltage sags only last a few seconds and are probably not even noticed.

The programs of all of the relays were downloaded and are provided on the flash drive with electronic copy of this report.

c. The high voltage breakers were cleaned and lubricated. Then they were tested with an AC VLF tester and high voltage megger. They were also ductored to verify contact resistance. All breakers passed testing, except PF2-1 breaker, which failed to charge. It was labeled as “Failed” and placed in the empty compartment PF1-4. The spare breaker in compartment PF1-3 was placed in compartment PF2-1. This failed breaker should be repaired. There is another spare breaker in compartment PF2-3.

d. There is a capacitor bank connected to the PF2-4 breaker. The breaker was found in the open position. The 2019 and 2016 reports showed this breaker open. It appears that the capacitor bank has been out of service for a while. CAVHCS should see if the utility is charging a low Power

Factor penalty. If a penalty is being charged, consideration should be given to re-energizing the capacitor bank. Before it is re-energized, the capacitor bank would need to be thoroughly cleaned and tested.

e. Many of the indicating lights on the doors of the switchgear were burnt out. The doors had to be opened to determine the position of the breakers. LED type lights are available to replace this older style incandescent type. There are 35 total light to be replaced having different colors.

f. The 15KV substation is ventilated by an exhaust fan. This fan brings moisture and dust into the substation. If an air-conditioner were installed in the substation, this problem would be resolved. The structure would be to be insulated to avoid sweating on the exterior walls.

2. LOW VOLTAGE BREAKERS –

a. After the low voltage breakers were cleaned and lubricated, they were tested with a “Ductor” tester to measure the contact resistance.

A low voltage megger was used to verify the insulation quality of the breakers.

b. For breaker 400A and larger, a primary current tester was used to verify the operation of the breakers’ trip units. Long-time, Short-time, Instantaneous and Ground-fault functions were tested has available on the trip units.

c. The results for the testing of these breakers are given on the enclosed test reports.

d. Many breakers (12) failed testing. Table 2 lists of the defective breakers giving the frame & trip ratings.

• TS GA-130 (800/ 100): has a defective, obsolete trip unit

• M1-4 (Spare) (800/ 800): has broken control contact; used a spare parts

• Main 2 (1600/ 1600) in Room G-101A: defective breaker

• P4-4 (800/ 800): defective breaker

• Tie (1600/ 1600): defective trip unit, instantaneous function

• S1-S2 (400/ 400): defective breaker

• Panel AP (1600/ 1600): defective breaker

• TS-Q (P4Q) (800/ 800): defective breaker

• P4-1N (800/ 800): defective breaker

• M2 – 8 (800/800): defective indicator

• Main 2 (2000/ 2000) in Room G-151A: defective breaker

• M1 – 7 (800/800): defective return spring

3. TRANSFORMERS –

a. The 10 transformers’ oil samples were sent to a laboratory for a

Dissolved Gas Analysis (DGA) and to measure moisture.

b. Table 3 lists the results of the DGA and moisture tests. The Test

Reports are also enclosed.

c. The DGA has established limits to indicate the status of the oil.

“Status 1” indicates normal gas levels and no indication of gassing.

The transformer is ready for normal operation. Routine DGA sampling is recommended within 1 year.

“Status 2” indicates elevated gas levels and/ or possible gassing.

Increase surveillance and re-sampling within 3 months is recommended.

d. All 10 transformers as listed on Table 3 are shown as DGA

“Status 1” - ready for normal operation.

e. The Main Switchgear transformer TX-1 shows a high moisture content of 36 mg/kg. The Lab states that moisture above 35 mg/kg exceeds the limit for in-service oil. Immediate servicing is recommended for this transformer. The other 9 transformers also have moisture content at 30 mg/kg or above. All transformers should be tested for moisture content within the next year.

4. GENERATOR LOAD BANK TESTING –

a. The two (2) generators that have one (1) hour monthly tests at levels above 30% were not load banked. These generators carried the entire hospital load during the 6 hour testing outage on June

29, 2019.

b. The other two (2) generators were resistive load bank tested at 25% for 1 hour, 50% for 1 hour and 75% for 2 hours. The % load was determined by the nameplate KW rating.

c. Enclosed are test reports for the generator load bank testing. All generators passed their load bank testing.

5. INFRARED THERMAL SCANS –

a. Electrical panels were scanned looking for “Hot” spots. A “Hot” spot is considered to be a measurement of 10 degree C above ambient.

b. Enclosed is an IR Panel Inventory of all of the scanned equipment.

c. There were three (3) “Hot” spots found: Panel C21BD-2B, Panel

C2GD-2 and Panel L1K. Individual IR Thermal reports show the

“Hot” areas.

6. PANEL CHECKS -

a. The distribution panels were inspected for problems.

b. The attached individual Panel Check reports details problem areas.

7. GROUND RESISTANCE CHECKS -

a. The Ground Resistance reports list the ground resistances at various points in each building and transformers.

b. There are many over the NEC requirement of 25 ohms or less.

C. RECOMMENDATIONS

1. Main 15KV Substation

a. It is recommended that the Automatic Transfer Scheme switch be kept in the AUTO position except which performing switching on the primary system.

b. It is recommended that the Capacitor Bank be maintained and returned to service if required. The utility billing should be reviewed to see if excess KVAR usage is being charged.

c. It is recommended that the switchgear indicating lights be replaced with LED type bulbs. The existing bulbs are incandescent type 48MB. There are 35 bulbs to be replaced – 15 Red, 12 Green, 5 White, 2 Amber and 1 Blue.

d. It is recommended that air conditioning be installed in the 15KV substation. This would control the moisture and dust problem. The structure walls and ceiling would need to be insulated.

e. The failed Breaker PF-2-1 should be repaired. It is now in

Compt. PF-1-3.

2. Low Voltage Breakers

a. It is recommended that the 12 defective breakers be replaced or repaired. Table 2 lists the information for these breakers.

b. There are vendors that can supply re-condition breakers.

3. Transformers

a. It is recommended that the Main Switchgear Transformer TX-1 be serviced immediately to lower its moisture content. Its moisture was measured at 36 mg/kg. The Lab states that the in-service moisture limit is 35 mg.kg. The probability of failure is increased with this condition.

b. As Table 3 shows, the other 9 transformers on site have high moisture content approaching the 35 mg/kg limit. It is recommended that all 10 transformers have their moisture content tested within the next 12 months.

4. Infrared Thermal Scans

a. It is recommended that the three (3) “Hot spots” areas be checked, and issues resolved

5. Panel Checks

a. It is recommended that the issues identified on the Panel Check reports be resolved.

6. Ground Resistance Checks

a. It is recommended that the areas over 25 ohms resistance be checked, and issues resolved.

Submitted by: Daniel L. Wehby, P.E.

III. LAYOUTS & TABLES

A. LAYOUT 1 – Main 15KV Switchgear

B. TABLE 1 – Main 15KV Relay Settings

C. TABLE 2 – Low Voltage Defective Breakers

D. TABLE 3 – Transformer Oil Testing Results

IV. TEST REPORTS

A. HIGH VOLTAGE BREAKERS (10)

B. LOW VOLTAGE BREAKERS (50)

C. TRANSFORMERS (10)

D. GENERATORS (4)

E. INFRARED THERMAL SCANS (3)

F. PANEL CHECKS (205)

G. GROUNDING TESTS (2)

8/22/2022

VA MONTGOMERY 15KV SWITCHGEAR

1 2 3 4 5 6 7

A

PF1-3 PF1-4 PT's CONTROL PT's PF2-4 PF2-3

B

PF1-2 PF1-1 MPF-1 52T MPF-2 PF2-1 PF2-2

TESTING PROCEDURE FOR AUTOMATIC TRANSFER SYSTEM

A. NORMAL CONFIGURATION

1. MPF-1 & MPF-2 = NORMALLY CLOSED; 52T = NORMALLY OPEN

2. AUTOMATIC TRANSFER SYSTEM SWITCH = AUTO

B. MPF-1 - LOSS-OF-VOLTAGE

1. PULL PT FUSES AHEAD OF MPF-1; AFTER 5 SECONDS - MPF-1 OPENS

2. WHEN MPF-1 OPENS, AFTER 2 SECONDS - 52T CLOSES.

3. REPLACE PT FUSES AHEAD OF MPF-1; AFTER 10 MINUTES - 52T OPENS.

4. WHEN 52T OPENS, AFTER 2 SECONDS - MPF-1 CLOSES.

5. SYSTEM BACK TO NORMAL CONFIGURATION.

C. MPF-2 - LOSS-OF-VOLTAGE

1. PULL PT FUSES AHEAD OF MPF-2; AFTER 5 SECONDS - MPF-2 OPENS

2. WHEN MPF-2 OPENS, AFTER 2 SECONDS - 52T CLOSES.

3. REPLACE PT FUSES AHEAD OF MPF-2; AFTER 10 MINUTES - 52T OPENS.

4. WHEN 52T OPENS, AFTER 2 SECONDS - MPF-2 CLOSES.

5. SYSTEM BACK TO NORMAL CONFIGURATION.

LAYOUT 1

22-Aug-22

VA MONTGOMERY, AL

MAIN SUBSTATION RELAYS - CURRENT SETTINGS

BREAKER CT (P) CT (N) 50P1P 51P1P 51P1C 51P1TD 50N1P 51G/N1P 51G/N1C 51G/N1TD

MPF-1 80 80 N 5.7 (456A) U2 0.98 N 1 (80A) U3 1.9

MPF-2 80 80 N 5.7 (456A) U2 0.98 N 1 (80A) U3 1.9

PF1-1 40 10 61 (2440A) 7.6 (304A) U3 0.9 10 (100A) 4 (40A) U4 0.5

PF1-2 40 10 61 (2440A) 7.6 (304A) U3 0.9 10 (100A) 4 (40A) U4 0.5

PF1-3 40 10 40 (1600A) 3 (120A) U4 1.25 10 (100A) 1.5 (15A) U4 1.5

PF1-4 40 10 40 (1600A) 3 (120A) U4 1.25 10 (100A) 1.5 (15A) U4 1.5

PF2-1 40 10 61 (2440A) 7.6 (304A) U3 0.9 10 (100A) 4 (40A) U4 0.5

PF2-2 40 10 61 (2440A) 7.6 (304A) U3 0.9 10 (100A) 4 (40A) U4 0.5

PF2-3 40 10 40 (1600A) 3 (120A) U4 1.25 10 (100A) 1.5 (15A) U4 1.5

PF2-4 (CAP) 40 10 40 (1600A) 3 (120A) U4 1.25 10 (100A) 1.5 (15A) U4 1.5

MAIN SUBSTATION RELAYS - VOLTAGE SETTINGS

BREAKER PT 27PP2P 27PP2D 59PP 59P1D 25VLO 25VHI

MPF-1 104

DELTA

(10KV)

300 cyc 108

(11.2KV)

36,000 cyc

(10.8KV)

(13.5KV)

MPF-2 104

DELTA

(10KV)

300 cyc 108

(11.2KV)

36,000 cyc

(10.8KV)

(13.5KV)

NOTES: 1. MPF-1 & MPF-2 RELAYS ARE SEL-351-6, FEEDER RELAYS ARE SEL-551C.

2. MPF-1 & MPF-2 SYNC CHECK - 25SF = 0.042, 25ANG1 = 25, 25ANG2 = 40, TCLOSD = 3.

3. MPF-1 & MPF-2 UNDERVOLTAGE TRIP TIME DELAY = 5 SECONDS (300 CYCLES).

4. TIE CLOSURE TIME DELAY = 2 SECONDS (120 CYCLES).

5. MPF-1 & MPF-2 RETURN TO NORMAL TIME DELAY = 10 MINUTES (36,000 CYCLES).

6. ALL RELAYS' FRONT PORT = 19.2K BAUD RATE.

7. 27PP2D = SV1PU; 59P1D = SV3PU.

8. ROTATION = ABC.

TABLE 1

SUNCOAST INDUSTRIAL TESTING SERVICES, INC. 22-Aug-22

VA MONTGOMERY, AL LOW VOLTAGE DEFECTIVE BREAKERS

SEQ. PANEL CIRCUIT LOCATION MANUF./ TYPE FRAME TRIP DEFECT RECOMMENDATION

TS GA-130 TS GA-130 RM G-153A WEST. /

AMPTECTOR

800 100 ST FUNCTION REPLACE BREAKER

M1-4 SPARE RM G-151A SQ. D /

RMS500

800 800 BROKE CONTROL

CONTACT

REPLACE BREAKER

MAIN 2 MAIN RM G-101A WEST. / SOLID

STATE

1600 1600 WOULD NOT TRIP UPGRADE TRIP UNIT

P4 #4 RM G-101A WEST. /

THERMAL M

800 800 WOULD NOT TRIP REPLACE BREAKER

TIE RM G-101A WEST. / SOLID

STATE

1600 1600 LOW INST TRIP UPGRADE TRIP UNIT

S1-S2 RM G-101A

WEST./

THERMAL MA 400 400 WOULD NOT TRIP REPLACE BREAKER

AP RM G-101A WEST. / SOLID

STATE

1600 1600 PHASE C - HIGH

RESIST. & LT TRIP

UPGRADE TRIP UNIT

TS-Q P4Q RM G-101A WEST./

THERMAL M

800 800 CONTACT RESIST.

HIGH

REPLACE BREAKER

P4 1N RM G-101A WEST./

THERMAL M

800 800 WOULD NOT TRIP REPLACE BREAKER

M2 #8 RM G-151A WEST. /

THERMAL M

800 800 INDICATOR BAD REPAIR BREAKER

MAIN 2 MAIN RM G-151A WEST. / SOLID

STATE

2000 2000 LT FAIL UPGRADE TRIP UNIT

M1 #7 RM G-151A WEST. /

THERMAL M

800 800 RETURN SPRING

FAIL

REPAIR BREAKER

TABLE 2

22-Aug-22

VA MONTGOMERY, AL

TRANSFORMER OIL SAMPLES

SEQ. LOCATION TRANSF. # S/N MOIST. STATUS 1 STATUS 2 RECOMMENDATIONS

1 MAIN BLD TX-2 979002664 33 X NORMAL OP./ RESAMPLE 1 YR

2 MAIN SWGR TX-1 979002662 36 X HIGH MOIST. IMMEDIATE SERVICING

3 B13 T-3 0850013240 31 X NORMAL OP./ RESAMPLE 1 YR

4 B11 T-4 0950001705 31 X NORMAL OP./ RESAMPLE 1 YR

6 B8 TX-9 930738A1 31 X NORMAL OP./ RESAMPLE 1 YR

10 B14 T-5 0950001706 31 X NORMAL OP./ RESAMPLE 1 YR

23 MAIN BLD T-7 0950001707 30 X NORMAL OP./ RESAMPLE 1 YR

32 MAIN BLD T-6 0950001708 31 X NORMAL OP./ RESAMPLE 1 YR

35 B13 T-CW 0850012691 31 X NORMAL OP./ RESAMPLE 1 YR

36 MAIN SWGR T-8 0850007742 31 X NORMAL OP./ RESAMPLE 1 YR

NOTES: 1. MOISTURE - MAX 35 = ACCEPTABLE.

2. WHEN MOISTURE IS OVER 35, IMMEDIATE SERVICING IS RECOMMENDED.

3. STATUS 1 = NORMAL GAS LEVELS. CONTINUE NORMAL OPERATION.

4. STATUS 2 = ELEVATED GAS LEVELS AND/ OR POSSIBLE GASSING.

5. STATUS 2 = RECOMMEND INCREASE SURVEILLANCE AND RE-SAMPLE WITHIN 3 MONTHS.

TABLE 3

Orange Park, Florida 32073

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59797 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: MPF-1 VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X GOOD

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B 61 G A-A 40 G A-GR 5.0 G A PHASE 27

A-C 58 G B-B 38 G B-GR 4.9 G B PHASE 28

B-C 59 G C-C 39 G C-GR 4.5 G C PHASE 28

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN 1 KV 25KV A PH 1 B PH 1 C PH 1 PASS

TEST WITNESS: TEST TECHNICIAN: Timothy Marsh

REMARKS

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59803 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: MPF-2 VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X GOOD

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B 47 G A-A 38 G A-GR 5.1 G A PHASE 25

A-C 48 G B-B 34 G B-GR 4.9 G B PHASE 26

B-C 50 G C-C 33 G C-GR 4.6 G C PHASE 26

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN 1 KV 25KV A PH 1 B PH 1 C PH 1 PASS

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59981 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: PF-2-3 VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X GOOD

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B 38 G A-A 30 G A-GR 4.2 G A PHASE 24

A-C 40 G B-B 35 G B-GR 4.5 G B PHASE 26

B-C 41 G C-C 38 G C-GR 4.7 G C PHASE 26

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN 1 KV 25KV A PH 1 B PH 1 C PH 1 PASS

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59804 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: PF-2-2 VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X GOOD

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B 44 G A-A 41 G A-GR 3.4 G A PHASE 24

A-C 47 G B-B 41 G B-GR 3.5 G B PHASE 25

B-C 45 G C-C 42 G C-GR 3.6 C PHASE 25

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN 1 KV 25KV A PH 1 B PH 1 C PH 1 PASS

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59805 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: PF-2-4 VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X GOOD

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B 47 G A-A 34 G A-GR 14 G A PHASE 25

A-C 51 G B-B 35 G B-GR 14 G B PHASE 26

B-C 51 G C-C 41 G C-GR 19 G C PHASE 24

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN 1 KV 25KV A PH 1 B PH 1 C PH 1 PASS

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59802 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: PF-2-1 VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X FAILED WOULD NOT CHARGE

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B A-A A-GR A PHASE

A-C B-B B-GR B PHASE

B-C C-C C-GR C PHASE

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN KV A PH B PH C PH

BREAKER WOULD NOT CHARGE. FAILED BREAKER MOVED TO COMPT. PF-1-4.

TEST WITNESS: TEST TECHNICIAN: Timothy Marsh

SPARE BREAKER FROM COMPT. PF-1-3 MOVED TO COMPT. PF-2-1.

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59796 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: PF-1-1 VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X GOOD

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B 46 G A-A 43 G A-GR 2.9 G A PHASE 24

A-C 46 G B-B 43 G B-GR 2.9 G B PHASE 24

B-C 49 G C-C 40 G C-GR 3.0 G C PHASE 25

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN 1 KV 25KV A PH 1 B PH 1 C PH 1 PASS

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59799 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: PF-1-3 VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X GOOD

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B 57 G A-A 56 G A-GR 5.5 G A PHASE 26

A-C 48 G B-B 59 G B-GR 5.0 G B PHASE 25

B-C 46 G C-C 57 G C-GR 5.1 G C PHASE 26

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN 1 KV 25KV A PH 1 B PH 1 C PH 1 PASS

BREAKER IN COMPT. PF-2-1 FAILED. THIS BREAKER MOVED FROM COMPT. PF-1-3 TO COMPT.

TEST WITNESS: TEST TECHNICIAN: Timothy Marsh

PF-2-1.

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59801 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: PF-1-2 VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X GOOD

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B 54 G A-A 47 G A-GR 2.8 G A PHASE 26

A-C 56 G B-B 46 G B-GR 2.9 G B PHASE 25

B-C 58 G C-C 47 G C-GR 3.0 G C PHASE 26

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN 1 KV 25KV A PH 1 B PH 1 C PH 1 PASS

Phone 904-272-2273 Fax 904-272-8438

HIGH VOLTAGE SWITCH/OCB TEST REPORT

CUSTOMER: MONTGOMERY CAVHCS DATE: 8/20/22

EQUIPMENT: 15KV MFG: SQ D

MOD #: V5D6122Y000 SER #: 17-59798 TYPE: VR 1200A

LOCATION: MAIN SUB CIRCUIT: 52-T VOLTAGE: 15KV

DESCRIPTION CHECKED CONDITION REMARKS

CONTACTS X GOOD

NA ARC CHUTES NA

MECHANICAL MECHANISM X GOOD

RACKING DEVICE X GOOD

CUBICLE CLEANED X GOOD

ELECTRICAL CONNECTIONS X GOOD

INSULATORS X GOOD

BUSHINGS X GOOD

MEGGER TEST RESULTS (MEG-OHMS)

CLOSED OPEN TO GROUND

DUCTOR TEST RESULTS

(MICRO-OHMS)

A-B 61 G A-A 40 G A-GR 5.0 G A PHASE 25

A-C 60 G B-B 44 G B-GR 4.2 G B PHASE 26

B-C 55 G C-C 41 G C-GR 4.7 G C PHASE 25

AC HIGH POTENTIAL TEST RESULTS

TEST TIME TEST VOLT LEAKAGE M/AMPS REMARKS

MIN 1 KV 25KV A PH 1.0 B PH 1.0 C PH 1.0 PASS

SUNCOAST INDUSTRIAL TESTING SERVICES INC.

LOW VOLTAGE CIRCUIT BREAKER TEST RECORD (Less than 600 volts)

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: GEN 2 SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 800 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X A TO F

1.0X DEL 20 4X DEL .33 6X A

CONTACT RESISTANCE: A 53 B 49 C 52

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

800 AMPS AMPS AMPS800 800

3X AMPS 48 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 48 3X 48

1.5X .3 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .3 1.5X .3

AMPS6X CY4 6X 4 6X 3

20 AMPS SEC AMPS SEC.011 20 .011 AMPS SEC20 .011

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

ORANGE PARK, FL 32065-7746

PHONE (904) 272-2273 FAX (904) 272-8438

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: TS GA-130 SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 100 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X A TO F

1.0X DEL 20 4X DEL .33 6X A

CONTACT RESISTANCE: A 89 B 94 C 96

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

100 AMPS AMPS AMPS100 100

** AMPS SEC

AMPS

AMPSAMPS

SEC

SECSEC

AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SECAMPS CY

AMPS SEC AMPS SEC AMPS SEC

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

TRIPS ON SHORT TIME SETTING AT 300A. TRIP UNIT BAD REPLACE WHEN CONVENIENT.

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-9D TSE SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 300 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X A TO F

1.0X DEL 20 4X DEL .33 6X A

CONTACT RESISTANCE: A 74 B 63 C 72

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

300 AMPS AMPS AMPS300 300

3X AMPS 57 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 58 3X 57

1.5X .3 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .3 1.5X .3

AMPS6X CY4 6X 3 6X 4

20 AMPS SEC AMPS SEC.13 20 .13 AMPS SEC20 .13

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-10D TSQ SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 400 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X A TO F

1.0X DEL 20 4X DEL .33 6X A

CONTACT RESISTANCE: A 65 B 67 C 72

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

400 AMPS AMPS AMPS400 400

3X AMPS 51 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 48 3X 52

1.5X .3 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .3 1.5X .3

AMPS6X CY4 6X 4 6X 4

40 AMPS SEC AMPS SEC.012 40 .12 AMPS SEC40 .12

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM-G-151A

CIRCUIT DESIGNATION: M2-8 SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: SQ D FRAME: 800

TRIP DEVICE: RMS 500 COIL RATING: 800 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.0 X 2X TO 10X 2X TO 12X A TO F

.95X DEL 4 4X DEL.1 6X B DEL .3

CONTACT RESISTANCE: A 68 B 68 C 64

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

800 AMPS AMPS AMPS800 800

3X AMPS 23 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 23 22 24

1.5X .13 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .13 1.5X .13

AMPS6X CY5 6X 5 6X 5

320 AMPS SEC AMPS SEC.34 320 .34 AMPS SEC320 ,34

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

Spring Position indicator bad.

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-151

CIRCUIT DESIGNATION: MCCN-1D SER#

BREAKER-INFORMATION

TYPE: ME 236LSIMAKE: SQUARE D FRAME: 400

TRIP DEVICE: SOLID STAT COIL RATING: 400 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X T0 1.0X 2X TO 9X 2X TO 10X .2X TP .75X

1.0X DEL 1 2X DEL.1 2X .2 DEL 1

CONTACT RESISTANCE: A 388 B 384 C 436

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

400 AMPS AMPS AMPS400 400

3X AMPS 38 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 38 3X 36

1.5X .12 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .12 1.5X .12

AMPS6X CY4 6X 2 6X 4

40 AMPS SEC AMPS SEC.16 40 .16 AMPS SEC40 .17

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-151

CIRCUIT DESIGNATION: MCCN-2B SER#

BREAKER-INFORMATION

TYPE: ME 236LSIMAKE: SQUARE D FRAME: 400

TRIP DEVICE: SOLID STAT COIL RATING: 250 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X T0 1.0X 2X TO 9X 2X TO 10X .2X TP .75X

1.0X DEL 1 2X DEL.1 2X .2 DEL 1

CONTACT RESISTANCE: A 411 B 399 C 418

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

250 AMPS AMPS AMPS250 250

3X AMPS 44 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 43 3X 44

1.5X .13 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .13 1.5X .13

AMPS6X CY4 6X 4 6X 4

40 AMPS SEC AMPS SEC,18 40 ,18 AMPS SEC40 ,18

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-151

CIRCUIT DESIGNATION: SPARE SER#

BREAKER-INFORMATION

TYPE: ME 236LSIMAKE: SQUARE D FRAME: 225

TRIP DEVICE: SOLID STAT COIL RATING: 200 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X T0 1.0X 2X TO 9X 2X TO 10X .2X TP .75X

1.0X DEL 1 2X DEL.1 2X .2 DEL 1

CONTACT RESISTANCE: A 368 B 384 C 373

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

200 AMPS AMPS AMPS200 200

3X AMPS 42 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 42 3X 42

1.5X ,13 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .13 1.5X .13

AMPS6X CY4 6X 4 6X 4

40 AMPS SEC AMPS SEC.16 40 .16 AMPS SEC40 .16

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM-G-151A

CIRCUIT DESIGNATION: M2-4 SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: SQ D FRAME: 800

TRIP DEVICE: RMS 500 COIL RATING: 300 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.0 X 2X TO 10X 2X TO 12X A TO F

0.7X DEL4 4X DEL .3 4 C DEL .3

CONTACT RESISTANCE: A 79 B 74 C 70

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

300 AMPS AMPS AMPS300 300

3X AMPS 22 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 25 3X 25

1.5X .18 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .18 1.5X .18

AMPS6X CY4 6X 4 6X 4

216 AMPS SEC AMPS SEC.28 216 .28 AMPS SEC216 .28

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-6 D SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTETOR I COIL RATING: 100 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.7X TP 1OX 3X TO 6X N/A

1.0X DEL 20 4X DEL.33 6X

CONTACT RESISTANCE: A 155 B 154 C 162

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

100 AMPS AMPS AMPS100 100

3X AMPS 66 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 67 3X 66

1.5X .35 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .35 1.5X .35

AMPS6X CY3 6X 3 6X 4

AMPS SEC AMPS SEC AMPS SEC

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-9 D SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTETOR I COIL RATING: 300 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.7X TP 1OX 3X TO 6X N/A

1.0X DEL 20 4X DEL.33 6X

CONTACT RESISTANCE: A 138 B 164 C 151

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

400 AMPS AMPS AMPS400 400

3X AMPS 68 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 68 3X 67

1.5X .4 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .4 1.5X .4

AMPS6X CY4 6X 4 6X 4

AMPS SEC AMPS SEC AMPS SEC

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-151

CIRCUIT DESIGNATION: NFP-GD-N44B SER#

BREAKER-INFORMATION

TYPE: ME 236LSIMAKE: SQUARE D FRAME: 225

TRIP DEVICE: SOLID STAT COIL RATING: 150 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X T0 1.0X 2X TO 9X 2X TO 10X .2X TP .75X

1.0X DEL 1 2X DEL 1 6X .2 DEL 1

CONTACT RESISTANCE: A 338 B 370 C 367

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

150 AMPS AMPS AMPS150 150

3X AMPS 42 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 42 3X 44

1.5X .45 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .45 1.5X .45

AMPS6X CY4 6X 4 6X 4

40 AMPS SEC AMPS SEC.18 40 .18 AMPS SEC40 ,18

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-151

CIRCUIT DESIGNATION: TSQ-XRAY SER#

BREAKER-INFORMATION

TYPE: ME 236LSIMAKE: SQUARE D FRAME: 400

TRIP DEVICE: SOLID STAT COIL RATING: 400 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X T0 1.0X 2X TO 9X 2X TO 10X .2X TP .75X

.95 DEL 8 7X DEL .1 9X .2 DEL 1

CONTACT RESISTANCE: A 332 B 356 C 384

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

400 AMPS AMPS AMPS400 400

3X AMPS 46 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 46 3X 46

1.5X .23 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X 23 1.5X 23

AMPS6X CY4 6X 4 6X 4

40 AMPS SEC AMPS SEC.17 40 .17 AMPS SEC40 ,17

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM-G153A

CIRCUIT DESIGNATION: 52-6D SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR1 COIL RATING: 100 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.7X TP 10 2X TO 10X 3X TO 6X N/A

1X DEL20 4X DEL .33 6X

CONTACT RESISTANCE: A 149 B 150 C 156

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

100 AMPS AMPS AMPS100 100

3X AMPS 67 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 68 3X 68

1.5X .35 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .35 1.5X .35

AMPS6X CY4 6X 4 6X 4

AMPS SEC AMPS SEC AMPS SEC

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-8D TS-CF SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 200 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X

1.0X DEL 20 4X DEL .33 6X 5A 2 CYCLES

CONTACT RESISTANCE: A 141 B 140 C 147

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

200 AMPS AMPS AMPS200 200

3X AMPS 66 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 64 3X 66

1.5X .3 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .3 1.5X .3

AMPS6X CY4 6X 3 6X 4

5 AMPS SEC AMPS SEC.13 5 .13 AMPS SEC5 .13

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-2D TSQFP- SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 200 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X

1.0X DEL 20 4X DEL .33 6X 7A 2 CYCLES

CONTACT RESISTANCE: A 168 B 164 C 158

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

200 AMPS AMPS AMPS200 200

3X AMPS 66 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 66 3X 65

1.5X .3 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .3 1.5X .3

AMPS6X CY3 6X 3 6X 3

7 AMPS SEC AMPS SEC.12 7 .12 AMPS SEC7 .011

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-5D TS-EFP SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 100 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X

1.0X DEL 20 4X DEL .33 6X 15A 6 CYCLES

CONTACT RESISTANCE: A 104 B 98 C 106

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

100 AMPS AMPS AMPS100 100

3X AMPS 64 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 66 3X 66

1.5X .3 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .3 1.5X .3

AMPS6X CY4 6X 3 6X 3

15 AMPS SEC AMPS SEC.045 15 .04 AMPS SEC15 .045

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-4D TS-QFP SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 400 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X

1.0X DEL 20 4X DEL .33 6X 20 6 CYCLES

CONTACT RESISTANCE: A 59 B 64 C 71

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

400 AMPS AMPS AMPS400 400

3X AMPS 59 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 64 3X 63

1.5X .3 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .3 1.5X .3

AMPS6X CY3 6X 4 6X 4

20 AMPS SEC AMPS SEC.45 20 .45 AMPS SEC20 .45

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-1D TS-Q-X SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 400 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X

1.0X DEL 20 4X DEL .33 6X 40A 6 CYCLES

CONTACT RESISTANCE: A 128 B 133 C 157

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

400 AMPS AMPS AMPS400 400

3X AMPS 62 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 63 3X 63

1.5X .35 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .33 1.5X .33

AMPS6X CY5 6X 5 6X 5

40 AMPS SEC AMPS SEC.05 40 .05 AMPS SEC40 .05

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-7D TS-CFP SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 600 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X

1.0X DEL 20 4X DEL .33 6X 20A 6 CYCLES

CONTACT RESISTANCE: A 117 B 120 C 134

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

600 AMPS AMPS AMPS600 600

3X AMPS 63 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 63 3X 62

1.5X .4 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .4 1.5X .3

AMPS6X CY4 6X 4 6X 3

20 AMPS SEC AMPS SEC.05 20 .05 AMPS SEC20 .05

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: 52-3D TSQFP- SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 800 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X

1.0X DEL 20 4X DEL .33 6X 20A 6 CYCLES

CONTACT RESISTANCE: A 110 B 119 C 120

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

800 AMPS AMPS AMPS800 800

3X AMPS 64 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 66 3X 64

1.5X .3 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .3 1.5X .3

AMPS6X CY3 6X 3 6X 3

20 AMPS SEC AMPS SEC.03 20 .03 AMPS SEC20 .03

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM G-153A

CIRCUIT DESIGNATION: GEN 1 SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: WESTINGHOUSE FRAME: 800

TRIP DEVICE: AMPTECTOR COIL RATING: 800 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.25X 2X TO 10X 2X TO 12 X

1.0X DEL 20 4X DEL .33 6X 120 2 CYCLES

CONTACT RESISTANCE: A 76 B 64 C 69

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

800 AMPS AMPS AMPS800 800

3X AMPS 66 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 65 3X 65

1.5X .3 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .3 1.5X .3

AMPS6X CY4 6X 4 6X 3

20 AMPS SEC AMPS SEC.013 20 .013 AMPS SEC20 .013

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM-G-151A

CIRCUIT DESIGNATION: MAIN 1 SER#

BREAKER-INFORMATION

TYPE: DS-402MAKE: SQ D FRAME: 2000

TRIP DEVICE: RMS 500 COIL RATING: 2000 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.0 X 2X TO 10X N/A A TO F

1.0X DEL4 2x del 0.5 N/A K DEL 0.5

CONTACT RESISTANCE: A 72 B 74 C 68

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 1k B-B 1k C-C 1k

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

2000 AMPS AMPS AMPS2000 2000

3X AMPS 66 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 67 3X 66

1.5X .18 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X ,18 1.5X ,18

AMPSN/A CY

500 AMPS SEC AMPS SEC,32 500 ,32 AMPS SEC500 ,32

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

BREAKER PICK-UP WAS SET AT 2000amps EVEN THOUGH ID PLATE ON DOOR INDICATED

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1800amps

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM-G-151A

CIRCUIT DESIGNATION: MAIN 2 SER#

BREAKER-INFORMATION

TYPE: DS-420MAKE: SQ D FRAME: 2000

TRIP DEVICE: RMS 500 COIL RATING: 2000 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.0 X 2X TO 10X N/A A TO F

1.0X DEL 20 10x DEL .5 N/A K DEL .5

CONTACT RESISTANCE: A 112 B 84 C 88

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

2000 AMPS AMPS AMPS2000 2000

3X AMPS * SEC

AMPS

AMPSAMPS

SEC

SECSEC3X * 3X *

6X .16 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

6X .16 6X ,16

AMPSN/A CY

500 AMPS SEC AMPS SEC.12 500 .12 AMPS SEC500 .12

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

breaker failed totrip on long time.

ANALYST (NAME): Timothy Marsh DATE: 8-2022

FAILED

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM-G-151A

CIRCUIT DESIGNATION: M1-8 /SPARE SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: SQ D FRAME: 800

TRIP DEVICE: RMS 500 COIL RATING: 800 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.0 X 2X TO 10X 2X TO 12X A TO F

1.0X DEL 24 5X DEL .3 6X D DEL .3

CONTACT RESISTANCE: A 184 B 181 C 181

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

800 AMPS AMPS AMPS800 800

3X AMPS 61 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 62 3x 61

1.5X .13 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .13 1.5X .13

AMPS6X CY5 6X 5 6X 5

320 AMPS SEC AMPS SEC.15 320 .15 AMPS SEC320 .15

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

BREAKER PICK-UP WAS SET AT 800amps EVEN THOUGH ID PLATE ON DOOR INDICATED 400a

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM-G-151A

CIRCUIT DESIGNATION: M1-4 /SPARE SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: SQ D FRAME: 800

TRIP DEVICE: RMS 500 COIL RATING: 800 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.0 X 2X TO 10X 2X TO 12X A TO F

1.0X DEL 24 5X DEL .3 6X D DEL .3

CONTACT RESISTANCE: A 208 B 210 C 204

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

800 AMPS AMPS AMPS800 800

3X AMPS 60 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 61 3X 61

1.5X .13 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .13 1.5X .13

AMPS6X CY5 6X 5 6X 5

320 AMPS SEC AMPS SEC,20 320 .21 AMPS SEC320 .21

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

RETURN TRIP ARM SPRING IS WEAK.

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM-G-151A

CIRCUIT DESIGNATION: M2-1 TS-QF SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: SQ D FRAME: 800

TRIP DEVICE: RMS 500 COIL RATING: 800 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.0 X 2X TO 10X 2X TO 12X A TO F

1.0X DEL4 4X DEL .1 6X A DEL .4

CONTACT RESISTANCE: A 124 B 136 C 154

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

800 AMPS AMPS AMPS800 800

3X AMPS 45 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 45 3X 47

1.5X ,15 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X .15 1.5X .15

AMPS6X CY5 6X 5 6X 5

200 AMPS SEC AMPS SEC.36 200 .36 AMPS SEC200 .37

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD STE 301

SCHEDULED: X NEW INSTALLATION: SPECIAL:

FIELD OFFICE: CAVHCS MONTGOMERY

BUILDING AND LOCATION: RM-G-151A

CIRCUIT DESIGNATION: M1-5 CDP-GD SER#

BREAKER-INFORMATION

TYPE: DS-206MAKE: SQ D FRAME: 800

TRIP DEVICE: RMS 500 COIL RATING: 800 CURVE NO:

LONG TIME SHORT TIME INST GROUND

RANGE

SETTING

.5X TO 1.0 X 2X TO 10X 2X TO 12X A TO F

1.0X DEL 12 10X DEL 0.4 12X B DEL .4

CONTACT RESISTANCE: A 204 B 183 C 188

MEGGER: A-B 2K B-C 2K C-A 2K A-GR 2K B-GR 2K C-GR 2K

MEGGER TEST OPEN: A-A 2K B-B 2K C-C 2K

TRIP-UNITS-TEST

MIN PICK UP

A PHASE B PHASE C PHASE

LONG TIME

SHORT TIME

INST

GROUND

800 AMPS AMPS AMPS800 800

3X AMPS 34 SEC

AMPS

AMPSAMPS

SEC

SECSEC3X 36 3X 36

1.5X ,4 AMPS

AMPS

SEC

CY

AMPS

AMPS

SEC

SEC

1.5X ,4 1.5X ,4

AMPS6X CY4 6X 4 6X 4

240 AMPS SEC AMPS SEC.13 240 .13 AMPS SEC240 .13

REMARKS: MEGGER READINGS IN MEG-OHMS DUCTOR IN MICRO-OHMS

ANALYST (NAME): Timothy Marsh DATE: 8-2022

1033 BLANDING BLVD…