36C24724Q0222 0002 Questions and Answers.docx
DOCX document 90 KB Posted
- Attached to
- N071--IDIQ WORKLOAD SERVICE
- Solicitation number
- 36C24724Q0222
About this file
This document is a set of Questions and Answers related to RFQ #36C24724Q0222 for Workload Services. The key details are:
The RFQ requires a contractor to provide a full range of services to disassemble/reassemble, repair, transport, and install furniture, equipment, and other property for the Atlanta VA Health Care System. This includes services to outlying Outpatient Clinics on a periodic basis. The contract will be a firm-fixed price IDIQ with a base period of May 1, 2024 through April 31, 2029 and four one-year renewal options. The RFQ will be issued as a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside. The questions address billing and invoicing details for the different line items, including hours worked, jobs/tasks, and inventory management.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24724Q0222 0002.docx | DOCX document | |
| 36C24724Q0222 0001.docx | DOCX document | |
| 36C24724Q0222 0001_1.docx | DOCX document | |
| 36C24724Q0222_2 Notice.docx | DOCX document | |
| 36C24724Q0222 Workload Service Contract.docx | DOCX document | |
| 36C24724Q0222_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
Department of Veterans Affairs VISN 7 Network Contracting Office LaVista Business Park - Bldg A 2008 Weems Road Tucker GA 30084
Department of Veterans Affairs VISN 7 Network Contracting Office LaVista Business Park - Bldg A 2008 Weems Road Tucker GA 30084 To all Offerors/Bidders
36C24724Q0222 05-15-2024
X x x
Amendment for RFQ#36C24724Q0222 Question and Answers:
1) RFQ#36C24724Q0222 Question and Answers are attached.
2) 3) All other terms and conditions remain unchanged.
RFQ#36C24724Q0222 Question and Answers:
1. Question: For Items 0001,2001,3001 & 4001(workload services), can you explain how the VA came up with number and how would we bill for that line item. For one full day of work (800hrs to 1630hrs), would we bill the VA 8 hours or a combined total of 24 hours (3worker * 8) for that line item?
Answer: All based on man hour; combined total of 24 hours (3worker * 8)
2. Question: How would the billing work for the contractor when workers take items to other locations?
Would we bill for the total hours worked for the day and the job, or would we be only allowed to use one line item? Let’s say they worked for 8 hours today at the main VA location they were there for 4 hours but had to move items to another location (CBOC) which took 4 hours. Would or would billing be 4 hours for line item 0001 and 1 JB for line item 0002/0003?
Answer: Billing will be 8 hours for line item 0001 and 1 JB for line item 0002/0003.
3.Question: Line item 0002/0003 the unit of measure is JB (job). Please describe for billing purposes what counts as one job. If workers were to go to multiple stops (sites) in one trip would this count as multiple jobs or one? For example, workers pick up from point A and take items to point B then to point C and then return to point A, would this count as 2 jobs or 1 job?
Answer: The example for multiple stops will be consider 1 job unless the delivery location includes a non-local site. In that case, non-local fee should be charge only to cover the days works.
4. Question: How would billing work for line items 0004/0005? Would we bill for hours worked plus each workstation disconnected/setup, or would we only bill for the workstation disconnected/setup?
Example being that if it took 4 hours to setup a workstation would we bill 4 hours under line item 0001 and 1 JB under line item 0004, or would it be just 1 JB under line item 0004?
Answer: Each workstation setup/disconnection will be 1 job underline item 0004.
5. Question: Is the contractor responsible for conducting inventory or keeping storage organized?
Answer: Responsible of keeping inventory and organization of the VA onsite storage areas as needed.
6. Question: How big is the storage area?
Answer: Approx 1250 sq.
7. Question: How long is the badging process?
Answer: Up to 14days.