36C24719Q0683-007.docx
DOCX document 14 KB Posted
- Solicitation number
- 36C24719Q0683
About this file
36C24719Q0683 36C24719Q0683_6.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24719Q0683-006.docx | DOCX document | |
| 36C24719Q0683-005.docx | DOCX document | |
| 36C24719Q0683-004.docx | DOCX document | |
| 36C24719Q0683-003.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FedBizOpps Amendment to a Previous Combined Solicitation
CLASSIFICATION CODE
SUBJECT
CONTRACTING OFFICE'S
ZIP-CODE
SOLICITATION NUMBER
BASE NOTICE TYPE
RESPONSE DATE (MM-DD-YYYY)
ARCHIVE
DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
SET-ASIDE
NAICS CODE
CONTRACTING OFFICE
ADDRESS
POINT OF CONTACT
(POC Information Automatically Filled from User Profile Unless Entered)
DESCRIPTION
See Attachment
AGENCY'S URL
URL DESCRIPTION
AGENCY CONTACT'S EMAIL
ADDRESS
EMAIL DESCRIPTION
ADDRESS
POSTAL CODE
COUNTRY
ADDITIONAL INFORMATION
GENERAL INFORMATION
PLACE OF PERFORMANCE
* = Required Field FedBizOpps Amendment to a Previous Combined Solicitation Rev. March 2010 J Water Treatment Service - Chiller and Boiler Plant QUESTIONS and ANSWERS following SITE VISIT Solicitation DUE DATE for Receipt of Quotes is 08/02/2019 29403-5799 36C24719Q0683 07-26-2019 N 325998 Department of Veterans Affairs Ralph H. Johnson VA Medical Center 109 Bee Street Charleston SC 29403-5799 John Norway at john.norway@va.gov WJB Dorn VA Medical Center Columbia, South Carolina 29209 SOLICITATION No. 36C247-19-Q-0683 Water Treatment Service Chiller and Boiler Plant WJB Dorn VA Medical Center, Columbia, SC
AMENDMENT No. 04 Solicitation DUE DATE for Quotes remains Friday, August 2nd 2019
SITE VISIT Questions and Answers:
1. Question: Do all the chillers potentially come online at the same time, depending on load of course. (i.e. 2750 combined tons available), or is there a lead-lag program with the chillers where a smaller total tonnage is utilized?
Answer: YES, ALL CHILLERS MAY BE ON LINE AT ONE TIME. YES, THERE IS A LEAD-LAG PROGRAM.
2. Question: What is the average water loss per year for the chilled water system? Answer: GOVERNMENT DOES NOT HAVE THAT INFORMATION AS RECORDS HAVE NOT BEEN KEPT ON WATER LOSS ON CHILL WATER SYSTEM.
3. Question: I have not seen a designation for a particular chilled loop inhibitor. There are a couple of main options concerning which chemical to use. Is there a designated chemical that companies are supposed to use? (I.e. Nitrite or Molybdenum)? Answer: NITRITE IS CURRENTLY IN SYSTEM. GOVERNMENT WOULD PREFER TO KEEP SAME CHEMICAL IN SYSTEM.
4. Question: What is the Boiler Steam Load?
Answer: DEPENDS ON THE DEMAND FROM THE HOSPITAL and UNIVERSITY of SOUTH CAROLINA SCHOOL OF MEDICINE. DAILY STEAM OUTPUT RUNS FROM 100,000 LBS to 500,000 LBS PER DAY.