36C24627Q0086 0001.docx

DOCX document 32 KB Posted

Attached to
RENTAL OF TWO CHILLERS FOR ONE YEAR
Solicitation number
36C24627Q0086
Issued by

About this file

This is a Standard Form 30 Amendment to Solicitation/Modification of Contract issued by the Department of Veterans Affairs Network Contracting Office 6 (Hampton, VA) for solicitation 36C24627Q0086. The amendment extends the deadline for quote submission from October 30, 2026 at 12:00 PM ET to November 10, 2026 at 12:00 PM ET, updates Section B.3 Statement of Work, provides government responses to 60 contractor questions, and replaces clause VAAR 852.219-76 with VAAR 852.219-75 (Limitations on Subcontracting for Services). The solicitation requires rental of two air-cooled chillers for one year at the Charles George VA Medical Center: a 100-ton chiller for Building 15 and a 400-ton chiller for Building 47, with both units required to be fully operational by December 11, 2026. Equipment specifications include the basis-of-design units manufactured by YORK/Johnson Controls, with both units maintaining 45-degree chilled water; equivalent manufacturers and models are acceptable with non-mandatory refrigerants. Electrical requirements are 480VAC 3-phase 60Hz for both units, with the 100-ton unit requiring 223-amp capacity on a single circuit and the 400-ton unit requiring 781-amp capacity available through facility power connections with temporary camlock receptacles already in place.

The contract scope includes delivery, installation, routine preventative maintenance, emergency response (2-4 hour target response time), and removal of the temporary chillers, with the contractor bearing responsibility for electrical tie-ins, rigging, permits, and final disconnection. Price/Cost Schedule line items include rental of the chillers (CLINs 0001 and 0002), hose assemblies (CLIN 0003—six 4-inch-diameter hoses at 25 feet each), 4/0 camlock cables (CLIN 0004—50 feet), and 4/0 pigtails (CLIN 0005), with pricing to cover the complete rental period and all maintenance included; delivery and installation may be unnecessary if existing rental equipment remains in place. The government will provide access, utilities, power and chilled water supply/return connections, and connection of temporary electrical conductors and chilled water lines to facility infrastructure. The solicitation is SDVOSB-set-aside and subject to VAAR 852.219-75, which limits subcontracting to no more than 50% of government payments to non-VIP-listed SDVOSB/VOSB firms. Required documentation includes monthly maintenance reports and immediate notification of any operational issues; the site map and equipment specifications are attached. This is a continuation of existing rental installation under current contract 36C24626P1084.

View the file

Other files

File Type Posted
100 Ton step-up xfmr.jpeg JPEG file
400 ton breaker 800 A.jpeg JPEG file
400 ton chilled water return.jpeg JPEG file
400 ton electrical.jpeg JPEG file
400 ton chilled water supply.jpeg JPEG file
Site Map.jpg JPG image
400 Ton chiller.jpeg JPEG file
100 Ton mechanical.jpeg JPEG file
100 Ton chiller.jpeg JPEG file
salient characteristics.docx DOCX document
36C24627Q0086.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 10-29-2026 Harold McQuillia harold.mcquillia@va.gov Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton

VA

23667 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton

VA

23667 To all Offerors/Bidders

36C24627Q0086

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 11-10-2026 12pm EST See CONTINUATION Page X The purpose of this amendment is to extend the deadline for quote submission, update Section B.3 SOW, and provide government answers to contractor questions for this solicitation.

a. The deadline for quote submission is hereby changed from 10/30/2026 12pm et. to 11/10/2026 12pm et.

b. Government answers to contractor questions are attached on page 2.

c. Section B.3 Statement of Work (SOW) is updated and attached on 4.

d. Clause 852.219-76 is hereby replaced with 852.219-75 and must be complete, signed, and dated by the offeror.

e. Required drawings and site maps are attached.

There are no other changes to this solicitation as a result of this amendment.

Harold McQuillia Contracting Officer

CONTINUATION PAGE

36C24627Q0086 Chiller Rental Questions

1. Appropriate equipment selection – Offerors need to verify existing conditions, connection points, available space, and clearances to confirm that the proposed equipment meets the facility's needs and is equivalent to the salient characteristics. The salient characteristics proposed are those of the 2 rental units currently on site. These units have been meeting the facility’s needs since April so there is no need to confirm.

2. Cable and hose lengths – The Price/Cost Schedule lists fixed quantities and lengths of chiller hose (CLIN 0003), 4/0 camlock cable (CLIN 0004), and 4/0 pigtails (CLIN 0005). Without seeing the distance between each chiller location, the electrical source, and the chilled water connections, offerors cannot confirm that these quantities and lengths are enough for a complete, working installation. The listed lengths and quantities represent the current configuration of the rental units currently on site, which are sufficient for a complete working installation.

3. Offerors need to determine whether a flatbed truck can get to each chiller location, or whether a crane or other means of placement will be required. This affects cost, schedule, safety planning, and coordination with hospital operations. A flatbed truck is able to get to each location, however the 400-ton chiller will most likely be permanently affixed to a trailer.

4. That the Government schedule a site visit for interested offerors, or allow individual site visits by appointment, at Buildings 15 and 47 before the quote due date.

A formal site visit will not be conducted.

5. If either option will take additional time, that the Government consider a short extension of the quote due date so offerors can include the site information in their quotes.

Deadline has been updated.

6. Are equivalent manufacturers/models acceptable, and are the specified refrigerants mandatory? Please confirm whether the 223-amp and 781-amp limits include associated pumps and accessories. Equivalent manufacturers/models are acceptable, the specified refrigerants are not mandatory. The 223-amp and 781-amp limits do include associated pumps and accessories.

7. Please provide the required entering/leaving water temperatures, flow rates, pressure requirements, design ambient conditions, and allocation of each chiller to Buildings 15 and 47. Building 15 and 47 need to be able to maintain 45 degrees. Flow rates, pressure requirements, and design ambient conditions will all be taken care of by getting a 100 ton chiller and a 400 ton chiller. The 100 ton will be supplied to building 15 and the 400 ton will be supplied to building 47.

8. Is this a continuation of an existing rental installation or a replacement requiring changeover? Please provide available site drawings, photographs, equipment locations, connection details, hose/cable routes, and electrical service/disconnect information. This is a continuation of an existing rental installation. Please see attachments.

9. Please identify responsibility for pumps, glycol/freeze protection, strainers, controls, electrical tie-ins, rigging, permits, and final disconnection/removal. Only the pumps that are integral to the unit will be the responsibility of the contractor. Freeze protection, strainers, and controls are N/A our facility does not utilize glycol, there are no strainers on our chilled water, and the units will be run manually. Electrical tie-in, rigging, permits, and disconnection will be the responsibility of the contractor.

10. Does CLIN 0003 intend six 4-inch-diameter hoses, each 25 feet long? Yes

11. For CLINs 0003–0005, should each quoted unit price cover use throughout the entire rental period, or is another pricing basis intended? Please confirm where delivery, installation, maintenance, and removal costs should be included within the five CLINs. Yes, price should cover use throughout the rental period. If the offeror intends to continue the rental of the existing rental equipment (preferable) then there should be no delivery or installation cost. Maintenance should be included in the cost of each line item. Removal will have to be a line item by itself and removal is contingent upon repair of the existing system so there is no way to know when this will take place.

12. Must both chillers be fully operational by December 11, 2026, and may installation occur beforehand? Please confirm the required operational time and permitted changeover/outage window.

Must be operational by 12/11/2026.

13. The schedule lists 52 weeks, while the stated performance period spans a full calendar year. Please confirm that the scheduled quantities cover the complete stated period. The units are needed for a full calendar year

14. Please specify required emergency acknowledgment, onsite response, restoration, and replacement timeframes. Is standby equipment, remote monitoring, or continuous onsite staffing required? Please clarify the division of daily operating responsibilities between VA and the contractor. Daily operations will be the responsibility of the VA. Standby equipment, remote monitoring, and continuous staffing are not required. The contractor should perform routine preventative maintenance on the units. Currently the rental contract does not specify a timeframe for onsite response, but if the unit fails on a hot day, patient care can be impacted within 1 hour. Therefore, it would be advantageous to make this response time as small as possible. Somewhere between 2-4 hours seems reasonable. Restoration and replacement timeframes should be as quickly as possible but availability of parts and replacement units is variable so it would be difficult to assign a solid figure to this.

15. Which chiller size (100-ton or 400-ton) is designated for Building 15 and Building 47? The 100-ton unit is for building 15, the 400-ton unit is for building 47

16. Are the quantities and lengths listed in the solicitation sufficient, or are additional hoses and electrical cables needed based on the distance to each building? Listed quantities and lengths are sufficient

17. Are external chilled-water connection points and electrical connections available, or is the contractor expected to route hoses and cables into the buildings? External connections are available at the chiller locations

18. Is there an incumbent contractor? If so, what is the contract number?

There is a current contract in place under 36C24626P1084.

19. Are there any chillers currently at the facility?

Yes, there are chillin place we are currently renting under the current contract in place.

20. Will the chillers connect to standby generators or existing electrical outlets? If outlets or other facility power connections are used, please confirm the required voltage and available connection points. Chillers will connect to facility power, voltage for both units is to be 480VAC. The connection points will be VA supplied cable and mechanical lugs at the units.

21. Is there a designated access route for delivery trucks and chiller transport to reach both buildings? Please advise of any access restrictions or clearance limitations. No restrictions or limitations

22. Please confirm that VAAR 852.219-76 (Limitations on Subcontracting - supplies/products) is the correct clause for this chiller rental requirement, rather than VAAR 852.219-75 (services), and advise how the 50% limitation is calculated for a one-year equipment rental: are the capped amounts the weekly rental payments to a supplying firm, are any rental amounts treated as excluded material cost, or does a different measure apply?

852.219-75 is the correct clause.

23. Does teaming with a supplier that is itself an SBA-certified SDVOSB satisfy the certification - that is, is a certified SDVOSB supplier treated as similarly situated so that amounts paid to it are not counted toward the 50% limitation - and if so, are we required to self-perform any portion of the requirement?

852.219-75 applies.

24. The 852.219-76 certification requires the offeror to represent that it will not pay more than 50% of the amount paid by the Government to subcontractors that are not similarly situated SDVOSBs, and the nonmanufacturer representations at 13 CFR 121.406(b) contemplate an offeror that normally sells the type of item involved and that takes ownership or possession of the item(s) with its own personnel, equipment, or facilities. For a rental requirement under which the supplying partner would retain possession of the units and perform delivery, installation, and maintenance, please advise how those representations apply.

Offeror must comply with 852.219-75.

25. The basis-of-design units are manufactured by YORK/Johnson Controls, which is not a small business. If we propose the basis-of-design units, is a waiver of the nonmanufacturer rule required, or should the quote propose an 'or equal' item manufactured by a small business? Does the rental nature of the requirement change that analysis?

N/A

26. Electrical Disconnect: Is there an existing, operational 460V / 3-Phase electrical disconnect box ready to receive temporary power cables from the rental unit? No, the temporary cables come from the breaker directly to the unit

27. Water Connections: Are the facility's chilled water lines equipped with 6-inch flanged tie-in valves at the exterior connection point, or will piping modifications be required?

No modifications required.

28. Please confirm whether delivery, installation, startup, and final disconnection/removal shall be included in the weekly rental pricing under Items 0001 and 0002, or priced separately. Separate line items, however, delivery installation and startup may be unnecessary if current units remain in place.

29. Are dedicated electrical circuits and connection points already available for both rental chillers? Please provide the source locations, available capacity, existing breaker sizes, and feeder sizes, along with any available one-line diagrams or panel schedules. Yes, connection points on both units are via twist lock connections to facility-owned DLO cable.

30. Who shall furnish and install any new breakers, disconnects, or feeders? Please provide the existing switchgear/MCC make/model, breaker requirements, and available spare breakers or MCC buckets. None of this is necessary, all infrastructure is already in place

31. Will electrical or chilled-water outages be permitted for installation and removal? Please identify allowable outage durations, work hours, advance notice, and any temporary cooling required during changeover. Outages will be made available, if necessary, most likely these will be able to occur during normal work hours. 1-week advance notice will suffice; no temporary cooling will be required during changeover if it takes place in December as planned.

32. Please identify the approved location for each chiller and confirm whether units may remain trailer-mounted or must be set on the ground. Please identify access restrictions and any required pads, ground preparation, fencing, or restoration. Units may remain trailer mounted, locations were identified in the previous set of questions, no access restrictions, pads, preparation, fencing or restoration is required

33. Please provide a site plan showing chiller locations, electrical and chilled-water connections, and hose/cable routes, including distances and required crossing protection. Site plan was provided with previous questions. Electrical and chilled water connections will take place at each unit, any connection beyond that is the responsibility of the facility

34. Electrical capacity (400-ton): The salient characteristics list a maximum load of 781A. Commercially available 400-ton-class rental units that are equal to the basis of design typically have an MCA of 828–880A, with a recommended 1,000A breaker. Does 781A reflect the facility's available electrical capacity? Will an equal unit with a higher MCA be acceptable? 781 does reflect the facility's available electrical capacity, a larger unit would be acceptable only if it has the capability to be run at less than full load

35. Electrical connection: Are camlock receptacles or fused disconnects already in place at each chiller location? If not, is the electrical tie-in the Government's or the contractor's responsibility? Camlock receptacles are already in place. Tie-in would be the responsibility of the government.

36. Cable and pigtail quantities (CLINs 0004 and 0005): Powering a 400-ton unit at that amperage requires three parallel 4/0 runs per phase plus ground (10 cables), and the 100-ton requires 4, for a total of 14. May offerors quote the quantities required to operate both units, or will the Government amend the CLIN quantities? Please also confirm whether the pigtails should be female camlock or bare-end.

Offerors shall quote for all equipment necessary to operate the chillers.

37. Freeze protection: Is the existing chilled-water loop glycol-treated? If not, is the contractor responsible for providing glycol or freeze protection for winter operation? No

38. If fittings, cabling, hoses, or any other items beyond those listed in B.2 are needed for a complete, working installation, will they be added by contract modification or chang How much power is available to connect the 100-ton temporary chiller at Building 15 (voltage, phase, available amperage, and overcurrent protection rating)? Our proposed 100-ton unit requires one 460 V, 3-phase, 60 Hz circuit with a minimum circuit ampacity (MCA) of 233 A and maximum overcurrent protection (MOP) of 250 A with its integral pump, or an MCA of 206 A and MOP of 225 A without the pump. Can the Building 15 power source support this load? Yes that is the exact configuration currently in use.

39. Is there only one power source available for the 100-ton chiller at Building 15? Our proposed 100-ton unit requires a single-point power connection. Yes

40. Will the Government be responsible for landing the power cables for the 100-ton chiller at the Building 15 power source? Yes

41. Is the Building 15 power source already outfitted with temporary camlock connections? Our proposed 100-ton unit uses Series 16 cam-type power connections. Yes

42. Is any modification to the Building 15 power source needed to connect the temporary cabling? If so, who is responsible for that work? No

43. Where is the Building 15 power source located, and approximately how far is it from the planned location of the 100-ton chiller? Located in an MCC adjacent to bldg. 15. Roughly 30’ from the proposed location

44. How long does the Government anticipate the electrical cabling will need to be for the 100-ton chiller at Building 15, from the power source to the planned chiller location? CLIN 0004 lists 50-ft 4/0 camlock cables. Please state whether a run longer than 50 ft is anticipated. Not anticipated

45. Will the awarded contractor be responsible for modifying the pre-existing water connections at Building 15 to make them suitable for the 100-ton temporary chiller? No

46. Is the awarded contractor responsible for providing glycol for the 100-ton chiller at Building 15? If so, what glycol type and percentage (concentration) is required, and how many gallons does the facility's chilled-water loop serving Building 15 hold? No

47. Is the awarded contractor responsible for providing water treatment for the 100-ton chiller at Building 15? No

48. Will existing facility pumps circulate chilled water through the 100-ton chiller at Building 15, or must the temporary chiller provide pumping? Our proposed 100-ton unit can be furnished with an integral 20-horsepower pump, which changes its electrical requirements? No

49. Will the awarded contractor be responsible for any wall penetrations needed to route the chilled-water piping or electrical connections for the 100-ton chiller into Building 15? If the piping and electrical connections must instead pass through a doorway, will the awarded contractor be responsible for sealing the doorway (for example, with plywood) for the rental term? No

50. Can the 100-ton temporary chiller remain on a flatbed trailer at Building 15 throughout the rental term, or must it be offloaded by crane? Are there any pad, weight, clearance, or access-route restrictions at that location? Our proposed 100-ton unit is approximately 17 ft 8 in. long by 8 ft 1 in. wide by 8 ft 6 in. high, with an operating weight of up to 12,700 lb, and requires clear space around the unit for airflow and service access. Yes, it can remain on a trailer, the proposed location is in the middle of a large parking lot so there are no route or access restrictions

51. If the 100-ton chiller at Building 15 goes into alarm because of facility infrastructure (for example, the building management system (BMS), the electrical power source, or the chilled-water system), will the Government pay for that out-of-scope service call through a contract modification or change order? yes

52. How much power is available to connect the 400-ton temporary chiller at Building 47 (voltage, phase, available amperage, and overcurrent protection rating)? Our proposed 400-ton unit requires two 460 V, 3-phase, 60 Hz circuits. With its integral pump, Circuit 1 requires an MCA of 482 A and MOP of 600 A, and Circuit 2 an MCA of 417 A and MOP of 500 A. Without the pump, each circuit requires an MCA of 417 A and MOP of 500 A. Can the Building 47 power source support this load? Building can provide one (3-phase) circuit up to 780 amps at 480vac

53. Will the Government be responsible for landing the power cables for the 400-ton chiller at the Building 47 power source? Yes

54. Is the Building 47 power source already outfitted with temporary camlock connections for two circuits? Our proposed 400-ton unit uses Series 16 cam-type power connections only. Building 47 power source is outfitted with temporary camlock connection for 1 circuit

55. Is any modification to the Building 47 power source needed to connect the temporary cabling? If so, who is responsible for that work? No

56. Will the awarded contractor be responsible for modifying the pre-existing water connections at Building 47 to make them suitable for the 400-ton temporary chiller? No

57. Is the awarded contractor responsible for providing glycol for the 400-ton chiller at Building 47? If so, what glycol type and percentage (concentration) is required, and how many gallons does the facility's chilled-water loop serving Building 47 hold? No

58. Is the awarded contractor responsible for providing water treatment for the 400-ton chiller at Building 47? No

59. Will the awarded contractor be responsible for any wall penetrations needed to route the chilled-water piping or electrical connections for the 400-ton chiller into Building 47? If the piping and electrical connections must instead pass through a doorway, will the awarded contractor be responsible for sealing the doorway (for example, with plywood) for the rental term? No

60. Can the 400-ton temporary chiller remain on a flatbed trailer at Building 47 throughout the rental term, or must it be offloaded by crane? Are there any pad, weight, clearance, or access-route restrictions at that location? Our proposed 400-ton unit is approximately 39 ft 2 in. long by 8 ft 6 in. wide by 8 ft high, with a shipping weight of 35,800 lb and an operating weight of 37,974 lb. It is delivered on a 48-ft trailer and is lifted by forklift or crane. It may remain on a trailer. There are no access restrictions, if lifted by crane, a crane lift permit will need to be provided.

B.3 STATEMENT OF WORK (SOW)

This PWS details the requirements for the rental of two air-cooled chillers for one year at the Charles George VA Medical Center (CGVAMC). The contract is necessary due to the current disrepair of the cooling system in Building 15 and the decommissioning of Chiller #2, which serves much of the main facility. Temporary chillers will provide essential cooling services while permanent repairs and replacements are planned and executed.

1. Background Building 15’s cooling system is no longer functional, requiring a temporary air-cooled chiller to maintain appropriate temperatures during the repair process. Simultaneously, Chiller #2, which supplies chilled water to the main hospital, has been decommissioned and is being replaced. To ensure continuity of service and patient comfort, a second temporary air-cooled chiller is needed until the new system is operational.

2. Scope of Work The contractor will be responsible for providing uninterrupted cooling services using temporary chillers in Building 15 and Building 47. The contractor must ensure the chillers remain fully operational, maintaining required temperature levels throughout the facility, and perform regular maintenance and inspections to guarantee optimal performance and energy efficiency.

Provide uninterrupted cooling services to Building 15 and Building 47 using the temporary chiller. Ensure the temporary chillers remain fully operational and effectively maintain the required temperature levels within the facility. Perform regular maintenance and inspections of the temporary chillers to ensure optimal performance and energy efficiency.

3. Deliverables The contractor shall deliver consistent cooling services to Building 15 and Building 47 throughout the contract period. Monthly maintenance reports detailing the condition and performance of the temporary chillers must be submitted. Any issues or malfunctions must be reported and resolved immediately to prevent disruptions to cooling services. Consistent cooling services to Building 15 and Building 47 throughout the contract period. Monthly maintenance reports detailing the condition and performance of the temporary chillers. Immediate reporting and resolution of any issues or malfunctions to avoid disruption of cooling services.

4. Responsibilities of the Contractor The contractor must install the temporary chillers safely, adhering to manufacturer specifications. Routine maintenance, including checking and replenishing coolant levels, inspecting mechanical components, and verifying electrical systems, should be conducted. Operational issues or breakdowns must be addressed promptly to minimize downtime. The contractor is responsible for ensuring compliance with all relevant safety and environmental regulations. Ensure temporary chiller is installed and operated safely according to manufacturer specifications. Conduct routine maintenance, including coolant checks, mechanical inspections, and electrical verification. Promptly address operational issues or breakdowns to minimize downtime. Ensure compliance with all relevant safety and environmental regulations.

5. Responsibilities of the Government The government will provide the contractor with access to Building 15 and Building 47, as well as necessary utilities for operation and maintenance. The government will inform the contractor of any changes or updates regarding the repair timeline for the existing cooling system and facilitate coordination with building personnel to ensure seamless service delivery. Provide access to Building 15 and Building 47 and necessary utilities. Inform contractor of updates to the repair timeline for the existing cooling system. Facilitate coordination between contractor and building personnel for seamless service delivery. Government will be responsible for providing power and chilled water supply and return to the units. Government will be responsible for connection of temporary electrical conductors and chilled water line to the facility infrastructure.

6. Security and Safety Requirements The contractor must comply with all applicable security protocols and safety regulations while performing duties, including proper handling and disposal of refrigerants and hazardous materials.

7. Quality Assurance The government will conduct regular inspections and monitoring of the temporary chillers to ensure contract compliance. Any deficiencies will be communicated to the contractor for immediate corrective action.

8. Acceptance Criteria The extension will be considered successful if the temporary chillers provide reliable cooling to Building 15 without significant interruptions or performance issues throughout the contract period.

9. Tobacco Usage Policy This is a federal facility and a medical center. Tobacco usage is not allowed inside any federal building or on the grounds except in designated areas. The Contracting Officer’s Representative (COR) will brief the contractor on designated smoking areas before the contract begins. Failure to comply may result in removal from the facility and/or legal penalties.

10. Compliance Awareness and Duty to Report Vendor compliance awareness training must be completed prior to access to the facility. The vendor is responsible for reporting any witnessed fraud, waste, or abuse to the Compliance Officer while on VA premises.

A.1 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (NOV 2022)

(a) Pursuant to 38 U.S.C. 8127(k)(2), the offeror certifies that—

(1) If awarded a contract (see FAR 2.101 definition), it will comply with the limitations on subcontracting requirement as provided in the solicitation and the resultant contract, as follows:

(i) [] Services. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219–73 or VOSBs as set forth in 852.219–74. Any work that a similarly situated VIP-listed subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6.

(ii) [] General construction. In the case of a contract for general construction, the contractor will not pay more than 85% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219–73or VOSBs as set forth in 852.219–74. Any work that a similarly situated VIP-listed subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(iii) [] Special trade construction contractors. In the case of a contract for special trade contractors, the contractor will not pay more than 75% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219–73 or VOSBs as set forth in 852.219–74. Any work that a similarly situated subcontractor further subcontracts will count towards the 75% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(2) The offeror acknowledges that this certification concerns a matter within the jurisdiction of an Agency of the United States. The offeror further acknowledges that this certification is subject to Title 18, United States Code, Section 1001, and, as such, a false, fictitious, or fraudulent certification may render the offeror subject to criminal, civil, or administrative penalties, including prosecution.

(3) If VA determines that an SDVOSB/ VOSB awarded a contract pursuant to 38 U.S.C. 8127 did not act in good faith, such SDVOSB/VOSB shall be subject to any or all of the following:

(i) Referral to the VA Suspension and Debarment Committee;

(ii) A fine under section 16(g)(1) of the Small Business Act (15 U.S.C. 645(g)(1)); and

(iii) Prosecution for violating section 1001 of title 18.

(b) The offeror represents and understands that by submission of its offer and award of a contract it may be required to provide copies of documents or records to VA that VA may review to determine whether the offeror complied with the limitations on subcontracting requirement specified in the contract. Contracting officers may, at their discretion, require the contractor to demonstrate its compliance with the limitations on subcontracting at any time during performance and upon completion of a contract if the information regarding such compliance is not already available to the contracting officer. Evidence of compliance includes, but is not limited to, invoices, copies of subcontracts, or a list of the value of tasks performed.

(c) The offeror further agrees to cooperate fully and make available any documents or records as may be required to enable VA to determine compliance with the limitations on subcontracting requirement. The offeror understands that failure to provide documents as requested by VA may result in remedial action as the Government deems appropriate.

(d) Offeror completed certification/fill-in required. The formal certification must be completed, signed and returned with the offeror’s bid, quotation, or proposal. The Government will not consider offers for award from offerors that do not provide the certification, and all such responses will be deemed ineligible for evaluation and award.

Certification I hereby certify that if awarded the contract, [insert name of offeror] will comply with the limitations on subcontracting specified in this clause and in the resultant contract. I further certify that I am authorized to execute this certification on behalf of [insert name of offeror].

Printed Name of Signee: ___________ Printed Title of Signee: _____________ Signature: ____________ Date: ______________ Company Name and Address: _______________ (End of Clause) See attached document: 100 Ton chiller.

See attached document: 100 Ton mechanical.

See attached document: 100 Ton step-up xfmr.

See attached document: 400 ton breaker 800 A.

See attached document: 400 ton chilled water return.

See attached document: 400 ton chilled water supply.

See attached document: 400 Ton chiller.

See attached document: 400 ton electrical.

See attached document: Site Map.

Chiller Rental