This is an Amendment to Solicitation document (SF 30) issued by the Department of Veterans Affairs, Network Contracting Office 6 for solicitation 36C24626Q0955, titled "652 Access Control System for B514 Polytrauma." The amendment was issued on September 3, 2026, and provides responses to 29 Requests for Information (RFIs) received prior to the submission deadline. The solicitation pertains to installation of an access control system at Building 514, a Polytrauma medical facility at the Richmond VA Medical Center, which was constructed in the 1990s and contains approximately 20,286 square feet.

The amendment clarifies that site visit attendance is mandatory for offerors seeking competitive consideration, as many detailed facility specifications—including dropped ceiling configurations, wall types, cable routing requirements, door frame construction, existing infrastructure conditions, and equipment quantities—require on-site verification rather than remote assessment. The Government does not provide as-built drawings, equipment specifications, or guarantee existing infrastructure availability; contractors are responsible for field verification and determining necessary materials, quantities, and installation methodologies in compliance with applicable building codes and safety requirements. Key terms include that the project is non-severable with payment due upon work completion, not progress payments; after-hours access requires Government escort due to the active medical facility status; equipment substitutions are permitted provided they comply with the Buy American Act and Trade Agreements Act; and no predetermined budget magnitude is provided as the work falls under NAICS code 561621 (service classification). The site visit was held on Monday, August 24, 2026, and the offer due date remains unchanged by this amendment.

View the file

Other files for this federal contract opportunity

Other files attached to J063--ACCESS CONTROL SYSTEM FOR B514, newest first.
File Type Posted
36C24626Q0955.docx DOCX document
ATTACHMENT A - SCA WD 2015-4313 Rev 35 20260811.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 5

0001 09-03-2026

Department of Veterans Affairs

Network Contracting Office 6

100 Emancipation Drive

Hampton VA 23667

Department of Veterans Affairs

Network Contracting Office 6

100 Emancipation Drive

Hampton VA 23667

To all Offerors/Bidders

36C24626Q0955

08-18-2026

X

X X

The purpose of this amendment is to provide responses to all questions received prior to the due date and time for submission of questions regarding the solicitation. See page 2 of this amendment and subsequent pages.

Daniel Spaulding

Contracting Officer, NCO 6

SOLICITATION 36C24626Q0955

652 Access Control System for B514 Polytrauma RFIs/Questions

1. How old is the facility?

RESPONSE: The Richmond VAMC opened in 1946. Building 514, the place of performance, appears to have been constructed sometime in the 1990s.

2. How much square footage is in the facility?

RESPONSE: The estimated total square footage of the facility is 20,286 sq. ft.

3. How stable is the power?

RESPONSE: The place of performance is a Polytrauma medical facility. Assume that the power is stable.

4. Is there a dropped ceiling in all areas of installation?

RESPONSE: Companies providing this service customarily would investigate the customer’s location to review this type of information, rather than attempt to submit a quote for work to be performed on a site that the offeror has not seen. The RFI process is not intended to be used as a substitute to site visit attendance for remote offerors attempting to submit a quote. Competitive quotes are anticipated with the current solicitation and site visit attendance.

5. What type of walls are in the perimeter areas?

RESPONSE: Companies providing this service customarily would investigate the customer’s location to review this type of information, rather than attempt to submit a quote for work to be performed on a site that the offeror has never seen. A site visit was held where this information would have been confirmed. The RFI process is not intended to be a substitute for attendance of a site visit for remote companies wanting to submit a quote.

Competitive quotes are anticipated with the current solicitation and site visit attendance.

6. Do we need to drill between the walls, to run our cable infrastructure?

RESPONSE: Companies providing this service customarily would investigate the customer’s location to review this type of information, rather than attempt to submit a quote for work to be performed on a site that the offeror has never seen. A site visit was held where this information would have been confirmed. The RFI process is not intended to be a substitute to attendance of a site visit for remote companies wanting to submit a quote.

Competitive quotes are anticipated with the current solicitation and site visit attendance.

7. Do we need to use conduit? If yes, what do you estimate the total conduit footage will be?

RESPONSE: The answer to the question depends on normal industry practice, as well as consideration for building codes/safety issues and practical matters such as the ability to service the system after installation. A site visit was held for offerors to make determinations regarding material/labor estimating. The RFI process is not intended as a substitute for remote offerors attempting to submit a quote for work at locations that they have not seen.

Competitive quotes are anticipated with the current solicitation and site visit attendance.

8. Are the door frames metal and concrete filled?

RESPONSE: The answer to this question may vary in different areas. A site visit was held for offerors to make determinations regarding material/labor estimating.

9. Please provide a comprehensive list of quantities of all IDS items needed (e.g. total number of motion sensors, glass breaks, etc.) per location.

RESPONSE: The statement of work of the solicitation provides the scope of work. A site visit was held for offerors to make determinations regarding material/labor estimating. The RFI process is not intended as a substitute for remote offerors attempting to submit a quote for work at locations that they have not seen.

10. Do you currently have existing IDS Sensors in your doors? Please specify which doors.

RESPONSE: The Government was unable to locate as-built drawings specifically identifying existing IDS device locations. Contractor shall field verify existing conditions. A site visit was already held and competitive offers are anticipated.

11. What is the manufacturer of the existing IDS system?

RESPONSE: The Government was unable to identify the existing IDS manufacturer from the available Building 514 record drawings, submittals, and project closeout documentation.

Contractor shall field verify existing conditions. A site visit was already held and competitive offers are anticipated.

12. Will we be able to reuse the existing cable? If so, what type of cable is there currently?

RESPONSE: Offerors should review the solution they intend to quote and the existing system stated in the Statement of Work. Reuse of existing wiring would be based on whether existing wiring is suitable for the system/components being installed, common industry practice and building code/safety requirements. A site visit was held for offerors to make determinations regarding material/labor estimating. The RFI process is not intended as a substitute for remote offerors attempting to submit a quote for work at locations that they have not seen. Competitive quotes are anticipated with the current solicitation and site visit attendance.

13. Are Ceilings Suspended? Or Hard Lid?

RESPONSE: Ceiling construction varies by location. Offerors shall verify existing field conditions. A site visit was provided for this purpose.

14. Are there existing Cable Trays for wiring above ceilings?

RESPONSE: The Government does not guarantee the availability or suitability of existing cable tray for the proposed installation. Offerors shall verify existing field conditions and include the pathway required to complete the work in accordance with the solicitation and applicable codes.

15. Can Existing Wiring be utilized?

RESPONSE: Offerors should review the solution they intend to quote and the existing system stated in the Statement of Work. Reuse of existing wiring would be based on whether existing wiring is suitable for the system, common industry practice and building code/safety requirements.

16. Is a “UPS” required? If so, What Time/Power Duration is required?

RESPONSE: Offerors shall provide all equipment necessary to meet the requirements of the solicitation and ensure no impact to facility operations. In the event a portion of the work may affect facility operation, the work and any necessary outages must be coordinated with the facility and approved by the Contracting Officer and/or Contracting Officer’s Representative.

17. Are “Or Equal” Equipment substitutions allowed?

RESPONSE: There are no brand name-only requirements for this action. However, the Buy American Act and Trade Agreements Act applies. See RFO FAR clause 52.225-5 and RFO FAR provision 52.225-6 included in the solicitation.

18. Is “Plenum Wire” acceptable?

RESPONSE: The Government will not authorize the use of inferior substitute materials in a general “blanket” statement responding to RFIs. Offerors should utilize the materials appropriate for the installation based on building code, power requirements and other needs specific to the work being performed. Plenum wire may be appropriate in some aspects of the work, and inappropriate for other parts of the installation. An offeror suitably experienced with this type of work would likely already be aware of the answer to this question.

19. Is “After Hours Access” for said work, available to contractor at no add’l cost to the

Gov’t?

RESPONSE: The Contractor needs to be escorted by Government personnel at all times due to the location being an active medical facility. This may be a limiting factor on the availability of ‘after hours access’.

20. What is the height of Exterior Cameras? (If any)

RESPONSE: A site visit was held for offerors to make determinations regarding material/labor estimating. The RFI process is not intended as a substitute for remote offerors attempting to submit a quote for work at locations that they have not seen.

Competitive quotes are anticipated with the current solicitation and site visit attendance.

21. Please provide/post other “Q & A” requests.

RESPONSE: Provided.

22. Please provide a list of equipment and parts # that are to be installed.

RESPONSE: The statement of work establishes the required system and performance requirements. It is the offeror's responsibility to determine and provide the equipment, materials, quantities, and part numbers necessary to furnish a complete and functional installation in accordance with the solicitation.

23. Are there pipe chases between floors?

RESPONSE: The Government does not guarantee the availability of pipe chases for this work. Offerors shall verify existing field conditions and include the pathways necessary to complete the installation in accordance with the solicitation and applicable codes.

24. What is the range of the budget for this project, and is it already appropriated?

RESPONSE: There is no magnitude of construction provided for this project as the scope of work falls under NAICS code 561621, which is a service NAICS code.

25. Because of the high cost of the parts can we bill when parts arrive on site, or in the alternative are progress payments allowed?

RESPONSE: The project is non-severable. Payment will be made upon completion of work.

26. How many feet of new wire will have to be run?

RESPONSE: Companies providing this service customarily would investigate the customer’s location to review this type of information, rather than attempt to submit a quote for work to be performed on a site that the offeror has never seen. A site visit was held where this information could have been estimated. Competitive offers are anticipated with the current solicitation and site visit attendance.

27. What kind of cipher lock and quantities are required e.g. X-10

RESPONSE: The statement of work establishes the access-control requirements. Offerors shall determine and provide the lock type, equipment, and quantities necessary to meet those requirements. No X-10 lock requirement is established by this RFI response unless specifically identified elsewhere in the solicitation.

28. Please post the sign in sheet and Q&A's from the site visit.

RESPONSE: All information that is required to be disclosed will be disclosed. The RFI process is not intended as a substitute for remote offerors attempting to submit a quote for work at locations that they have not seen. The site visit attendance sheet is provided with this Amendment 0001.

29. Please post the drawings and the key for the drawings.

RESPONSE: There are no drawings for this project.

See SF30 Amendment 36C24626Q0955 0001. This amendment provides responses to all RFIs received prior to the due date and time for submission of questions regarding the solicitation.

The due date for offers is unchanged by this amendment. A site visit was already held on Monday, August 24, 2026 in accordance with the solicitation.