This document contains the results of a vertical transportation onsite survey conducted at a VA Medical Center. The survey assessed twenty units across nine buildings, including ten traction elevators, eight hydraulic elevators, and two service cart lifts. Seventeen of the units were found to be in poor condition and past their useful life, requiring modernization of major components at an estimated total cost of $3.9 to $3.95 million. Modernization of all seventeen units is projected to take approximately two and a half years to complete.

The related federal contract opportunity is a solicitation from the Department of Veterans Affairs to upgrade elevators in Phase II of a project. The solicitation number is 36C24623B0032_1 and corresponds to project number 658-22-103 under the Veterans Health Administration VISN 6.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Vertical Transportation Survey

312.519.9949 www.theelevatorconsultants.com http://www.theelevatorconsultants.com/

VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com

The Elevator Consultants conducted a vertical transportation onsite survey at the VA Medical

Center located at 1970 Roanoke Blvd in Salem, VA on October 1, 2018. The onsite survey was performed at nine (9) buildings which consisted of twenty (20) units; ten (10) traction elevators, eight (8) hydraulic elevators and two (2) service cart lifts. The vertical transportation onsite survey includes a review of the equipment type and condition, an estimated cost to replace the systems and a potential schedule to replace the systems.

Building 1

There is one (1) hydraulic elevator located in Building 1 that has a capacity of 4,000 pounds, travels at a speed of 125 feet per minute and serves 3 landings. The elevator uses a Dover controller, Dover dry hydraulic pump unit assembly, Dover in-ground jack unit assembly, Dover door operation system, slide guide assemblies, spring buffers and cab fixtures that are all original from 1976. Overall, the equipment is in poor condition and is operating beyond its useful life expectancy. The condition of the hydraulic jack unit assembly is unknown because the jack unit is in the ground. The major components; controllers, machine, pump units, door operating equipment, guide assemblies, safety equipment, hall and car fixtures and a safety buffer will be replaced except for the hydraulic jack unit assembly which will be reused during the modernization. An estimated budget of $150K should be planned to modernize the elevator.

This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code. The modernization will take an estimated 4 – 6 weeks from the time material is onsite.

Original Dover controller

VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com

Building 2

There are two (2) hydraulic elevators located in Building 2. The elevators have a capacity of 4,000 pounds, travel at a speed of 100 feet per minute and serves 4 landings. The elevators use Virginia control systems, dry hydraulic pump unit assemblies, GAL door operators and cab fixtures that were installed during the 1995 modernization. The elevators use original slide guide assemblies, spring buffers and in-ground jack unit assemblies. All equipment is in poor condition. The condition of the hydraulic jack unit assembly is unknown because the jack unit is in the ground.

The major components; controllers, machine, pump units, door operating equipment, guide assemblies, safety equipment, hall and car fixtures and a safety buffer will be replaced except for the hydraulic jack unit assembly which will be reused during the modernization. An estimated budget of $150K per elevator for a total of $300K should be planned to modernize both elevators.

This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code. The modernization of both elevators will take an estimated

4 – 6 weeks to modernize after material is on site.

Pump Unit Assembly

VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com

Building 2A

There is a total of two (2) traction elevators located at Building 2A. The elevators have a capacity of 4,000 pounds, travel at a speed of 300 feet per minute and serve 4 landings. The elevators use

Dover Composite controllers, Dover geared traction machines and Dover door operators. All equipment, including the governors, roller guide assemblies, oil buffers and cab fixtures are all original from 1977. The equipment is in poor condition and operating beyond its useful life. The major components such as the controllers, machines, governors, slide guides, safety equipment, door operating equipment, cables, hall fixtures and cab fixtures will be replaced during the modernization. An estimated budget of $250K per elevator for a total of $500K should be planned to modernize both elevators. This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code. The modernization will take an estimated 10 - 12 weeks each to complete after material is on site.

VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com

Building 4

There is a total of two (2) elevators located at Building 4; Traction Elevator F1 and hydraulic

Elevator #1. The traction Elevator F1 has a capacity of 2,500 pounds, travels at a at an estimated speed of 200 feet per minute and serves 2 landings. The Elevator 1 uses a Westbrook control system, a Westbrook geared machine, and a PEELE door operation system. All equipment, including the governor, slide guide assemblies, spring buffers and cab fixtures are original from

1966. The equipment is in poor condition and operating beyond its useful life. The major components like the controller, machine, governor, slide guides, safety equipment, door operating equipment, cables, hall fixtures and cab fixtures will be replaced during the modernization. An estimated budget of $250K should be planned to modernize the elevator.

This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code. The modernization will take an estimated 12 – 16 weeks from the time material is onsite.

The hydraulic Elevator #1 was recently modernized in 2010 and is in good condition. The elevator uses a ThyssenKrupp TAC22 controller, a ThyssenKrupp dry hydraulic pump unit, new fixtures and a ThyssenKrupp door operator. All the equipment is newly modernized from 2010. The major components have estimated useful life of 12 – 17 years left with the proper level of maintenance and parts support from the manufacturer.

Original Westbrook geared machine

VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com

Building 5

There is one (1) hydraulic elevator located in Building 5 that has a capacity of 4,000 pounds, travels at a speed of 125 feet per minute and serves 3 landings. The elevator uses a Dover controller, Dover dry hydraulic pump unit assembly, Dover in-ground jack unit assembly, Dover door operation system, slide guide assemblies, spring buffers and cab fixtures that are all original from 1973. Overall, the equipment is in poor condition and is operating beyond its useful life expectancy. The condition of the hydraulic jack unit assembly is unknown because the jack unit is in the ground. The major components; controllers, machine, pump units, door operating equipment, guide assemblies, safety equipment, hall and car fixtures and a safety buffer will be replaced except for the hydraulic jack unit assembly which will be reused during the modernization. An estimated budget of $150K should be planned to modernize the elevator.

This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code. The modernization will take an estimated 4 – 6 weeks from the time material is onsite.

VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com

Buildings 10 & 11

There is one (1) hydraulic elevator located in Building 10 and one (1) hydraulic elevator located in Building 11. The elevators have a capacity of 4,000 pounds, travel at a speed of 125 feet per minute and serves 3 landings. The elevators use Dover controllers, Dover dry hydraulic pump unit assemblies, Dover in-ground jack unit assemblies, Dover door operation systems, slide guide assemblies, spring buffers and cab fixtures that are all original from 1985. Overall, the equipment at both buildings is in poor condition and are operating beyond the useful life expectancy. The condition of the hydraulic jack unit assembly is unknown because the jack unit is in the ground.

The major components; controllers, machines, pump units, door operating equipment, guide assemblies, safety equipment, hall and car fixtures and safety buffers will be replaced except for the hydraulic jack unit assembly which will be reused during the modernization. An estimated budget of $150K should be planned to modernize each elevator for a total of $300K. This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code. The modernization will take an estimated 4 –6 weeks per elevator from the time material is onsite.

Original Dover controller at both buildings

VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com

Building 76

There is a total of one (1) traction elevator located at Building 76 that has a capacity of 4,000 pounds, travels at a speed of 200 feet per minute and serves 3 landings. The elevator uses a

Dover control system from the 1960’s and a Salem Foundry geared machine from 1936. The slide guide assemblies and spring buffers are from 1936. The fixtures and the door operating equipment are from 1983. The equipment is in poor condition and operating beyond its useful life. The major components like the controller, machine, governor, slide guides, safety equipment, door operating equipment, cables, hall fixtures and cab fixtures will be replaced during the modernization. An estimated budget of $250K should be planned to modernize the elevator. This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code. The modernization will take an estimated 10 – 12 weeks from the time material is onsite.

Original 1936 Salem Foundry geared machine

VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com

Building 143

There are a total of six (6) traction elevators, one (1) hydraulic elevator and two (2) cart lifts located at Building 143. The traction elevators are Elevators P1, P2, P3, S1, S2 and S3. The traction Elevators P1 – P3 have a capacity of 4,000 pounds, travel at a speed of 350 feet per minute and serve 5 landings. The traction elevators S1 – S3 have a capacity of 5,000 pounds, travel at a speed of 350 feet per minute and serve 5 landings. The hydraulic elevator is Elevator

S4 that has a capacity of 5,000 pounds, travels at a speed of 125 feet per minute and serves 3 landings. The cart lifts are SCL 1 and SCL 2. The two (2) cart lifts have a capacity of 1,000 pounds, travel at an estimated speed of 50 feet per minute and serve 2 landings.

All six (6) traction elevators use Dover control systems, Dover geared traction machines and

Dover door operators. All equipment, including the governors, roller guide assemblies, oil buffers and cab fixtures are original from 1970. The equipment is in poor condition and operating beyond its useful life. The major components such as the controllers, machines, governors, slide guides, safety equipment, door operating equipment, cables, hall fixtures and cab fixtures will be replaced during the modernization. An estimated budget of $250K should be planned to modernize each elevator for a total of $1.5M. This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code. The modernization will take an estimated 12 – 16 weeks per elevator from the time material is onsite, completing one elevator per bank at a time.

Original Salem Foundry geared machine

The hydraulic elevator uses a Dover control system, a Dover dry hydraulic pump unit assembly, a

Dover in-ground jack unit assembly, a Dover door operation system, slide guide assemblies, VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com spring buffers and cab fixtures that are all original from 1989. Overall, the equipment is in poor condition and is operating beyond its useful life expectancy. The condition of the hydraulic jack unit assembly is unknown because the jack unit is in the ground. The major components;

controller, machines, pump unit, door operating equipment, guide assemblies, safety equipment, hall and car fixtures and safety buffers will be replaced except for the hydraulic jack unit assembly which will be reused during the modernization. An estimated budget of $150K should be planned to modernize the elevator. This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code. The modernization will take an estimated 4 – 6 weeks for the elevator from the time material is onsite.

The two (2) cart lifts use Dover control systems, dover machines and PEELE door operators that are original from 1990. The cart lifts are in poor condition and are past their projected life cycle.

The modernization of each lift will take one month for each unit and a projected cost of $175K to $200K each for a total of $350K to $400K for both. This budget does not include non-elevator work such as electrical, fire life safety, hoistway patching, etc. to meet current code

VAMC 1970 Roanoke Blvd | Vertical Transportation Onsite Survey October 1, 2018

©2018 The Elevator Consultants | Confidential and Proprietary. This document is exclusive property of The Elevator Consultants and no part of this may be reproduced or shared in any format without prior written permission. | www.theelevatorconsultants.com

Original PEELE door controller

Overall

Overall, the twenty (20) units surveyed, the overall condition of seventeen (19) of the units were rated as poor and due for modernization based on the use, age of the equipment, parts availability and engineering. An estimated cost of $3.9M to $3.95M should be budgeted to modernize the seventeen (17) elevators and two (2) cart lifts and does not include non-elevator work. It is recommended that quotes be received for all of the non-elevator work (electrical, fire life safety and hoistway patching) so a full budget can be planned attained. The schedule for modernization with 2 crews will take an estimated two and a half (2 1/2) years from the time material arrives on site until the last elevator is completed.