36C24623B0027.docx
DOCX document 178 KB Posted
- Solicitation number
- 36C24623B0027
About this file
This solicitation seeks proposals for a construction project to tuck point, caulk, and seal various buildings at the Hampton VA Medical Center. Key details include:
-
The project scope involves general construction work including masonry cleaning, tuck pointing, crack sealing, brick replacement, window sill repairs, caulking, and stone resurfacing at five buildings on site.
-
The period of performance is 455 calendar days from notice to proceed. An alternate line item proposes reducing this to 395 days by excluding work on one building.
-
The procurement is fully set aside for Service-Disabled Veteran-Owned Small Businesses.
-
Proposals are due by April 20, 2023. A pre-bid conference will be held on March 15 and questions are due by April 2.
-
The estimated value ranges from $1-2 million. Pricing is fixed-firm for line items covering the base scope and alternate deductive scope.
-
The Department of Veterans Affairs is the contracting agency. Work will be performed at the Hampton VA Medical Center campus in Hampton, Virginia.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Hampton Tuckpoint Forensic Investigative Report.pdf | ||
| 36C24623B0027 0004.docx | DOCX document | |
| 36C24623B0027 0003.docx | DOCX document | |
| Questions and Answers Project 590-19-114 Tuck Point Caulk and Seal.pdf | ||
| 36C24623B0027 0001.docx | DOCX document | |
| ATTENDANCE PRE BID SITE VISIT 03152023 Tuck Point Caulk and Seal.pdf | ||
| 36C24623B0027 0002.docx | DOCX document | |
| 590-19-114 Project Specs- Bid Set.pdf | ||
| 590-19-114 Service Contract Act WD 2015-4341.pdf | ||
| 590-19-114 Hampton Tuck Point Project Drawings (1).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5.
REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL
SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24623B0027 X 03-10-2023 N/A 590-19-114 36C246 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 Tonya Bradley (757) 722-9961 Ext. 8807 INVITATION FOR BID: Project No.: 590-19-114 – “Tuck Point, Caulk and Seal Various Buildings”
** This is a 100% set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) **
Contract Type: Firm-Fixed Price
Magnitude of constru ction for this project between $1,000,000 and $2,000,000 IAW VAAR 36.204(f)(1).
North American Industry Classification System (NAICS) Code: 236220, Commercial and Institutional Building Construction.
Size standard of $39.5 Million and Geographical Location of work to be performed: Hampton, VA
Site Visit: March 15,2023 at 10:00AM.
Questions/requests for information due 12:00PM EST on April 2,20 23; Email: guy.brooks@va.gov and tonya.bradley@va.gov
Bids Due: April 20, 2023 9:00 AM EST. Bids must be emailed only to: tonya.bradley@va.gov and guy.brooks@va.gov.
Virtual Bid Opening: April 20, 2023 9:00 AM EST, Microsoft Teams invite will be sent to all responsive bidders.
Bid Bonds required at time of bid opening. Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid per FAR 52.228-1(a).
Payment and Performance Bonds are required NLT 15 calendar days from award notice.
Bid Item(s): See Line Item 0001 and Line Item 0002 under Section A.3 PRICE/COST SCHEDULE.
X X 52.211-10 X
9AM
EDT
04-20-2023 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMEN
DMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND
TITLE OF CONTRACTOR OR PERSON AUTHORIZED
31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or pr int) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C246 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 Department of Veterans Affairs Financial Services Center
PO BOX 149971
Austin TX 78714-9971 512-460-5049 512-460-5221 Guy K. Brooks Contracting Officer
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.3 PRICE/COST SCHEDULE | 6 |
| ITEM INFORMATION | 6 |
| A.4 DELIVERY SCHEDULE | 7 |
| A.5 PERFORMANCE WORK STATEMENT | 7 |
| A.6 WAGE DETERMINATION | 8 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 15 |
| 2.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 24 |
| 2.2 52.216-1 TYPE OF CONTRACT (APR 1984) | 25 |
| 2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 25 |
| 2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 26 |
| 2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 27 |
| 2.6 52.225-22 NOTICE OF REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED GOODS—BUY AMERICAN STATUTE—CONSTRUCTION MATERIALS (JAN 2021) ALTERNATE I (JAN 2021) | 28 |
| 2.7 52.225-24 NOTICE OF REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED GOODS—BUY AMERICAN STATUTE—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (JAN 2021) | 29 |
| 2.8 52.228-1 BID GUARANTEE (SEP 1996) | 30 |
| 2.9 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 31 |
| 2.10 52.233-2 SERVICE OF PROTEST (SEP 2006) | 31 |
| 2.11 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 32 |
| 2.12 52.246-26 REPORTING NONCONFORMING ITEMS (NOV 2021) | 32 |
| 2.13 VAAR 852.209-70 ORGANIZATIONAL CONFLICTS OF INTEREST (OCT 2020) | 35 |
| 2.14 VAAR 852.214-73 ALTERNATE PACKAGING AND PACKING (MAY 2018) | 36 |
| 2.15 VAAR 852.214-74 MARKING OF BID SAMPLES (MAY 2018) | 36 |
| 2.16 VAAR 852.223-70 INSTRUCTIONS TO OFFERORS—SUSTAINABLE ACQUISITION PLAN (SEP 2019) | 36 |
| 2.17 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 36 |
| 2.18 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 37 |
| 2.19 VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019) | 37 |
| REPRESENTATIONS AND CERTIFICATIONS | 39 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEC 2022) | 39 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 43 |
| 3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 45 |
| 3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 47 |
| 3.5 52.229-11 TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND REPRESENTATION (JUN 2020) | 49 |
| GENERAL CONDITIONS | 51 |
| 4.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 51 |
| 4.2 SUPPLEMENTAL INSURANCE REQUIREMENTS | 54 |
| 4.3 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021) | 54 |
| 4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 56 |
| 4.5 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022) | 56 |
| 4.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (OCT 2022) | 58 |
| 4.7 VAAR 852.219-73 VA Notice of total set-aside for verified service-disabled veteran-owned small businessES (NOV 2022) (NOV 2022) | 61 |
| 4.8 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (NOV 2022) | 66 |
| 4.9 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014) | 68 |
| 4.10 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008) | 68 |
| 4.11 52.223-21 FOAMS (JUN 2016) | 69 |
| 4.12 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (OCT 2021) (DEVIATION) | 70 |
| 4.13 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 70 |
| 4.14 52.225-23 REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED GOODS—BUY AMERICAN STATUTE—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (JAN 2021) (JUL 2020) (DEVIATION) | 75 |
| 4.15 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020) | 80 |
| 4.16 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022) | 80 |
| 4.17 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 81 |
| 4.18 VAAR 852.204-71 Information and Information Systems Security (FEB 2023) | 81 |
| 4.19 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 89 |
| 4.20 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR VERIFIED SERVICE-DISABLED VETERAN OWNED SMALL BUSINESSES (NOV 2022) | 90 |
| 4.21 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 93 |
| 4.22 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 93 |
| 4.23 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS–CPM) (NOV 2018) (ALTERNATE I) | 93 |
| 4.24 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 96 |
| 4.25 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 97 |
| 4.26 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019) ALTERNATE I (APR 2019) | 98 |
| 4.27 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 99 |
| 4.28 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) ALTERNATE I (APR 2019) | 99 |
| 4.29 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 100 |
| 4.30 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 102 |
| 4.31 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 102 |
| 4.32 VAAR 852.246-75 WARRANTY OF CONSTRUCTION—GUARANTEE PERIOD SERVICES (OCT 2018) | 103 |
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 0.00 |
| JB |
| _____________ |
| ______________ |
This is a new requirement and being procured in accordance with Federal Acquisition Regulation (FAR) 36 and VA Acquisition Regulation (VAAR) 836 and VA Acquisition Manual (VAAM) 836 for the project to include general construction, clean all masonry, tuck point all masonry, seal cracks around door frames and windows, replace any damaged brick, remove non matching mortar full depth and repoint brick, repoint around 3 sides of all window sills, repair/refinish damaged window sills, caulk and seal transoms, reset window well bricks, remove concrete parging on brick, repair/replace half wall caps, replace steel corner guard angles on brick, install weep holes with reticulated baffles at 24” around building, sand and resurface limestone, and any other requirements of the specifications for Buildings 28, 31, 43, 48, and 114. Parking lots cannot be block or used as laydown areas for this project.
PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries UNSPSC: 72121403 - Hospital construction service
SIC CODE: 5039 - CONSTRUCTION MATERIALS, NEC
MANUFACTURER PART NUMBER (MPN): n/a NATIONAL STOCK NUMBER: n/a LOCAL STOCK NUMBER: n/a
| 0.00 |
| JB |
| _____________ |
| ______________ |
(DEDUCT NO.1): Complete all work associated with the base bid, except delete all work on building 114. Provide price and number of days to deduct work.
Period of Performance is 395 days PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries UNSPSC: 72121403 - Hospital construction service
SIC CODE: 5039 - CONSTRUCTION MATERIALS, NEC
MANUFACTURER PART NUMBER (MPN): n/a NATIONAL STOCK NUMBER: n/a LOCAL STOCK NUMBER: n/a
| GRAND TOTAL |
| ______________ |
A.4 DELIVERY SCHEDULE
| ITEM NUMBER |
| QUANTITY |
| DELIVERY DATE |
| 0001 |
| SHIP TO: |
| Department of Veterans Affairs |
Hampton VA Medical Center 100 Emancipation Drive Hampton, VA 23667 U.S.A.
| 0.00 |
| 455 Days from NTP |
| MARK FOR: |
| TBD |
| 0002 |
| SHIP TO: |
| Department of Veterans Affairs |
Hampton VA Medical Center 100 Emancipation Drive Hampton, VA 23667 U.S.A.
| 0.00 |
| 395 days from NTP |
| MARK FOR: |
| TBD |
A.5 PERFORMANCE WORK STATEMENT
Tuck Point, Caulk, and Seal Various Buildings 590-19-114
Scope; Provide construction services to tuck point, caulk, and seal various buildings, and all associated work involved as per attached specifications at Hampton, VA Veterans Affairs Center:
GENERAL CONSTRUCTION:
Work includes general construction, clean all masonry, tuck point all masonry, seal cracks around door frames and windows, replace any damaged brick, remove non matching mortar full depth and repoint brick, repoint around 3 sides of all window sills, repair/refinish damaged window sills, caulk and seal transoms, reset window well bricks, remove concrete parging on brick, repair/replace half wall caps, replace steel corner guard angles on brick, install weep holes with reticulated baffles at 24” around building, sand and resurface limestone, and any other requirements of the specifications for Buildings 28, 31, 43, 48, and 114. Parking lots cannot be block or used as laydown areas for this project.
Period of Performance is 455 calendar days.
(DEDUCT NO.1): Complete all work associated with the base bid, except delete all work on building 114. Provide price and number of days to deduct work.
Period of Performance is 395 days
Work Hours: This task can be conducted and accomplished during normal duty hours on (Monday-Friday 7:00 AM-4:30 PM). Work accomplished outside these hours must be approved by the POCs.
Recognized Holidays: Normal operational hours of the Hampton VA Medical Center are Monday through Friday, 7:00AM to 4:30PM except weekends and Federal Holidays (see list of holidays below).
Holiday
| Date |
| Month |
| New Year’s Day |
| 1st |
| January |
| Martin Luther King Jr.’s Birthday |
| 3rd Monday |
| January |
| President’s Day |
| 3rd Monday |
| February |
| Memorial Day |
| Last Monday |
| May |
| Juneteenth |
| 19th |
| June |
| Independence Day |
| 4th |
| July |
| Labor Day |
| 1st Monday |
| September |
| Columbus Day |
| 2nd Monday |
| October |
| Veterans Day |
| 11th |
| November |
| Thanksgiving Day |
| 4th Thursday |
| November |
| Christmas Day |
| 25th |
| December |
Table 1
A.6 WAGE DETERMINATION
"General Decision Number: VA20230022 01/13/2023 Superseded General Decision Number: VA20220022 State: Virginia Construction Type: Building County: Hampton* County in Virginia.
* INDEPENDENT CITY
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658. Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).
______________________________________________________________ |If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $16.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2023. | |______________________________|_____________________________| |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.15 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2023. | |______________________________|_____________________________| The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/06/2023 1 01/13/2023
ASBE0024-006 04/01/2021
Rates Fringes ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL (Duct, Pipe & Mechanical System Insulation)......................$ 39.27 18.67+a
a. PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day,the day after Thanksgiving and Christmas Day provided the employee works the regular work day before and after the paid holiday.
---------------------------------------------------------------- BOIL0045-003 01/01/2021 Rates Fringes BOILERMAKER......................$ 42.62 24.81 ---------------------------------------------------------------- BRVA0008-001 05/01/2022 Rates Fringes BRICKLAYER.......................$ 22.44 10.23 ---------------------------------------------------------------- ELEC1340-001 12/01/2022 Rates Fringes ELECTRICIAN (Includes Low Voltage Wiring and Alarm Installation)....................$ 31.30 8.5%+6.35 ---------------------------------------------------------------- * ELEV0052-005 01/01/2023 Rates Fringes ELEVATOR MECHANIC................$ 47.72 37.335+a+b
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the Friday after Thanksgiving Day and Christmas Day.
b. VACATIONS: 6% men under 5 years based on regular hourly rate and 8% men over 5 years based on regular hourly rate for all hours worked.
---------------------------------------------------------------- ENGI0147-019 05/01/2022 Rates Fringes POWER EQUIPMENT OPERATOR Cranes 90 tons & over capacity; Tower & Climbing Cranes with Controls 100 ft. above ground............$ 34.17 15.21 Cranes under 90 tons........$ 33.26 15.12 ---------------------------------------------------------------- IRON0079-012 05/01/2022 Rates Fringes IRONWORKER, STRUCTURAL AND ORNAMENTAL.......................$ 28.87 11%+14.24 ---------------------------------------------------------------- IRON0079-013 05/01/2022 Rates Fringes IRONWORKER, RIGGER...............$ 28.87 11%+14.24 ---------------------------------------------------------------- PLUM0110-008 11/01/2022 Rates Fringes PIPEFITTER (Includes HVAC Pipe, Unit and Temperature Controls Installations)..........$ 31.77 17.40 PLUMBER..........................$ 31.77 17.40 ---------------------------------------------------------------- * SUVA2013-037 01/11/2016 Rates Fringes CARPENTER, Includes Acoustical Ceiling Installation, Drywall Hanging, and Form Work...........$ 18.50 0.00
CAULKER..........................$ 18.49 1.33
CEMENT MASON/CONCRETE FINISHER...$ 17.48 0.00
GLAZIER..........................$ 19.36 4.68
IRONWORKER, REINFORCING..........$ 27.18 4.13
LABORER: Mason Tender - Brick...$ 13.48 ** 3.27 LABORER: Mason Tender - Cement/Concrete..................$ 12.96 ** 3.12 LABORER: Pipelayer..............$ 12.40 ** 1.96 LABORER: Common or General, Including Demolition.............$ 12.14 ** 1.60 OPERATOR: Backhoe/Excavator/Trackhoe.......$ 20.69 1.35 OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 18.95 4.03 OPERATOR: Bulldozer.............$ 18.07 3.50 OPERATOR: Forklift..............$ 19.40 7.00 OPERATOR: Loader................$ 21.28 3.17 OPERATOR: Roller................$ 16.25 4.88 PAINTER (Brush and Roller).......$ 16.87 0.00 PAINTER: Spray..................$ 18.10 5.43
ROOFER...........................$ 18.40 2.31
SHEET METAL WORKER, Includes HVAC Duct Installation...........$ 19.24 2.80 SPRINKLER FITTER (Fire Sprinklers)......................$ 18.91 4.67
TILE FINISHER....................$ 23.40 0.00
TILE SETTER......................$ 27.80 10.25
TRUCK DRIVER: Dump Truck........$ 15.50 ** 0.75 ---------------------------------------------------------------- WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($16.20) or 13658 ($12.15). Please see the Note at the top of the wage determination for more information.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination * a survey underlying a wage determination * a Wage and Hour Division letter setting forth a position on a wage determination matter * a conformance (additional classification and rate) ruling On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISIO"
Page 1 of Page 1 of
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
1. SUBMISSION OF BIDS:
The bidder shall submit the following in response to this Invitation for Bids:
(a) A completed and signed Standard Form 1442. Contractor must acknowledge all amendments in force at the time of the bid opening.
(b) A completed copy of the Representations and Certifications (See FAR 52.204-8 Annual Representations and Certifications (MAR 2012)).
(c) Compliant with VAAR 852.219-73 VA Notice of total set-aside for verified service-disabled veteran-owned small businesses (NOV 2022).
(d) Compliant with VAAR 852.219-75 VA Notice of Limitations on Subcontracting – Certificate of Compliance for Services and Construction (NOV 2022).
(e) A fully executed bid bond.
(f) Documentation of their safety record.
(g) Itemized Schedule of Values Cost breakdown.
o NOTE 1: Offerors must submit an itemized breakdown of costs (Attachment A) to include an Itemized Schedule of Values Cost breakdown for Base Bid and Alternative 1, in sufficient detail to permit a complete analysis of labor burden, materials, equipment, transportation, supervision, disposal costs, overhead and profit and shall cover all work involved in accordance with (IAW) Statement of Work (SOW). If Itemized Schedule of Values Cost breakdown is not provided, bidders/offerors’ bid could be deemed non-responsive.
o NOTE 2: Copies of all subcontractor quotes are required.
2. BID SUBMISSION: All bids shall be submitted by the prime contractor, through Email to guy.brooks@va.gov and tonya.bradley@va.gov. Also, submit your bid via email to the Contract Specialist/Contracting Officer ONLY. All bids are due by 4/20/2023 9:00 AM, EST.
NOTE 1: To be considered and accepted as timely the bid must be uploaded in its entirety prior to the deadline. Failure to provide a bid in its entirety prior to the deadline will render the bid noncompliant.
NOTE 2: Due to Coronavirus (COVID-19), and Monkey Pox Outbreak the Bid Opening will be conducted via MS Teams:
Microsoft Teams meeting Join on your computer, mobile app or room device Click here to join the meeting Meeting ID: 294 864 717 478 Or call in (audio only) +1 872-701-0185,,369764555# United States, Chicago Phone Conference ID: 369 764 555#
3. BASIS FOR AWARD: The Government intends to award a contract to the responsible offeror with the lowest evaluated price. Offerors must submit a cost breakdown in sufficient detail to permit a complete analysis of labor, burden, materials, equipment, transportation, supervision, and disposal. When price is the only factor considered, award will be based on the lowest reasonable price received.
4. TECHNICAL BID: A technical bid is not required.
5. EVALUATION OVERVIEW: Bids will be evaluated and ranked according to price and price alone, from lowest to highest. All bids shall include a cost breakdown in sufficient detail to permit a complete analysis of labor, burden, materials, equipment, transportation, supervision, and disposal. The Government may use various price analysis techniques and procedures to make a price reasonableness determination. Bids unreasonably high or unrealistically low in price, when compared to the Government estimate, and market conditions evidenced by other competitive bids received, may be indicative of an inherent lack of understanding of the solicitation requirements and may result in bid rejection without discussion.
For a bids to be eligible for award, the bidders must ensure they are in compliance with the NAICS code listed on Page #1, block #10 of the 1442 and by issuing a bid for this solicitation confirms that the bidders amount is good for 120 days from the date issued.
6. ATTACHMENTS:
a. Itemized Schedule of Values Cost Breakdown
b. Specifications
c. Drawings
7. SAFETY AND ENVIRONMENTAL RECORD: In order to be eligible for consideration and award, the contractor shall have no more than two serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 5 years and have an Experience Modification Rate (EMR) of equal to or less than 1.0.
All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record with their bid.
1. A self-certification on company letterhead that the bidder has no more than two (2) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past five years. Bidders shall submit copies of their OSHA logs (OSHA Form 300A) for the past three years with their bid. If the firm has been in business for less than three years, they shall submit copies of their OSHA logs for the period of time they have been in business.
2. Information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.
NOTE: Failure to submit this documentation with the bid shall be grounds for rejection of the bid as non-responsive.
8. Security – Background PIV requirement In accordance with VHAPM Part 822.18 CONTRACTOR PERSONNEL SECURITY AND SUITABILITY SOP Part B:
1.4, Deputy Under Secretary for Health and Operations and Management (10N) Memorandum, Contractors Excepted from Background Investigation and Screenings, dated February 8, 2007, specifies that the following low risk or non-sensitive contractor positions are excepted from the requirement to have a background investigation:
1.4.1. Contract personnel not accessing VA information resources such as personnel hired to maintain the medical facility grounds, construction contractors, utility system contractors, etc.
1.4.2. Contract personnel with limited and intermittent access to equipment connected to facility networks where limited Personal Health Information (PHI) is available, including contractors who install, maintain and repair networked building equipment such as fire alarm, heating ventilating and air conditioning equipment, elevator control systems, etc. If equipment to be repaired is located within sensitive areas (e.g. computer room/communications closets) VA IT staff must escort contractors while on site.
1.4.3. Contract personnel with limited and intermittent access to equipment connected to facility networks where limited PHI may be resident, including medical equipment contractors who install, maintain and repair networked medical equipment such as CT Scanners, EKG Systems, ICU monitoring, etc. Here, medical facilities must have a VA Business Associate Agreement (see VHAPM Part 839.105-70) if appropriate with the vendor to assure compliance with the requirements of the Health Insurance Portability and Accountability Act of 1996. Contract personnel, if on site, should be escorted by VA IT staff.
| 1.5. Special Agreement Check (SAC) Requirements and Exemptions: If it is determined | that an exemption to a background investigation applies, the CO and COR shall | determine whether or not a Special Agreement Check is required. All contract personnel | who are exempt from a background investigation and who provide direct and/or ancillary | health care services at VA facilities or have access to VA information systems or | sensitive information must have a SAC completed unless an exemption applies. Deputy | Under Secretary for Health and Operations and Management (10N) Memorandum, | Contractors Excepted from Background Investigation and Screenings, dated February 8, | 2007, specifies that the following low risk or non-sensitive contractor positions are | excepted from the requirement to have a background screening (Special Agreement | Check): |
| 1.5.1. Contract personnel not accessing VA information resources such as personnel hired to maintain the medical facility grounds, construction contractors, utility system contractors, etc. | ||||||||||
| 1.5.2. Contract personnel with limited and intermittent access to equipment connected to facility networks where limited Personal Health Information (PHI) is available, including contractors who install, maintain and repair networked building equipment such as fire alarm, heating ventilating and air conditioning equipment, elevator control systems, etc. If equipment to be repaired is located within sensitive areas (e.g. computer room/communications closets), VA IT staff must escort contractors while on site. | ||||||||||
| 1.5.3. Contract personnel with limited and intermittent access to equipment connected to facility networks where limited PHI may be resident, including medical equipment contractors who install, maintain and repair networked medical equipment such as CT Scanners, EKG Systems, ICU monitoring, etc. Here, medical facilities must have a VA Business Associate Agreement with the vendor to assure compliance with the requirements of the Health Insurance Portability and Accountability Act of 1996. Contract personnel, if on site, should be escorted by VA IT staff. |
Therefore, it is determined that this project is excepted from the background investigation and screening requirements. No access to VA Sensitive Information or access to VA network is required under this contract. Designers shall only be required to obtain flash badges for this project.
9. TRAINING: All employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s competent person shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.
10. MAGNITUDE OF CONSTRUCTION: Range between $1,000,000 and $2,000,000
11. PLANS/DRAWINGS:
a. Drawings.
b. Specifications.
12. DESCRIPTION OF WORK: This is a new requirement and being procured in accordance with Federal Acquisition Regulation (FAR) 36 and VA Acquisition Regulation (VAAR) 836 and VA Acquisition Manual (VAAM) 836 for the project to include general construction, clean all masonry, tuck point all masonry, seal cracks around door frames and windows, replace any damaged brick, remove non matching mortar full depth and repoint brick, repoint around 3 sides of all window sills, repair/refinish damaged window sills, caulk and seal transoms, reset window well bricks, remove concrete parging on brick, repair/replace half wall caps, replace steel corner guard angles on brick, install weep holes with reticulated baffles at 24” around building, sand and resurface limestone, and any other requirements of the specifications for Buildings 28, 31, 43, 48, and 114. Parking lots cannot be block or used as laydown areas for this project.
Period of Performance is 455 calendar days (DEDUCT NO.1): Complete all work associated with the base bid, except delete all work on building 114. Provide price and number of days to deduct work.
Period of Performance is 395 days
13. COMPLETION TIME: All work shall be completed per above calendar days’ from receipt of the Notice to Proceed.
14. SDVOSB SET-ASIDE: This procurement is 100% set-aside for Service-Disabled, Veteran-Owned Small Business (SDVOSB). Bids are solicited only from SDVOSB concerns and bids received from concerns that are not SDVOSB concerns shall be rejected. In order to be considered, the firm must be shown in the Veteran Small Business Certification (VetCert) Program (https://veterans.certify.sba.gov) website as verified at the time of submission of their bid.
15. CONTRACTOR RESPONSIBILITY: Contractor shall be required to complete all contract work and schedule a final inspection within the specified contract performance period. Should the Contractor fail to complete the contract work (including scheduling of the final inspection), and it is determined by the Government to be a Contractor-caused delay, the Contractor shall be in default status. If the Government determines it to be in the best interest of the Government to allow the Contractor to continue to perform contract work, the Contractor shall provide equitable consideration to the Government for additional time granted for completion of contract work. Such agreement shall not be deemed a waiver of the Government’s right to terminate this contract in the event the Contractor fails to complete the contract work (including scheduling of the final inspection) on or before the completion date.
16. TB TESTING: In accordance with VHA Directive 2011-036, CEOSH Construction Safety Guidebook, 2012 1.1.1 VHA Policy, CDC 2005 Guidelines for Preventing the Transmission of Mycobacterium tuberculosis in Health-Care Settings.
(a) The contractor must provide written certification that all contract employees assigned to the work site have had a pre-placement tuberculin screening within 90 days prior to assignment to the worksite and been found have negative TB screening reactions. Contractors will be required to show documentation of negative TB screening reactions for any additional workers who are added after the 90-day requirement before they will be allowed to work on the work site.
NOTE: This can be the Center for Disease Control (CDC) and Prevention and two-step skin testing or a Food and Drug Administration (FDA)-approved blood test.
(b) Contract employees manifesting positive screening reactions to the tuberculin must be examined according to current CDC guidelines prior to working on VHA property.
(c) Subsequently, if the employee is found without evidence of active (infectious) pulmonary TB, a statement documenting examination by a physician must be on file with the employer (construction contractor), noting that the employee with a positive tuberculin screening test is without evidence of active (infectious) pulmonary TB.
(d) If the employee is found with evidence of active (infectious) pulmonary TB, the employee would require treatment with a subsequent statement to the fact on file with the employer before being allowed to return to work on VHA property.
17. PRE-BID CONFERENCE: A pre-bid conference has been scheduled Wednesday, March 15, 2023, at 10:00 a.m., in the Contracting Parking Lot, 100 Emancipation Drive, Building 27, outside of Contracting Office, Hampton VA Medical Center. This pre-bid conference will be the only opportunity for potential bidders to visit the site.
No more than two (2) representatives from each company and Contractor must submit their name(s) no later than Tuesday, March 14, 2023 @ 1:00 PM EST to guy.brooks@va.gov and tonya.bradley@va.gov.
All potential bidders, subcontractors, and suppliers are required to attend this pre-bid conference to submit a bid. The signing of names for bidders, subcontractors, and suppliers who do not attend the site visit is prohibited.
NOTE: QUESTIONS REGARDING THIS SOLICITATION MUST BE SUBMITTED VIA E-MAIL TO guy.brooks@va.gov and tonya.bradley@va.gov; NO TELEPHONE QUESTIONS WILL BE ACCEPTED. CUT OFF FOR QUESTIONS IS 12:00 PM (LOCAL TIME), WEDNESDAY, April 2 , 2023. NO FURTHER QUESTIONS WILL BE ADDRESSED AFTER THAT DATE/TIME.
18. KEYS: All keys provided the Contractor for use during the project shall be returned to the Contracting Officer's Representative (COR) at completion of the work or upon request. No keys shall be reproduced by the Contractor. There shall be a charge of $10.00 for each key that is lost or not returned to the COR. Payment shall be made to the VA Medical Center, Hampton, VA upon receipt of a Bill of Collection.
19. PREPARATION OF BIDS/OFFERS/BIDS: Neither the VAMC nor the VISN 6 CAS will pay for any costs incurred in preparation and submission of bids or bids.
For a bids to be eligible for award, the bidders must ensure they are in compliance with the NAICS code listed on Page #1, block #10 of the 1442 and by issuing a bid for this solicitation confirms that the bidders amount is good for 120 days from the date issued.
20. PRIVACY AND CONFIDENTIALITY: Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information. Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized by this contract or its’ attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.
21. VETS 100: Title 38, USC Section 4212(d), and Public Law 105-339, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS 100 reporting information can be done electronically at: http://vets100.cudenver.edu. Award cannot be made unless the awardee has filed their VETS 100 report. Therefore, all bidders/offerors are encouraged to file every year.
22. SYSTEM FOR AWARD MANAGEMENT (SAM): Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Award cannot be made until the contractor has registered. Bidders are encouraged to ensure that they are registered in SAM prior to submitting their bid.
23. CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM:
| (a) FAR 42.1502 direct all Federal agencies to collect past performance information on contracts. The Department of Veterans Affairs has implemented use of the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15 |
| (b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action. |
(c) Please furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm’s past performance evaluation(s) for the contract no later than 30 calendar days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.
(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, system requirements, and training information for CPARS are available at www.cpars.gov. The CPARS User Manual, registration for online training for Contractor Representatives may be found at this site.
(e) Within 60 calendar days after the end of a performance period, the Contracting Officer will complete an interim or final past performance evaluation and the report will be accessible at www.cpars.gov. Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment. Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official’s narrative and should provide your views on the causes and ramifications of the assessed performance. In addition to the ratings and supporting narratives, blocks 1-17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection evaluations. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating, “No Comment” in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government.
This is the start of the file's text. The full file is on GovTribe.