Renovate and Modernizing Questions RFI.pdf

PDF 156 KB Posted

Attached to
Z1DA--Renovate Imaging (VA-22-00058593)
Solicitation number
36C24622B0047
Issued by

About this file

This document contains questions submitted in response to a solicitation by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6. The solicitation seeks a general contractor to renovate and modernize the imaging suite at the VA Medical Center in Asheville, North Carolina. The project scope involves demolishing existing spaces within the imaging suite such as an old file area and reworking some interior spaces. It will rebuild the area to provide three additional ultrasound exam rooms, three new restrooms, converting one exam room into a new HAC office, and removing and relocating all imaging equipment from construction impact areas. The document clarifies questions around flooring requirements, changes to the existing HVAC system, the identity of the contractor maintaining the existing DDC system, occupant relocation plans during construction, the potential for project extensions due to product availability, requirements for after-hours shutdowns and wage rates, and the designated laydown and dumpster areas.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovate and Modernizing

Imaging Suite

NOTE: The following questions were submitted for clarification of the requirement.

Questions:

1.) There are several numbered/labeled rooms that are not on the Room Finish Schedule. Can you check on ID175 Control Room? It is surrounded by rooms that require flooring but this room is not listed on the finish schedule? Please clarify. 1D175 requires new flooring to match 1D172, 1D173, 1D174.

2.) Will any changes to the existing F/A system be required? Yes. See drawing FP001, FD101, FP101

3.) Who is the service contractor of record maintaining your ddc system? ASI

4.) Will the Occupants be relocated during construction? YES. Only in the rooms that are designated on the drawing.

5.) Solicitation states project to be 180 days from NTP. With current product availability will there be an extension of the project? If needed

6.) Where some shutdowns will be required after hours to not impact the VA and limit the interruption of operations. Will there be a shift differential of Wage rates? The Va does not determine

7.) Will all Imaging equipment be removed/relocated from construction impact areas? YES 8.) Are there any known Hazardous materials (Asbestos, Lead, etc.…) present in the construction impacted areas? None Identified

9.) Where is the designated Laydown area? Behind Imaging department in the grass

10.) Where is the designated Dumpster laydown area? Behind building 47