This statement of work describes a renovation project for the imaging suite at the VA Medical Center in Asheville, NC. The project will demolish existing spaces within the imaging suite such as the old file area and rework some interior spaces. It will rebuild the area to provide space for three additional ultrasound exam rooms and three new restrooms. One exam room will be converted into a new HVAC and office. Offerors must submit bids for all bid items, including the base bid, by the specified deadline to be considered responsive. The selected contractor will be required to complete construction within 180 calendar days of the notice to proceed and all administrative items within 30 days thereafter. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Imaging Suite
Project Number 637-18-107
ASHEVILLE VAMC
The VA Medical Center located in Asheville, NC is seeking a general contractor to completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the project will renovate and modernize the imaging suite. It will demolish existing space within the Imaging Suite such as the old file area and rework some interior spaces. Project will rebuild the area to provide space for three additional Ultrasound Exam Rooms and three new restrooms. One exam room will be converted into a new HVAC and new office.
Construction, or work, for the Base Bid is to be completed in 180 calendar days from the Notice to Proceed (NTP).
Submittals, close out, and other administrative items are to be completed within 30 days of the end of work.
Please Note: Offerors MUST affix a bid to ALL bid items to be considered responsive to the invitation for bid (IFB) requirements; to include the Base Bid.