36C24621B0010- Request for Information.pdf

PDF 480 KB Posted

Attached to
Z2GC--659-21-2-6049-0345 Underground Storage Tanks B 42 & 21 (VA-21-00046434)
Solicitation number
36C24621B0010
Issued by

View the file

Other files

File Type Posted
OPPORTUNITIES-DESCRIPTION P0007.pdf PDF
P0007.pdf PDF
36C24621B0010 0004_1.docx DOCX document
36C24621B0010 0003.docx DOCX document
36C24621B0010 0002.docx DOCX document
B21_E2.pdf PDF
B21_E1.pdf PDF
B42-E36.pdf PDF
36C24621B0010 0001.docx DOCX document
36C24621B0010_1.docx DOCX document
Updated SOW.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information 36C24621B0010

Underground Storage Tanks B21 & B42

1. Please confirm the current bid due date and time:

A. 07/12/2021 @11:00AM

2. Will you be issuing a form SF1442 for completing our offer/price?

A. All bids will be opened at the virtual bid opening

3. Is a bid guarantee required (bid bond)?

A. Yes

4. Due to the difficulty of supply in the current market and the upcoming July 4th holiday, would the VA please extend the bid due date by 21 days?

A. The due date will be extended 5 business days until July 12, 2021.

5. Will the VA assist in the locate of underground utilities in the areas of the tanks?

A. The contractor will be responsible for locating the underground utilities.

6. Do the bollards need to have stainless steel covers like some of the others around the campus?

A. The bollards can be of a concrete type.

7. Could you please provide the period of performance (number of days to complete the contract)?

A. The period of performance is 90-180 days

8. Is there a phasing requirement? Does all work have to be completed on Building 42’s tank before work is started on Building 21’s tank?

A. There is phasing requirements. Complete building 21’s tank first and then building 42’s tank.

There should not be a shutdown of more than 1 work shift and all required permits must be completed prior to each shutdown.

Request for Information 36C24621B0010

Underground Storage Tanks B21 & B42

9. Is chain link construction fencing required or will orange safety fence be acceptable?

A. The contractor must follow VA construction specifications.

File details come from the government source that posted it. Updated .