36C24621B0006 0002.docx
DOCX document 22 KB Posted
- Attached to
- Z1DA--Upgrade Fire Suppression-Annunciation System Federal contract opportunity
- Solicitation number
- 36C24621B0006
About this file
This document provides details for an upcoming federal contract solicitation to upgrade the fire suppression and annunciation system at the Hunter Holmes McGuire Hospital building in Richmond, Virginia. The solicitation will be issued by the Department of Veterans Affairs and is anticipated to have a value between $500,000 and $1,000,000, with a performance period of 275 calendar days. The solicitation will be set aside for service-disabled veteran owned small businesses and will require electrical and mechanical work to reconfigure the existing diesel fire pump, demolish structures, and perform associated architectural, electrical, plumbing and structural improvements. Interested vendors should monitor the website for issuance of the solicitation around May 4, 2021, with proposals due approximately 30 days later. A pre-solicitation site visit is scheduled for May 17, 2021.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24621B0006 0003.docx | DOCX document | |
| 36C24621B0006_1.docx | DOCX document | |
| WAGE DETERMINATION.pdf | ||
| Drawings.pdf | ||
| Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
TBD
652-18-100 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton
VA
23667 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton
VA
23667 To all Offerors/Bidders
36C24621B0006 06-15-2021
X X
The purpose of this amendment is to provide RFI responses, see pages 2-5 for clarification.
Acknowledge all solicitation amendments when submitting bids.
Desiree Mills Contracting Officer Fire Suppression RFI Responses
1. The diesel fire pump room enclosures are to be 2-hr rated. Per NFPA 20, fire pump room with sprinkler protection is only required to be 1 hr rated. Is the reduction in fire rating allowed?
Please provide 2-hr rated enclosure for diesel fire pump room. Provide deduct alternate for providing 1 hr. rated wall.
2. The diesel fire pump is out of service. However, Phase 3 requires testing of both fire pumps. Is the diesel to be repaired by others? How to program the diesel fire pump controller if the pump is out of service?
It is our understanding that the diesel pump is working and is the primary pump for building 1.
3. Any work and testing required to be done after hours?
This will have to be coordinated with VA.
4. Does the fire watch area include the hospital?
This will have to be coordinated with VA. This will depend upon the duration of time needed during switchover to new electric pump.
5. The areas of fire pump installation are not considered healthcare. Does exhaust air flow required?
Refer to F-101, Keynote 5.
6. What risers are required to be pressure tested after the fire pump is installed?
Existing pressure at the top of the risers need to be serviced by the new pump. Ensure new pump maintains required pressure at the top of the riser.
7. Is sprinkler protection required in the new electric fire pump room?
Yes
8. Does the new fire pump controller need to be monitored by the fire alarm system?
Yes (Explanation: The new fire pump room (which includes pump and controller) will be monitored and provided with detection per NFPA 72 section 23.8.5.9).
9. Please confirm there is no fire alarm scope in the new 2hr rated diesel fire pump enclosure.
Fire alarm scope is shown in the new fire pump enclosure on sheet E-101.
10. Is double check backflow acceptable in lieu of pressure reduced backflow?
Provide as specified.
11. Please confirm jockey pump rating of 60GPM.
Confirmed.
12. Underground utility plans available?
Utility plans provided might not be up to date, it is up to the contractor to investigate and mark out for utilities.
13. Is another site visit allowed?
| No | |
| 14. | Sub-contractors indicated that there were no VA personnel to conduct the site visit as per the Solicitation information below: |
"A Site Visit will be conducted on: May 24, 2021 at 10:00 am Eastern Standard Time (EST) Location: 1201 Broad Rock Blvd Richmond, VA 23249 (outside building 501)" Provide information for when this site visit can occur for interested parties.
| Site visit was conducted as scheduled | |
| 15. | Can the superintendent also be the SSHO? |
| Yes | |
| 16. | Can the superintendent also be the QCM? |
| Yes | |
| 17. | Can the superintendent be both the SSHO and the QCM? |
| Yes | |
| 18. | Is project tax exempt or taxable? |
| Taxable | |
| 19. | Can photos of existing areas be provided for review. |
| Photos should have been taken during site visit. | |
| 20. | Sheet S-101, coded note 3. Provide existing column foundation information as well as existing exterior building foundation information. |
Existing structural drawings indicates that column footing at gridline E8 is 4’-0 x 4’-0 x 12” deep. Bottom of footing elevation is (-3’-8) below adjacent slab.
Existing exterior building foundation dimensions are depicted in detail 8/S201.
| 21. | Sheet S-201 / detail 6: |
| a. | Has soil test been obtained? |
No, soil testing has not been performed for this project.
b. Is concrete pad to be at sufficient depth for both sufficient bearing and for frost depth?
Yes, concrete pad depicted in detail 6/S201 shall provide adequate bearing and frost protection.
22. Sheet C-501 / Demolition Plan / coded note 17 calls for existing GPRS report, sheet V-101. Sheet is not included within set. Provide sheet V-101 and all pertinent information on findings.
Note 17 does not indicate a report, but that a Level B subsurface utility investigation was performed. Said survey info is provided and reflected on the demo plan, therefore a separate survey sheet (V-101) was not necessary and not provided within the plan set.
23. Sheet C-502 / detail 1 & 4. Provide specification for removable bollard as basis of design.
Specifications for the removable bollard are provided via details 1, 4 & 5 as reflected on C-502. Also, C-501 indicates a Type A bollard shall be installed.
24. Sheet C-502 / detail 5. Can plastic protective cover similar to Post Guard with reflective stripe be utilized in place of painting? Cost would offset painting and repainting.
The detail provided is the standard VA detail. Any deviation from the detail will need to be approved by the VA.
25. Provide existing sprinkler information including pressure and flow rates.
Please specify what sprinkler information are you requesting? Entire building sprinkler information or for the new enclosure?
| 26. | Sheet F-101, coded note 2: |
| a. | Provide existing tank size and dimensions. |
Please refer to photos on same sheet.
Electrical
| 27. | Sheet E-001: |
| a. | Note A: Note calls for salvageable materials to be returned. Can specific information on salvage equipment be provided |
For this project, since the scope changed from the original, would not include any identifiable salvageable materials.
| b. | Luminaire Schedule / fixture B: is fixture tied to power before switch to remain on all the time or is unit contain night sensor? |
| Fixture is to be controlled with existing exterior, building mounted lights. Extend existing circuit and controls to new fixture. | |
| 28. | Sheet E-101 |
Key Notes:
a. What is existing Fire Alarm mfgr and system?
EST-3 by Edwards system
| b. | Is existing FA system able to handle new notification device? At the time of survey, it was able to handle new notification devices |
| c. | Note 11: Provide tank specific electrical information for extension. |
The tank appeared to have sensor connections.
| d. | Proposed 2-way duct bank to existing transformer (E) T1 appears to run through both existing asphalt and concrete (at transformer). |
| • | Is existing transformer pad contain grounding grid to be repaired? Can this occur and be accepted by NEC? |
Contractor should be able to start the concrete encasement outside of the fenced area. This area should be relatively safe from risk that the ducts will be accidently cut by excavation. After confirming with the COR, contractor should be able to just dig by hand and bury new conduit inside the fenced area, turning up the conduit under the existing pad, without actually disturbing the pad itself.
• What is thickness of existing concrete to be removed.
Existing concrete pad is 6” high, 9’ wide by 9’ deep.
e. Provide concrete transformer pad patch / repair details where new buried duct bank occurs.
Apogee has a new xfmr pad detail available; contractor shall let us know if that is acceptable.