36C24618R0224-000.docx
DOCX document 62 KB Posted
- Solicitation number
- 36C24618R0224
About this file
36C24618R0224 36C24618R0224_1.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24618R0224-00001000.docx | DOCX document | |
| 36C24618R0224-006.pdf | ||
| 36C24618R0224-002.pdf | ||
| 36C24618R0224-004.pdf | ||
| 36C24618R0224-001.pdf | ||
| 36C24618R0224-005.pdf | ||
| 36C24618R0224-003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C246-18-R-0224 Renovate PRRC
FedBizOpps Combined Synopsis/Solicitation Notice
CLASSIFICATION CODE
SUBJECT
CONTRACTING OFFICE'S
ZIP-CODE
SOLICITATION NUMBER
RESPONSE DATE (MM-DD-YYYY)
ARCHIVE
DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
SET-ASIDE
NAICS CODE
CONTRACTING OFFICE
ADDRESS
POINT OF CONTACT
(POC Information Automatically Filled from User Profile Unless Entered)
DESCRIPTION
See Attachment
AGENCY'S URL
URL DESCRIPTION
AGENCY CONTACT'S EMAIL
ADDRESS
EMAIL DESCRIPTION
ADDRESS
POSTAL CODE
COUNTRY
ADDITIONAL INFORMATION
GENERAL INFORMATION
PLACE OF PERFORMANCE
* = Required Field FedBizOpps Combined Synopsis/Solicitation Notice Rev. March 2010 Z Project 565-17-307 Reconfigure and Renovate Psychosocial Rehabilitation and Recovery Center Fayetteville VAMC 28301 36C24618R0224 04-06-2018 N 236220 Department of Veterans Affairs Network Contracting Office 6 201 Hay Street, Suite 304 Fayetteville NC 28301 Frank A .Fogg frank.fogg@va.gov 2300 Ramsey ST.
BLDG. 46
Fayetteville NC 28301
US
Frank.Fogg@va.gov frank.fogg@va.gov
XX (
1. SOLICITATION NO.
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
6. PROJECT NO.
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
A. NAME
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12B.)
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 4-85)
STANDARD FORM 1442
Prescribed by GSA YFAR (48 CFR) 52.236-1(d)
NSN 7540-01-155-3212
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See _____________________________.)
YES
NO
A.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due B.
An offer guarantee is, is not required.
C.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference D.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24618R0224 03-05-2018
TBD
565-18-1-5063-0004 565-17-307 Department of Veterans Affairs Network Contracting Office 6 2300 Ramsey St Fayetteville NC 28301 Department of Veterans Affairs Network Contracting Office 6 ATTN: Frank A. Fogg 201 Hay St., Suite 305 Fayetteville NC 28301 Frank Fogg 910-488-2120 x 5250 Project Title: Renovate for Psychosocial and Rehabilitation and Recovery Center (PRRC)
The Contractor shall provide all supervision, labor, materials, and equipment necessary to complete Project 565-17-307, Renovate for Psychosocial Rehabilitation and Recovery Center at the Fayetteville VAMC in accordance with the plans and specifications. The project entails the renovation of Building no. 46, which is approximately 4,265 GSF. The work includes, but is not limited to the following: demolition of interior walls, ceiling grid, flooring, etc.; framing, drywalling, finishing and painting; mechanical; electrical; plumbing; exterior improvements; etc. Performance of this work shall meet all State, Federal, and Veterans Affairs regulations and requirements as indicated in the plans and specifications.
See the SCOPE OF WORK, the BID ITEM LIST, the Specifications, and the Drawings for additional descriptions.
X X 52.211-10 X N/A N/A X X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NO.
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
20B. SIGNATURE
20C. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 253(c) (
26. ADMINISTERED BY
CODE
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation, is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work, requisitions identified award consummates the contract. which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
31A. NAME OF CONTRACTING OFFICER
TO SIGN
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
OFFER
AWARD
STANDARD FORM 1442(REV. 4-85)BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14) (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Bid Item 1.
$0.00 Department of Veterans Affairs Network Contracting Office 6 201 Hay St., Suite 304 Fayetteville NC 28301 Department of Veterans Affairs Financial Services Center
PO BOX 149971
Austin TX 78714-9971 Frank A. Fogg NCO 6 Contracting Officer
Table of Contents
| PART I - THE SCHEDULE (R$PG1) | 2 |
| SECTION A - SOLICITATION/CONTRACT FORM (R$PG#) | 2 |
| SF 1442 SOLICITATION, OFFER, AND AWARD(I$DESC1-26) (Construction, Alteration, or Repair)(I$DESC2-26) | 2 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 6 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 7 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 12 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 13 |
| 2.3 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014) AND ALTERNATE II (JUN 2009) | 13 |
| 2.4 52.228-1 BID GUARANTEE (SEP 1996) | 14 |
| 2.5 52.233-2 SERVICE OF PROTEST (SEP 2006) | 14 |
| 2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 15 |
| GENERAL CONDITIONS | 16 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 18 |
| 4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 18 |
| 4.3 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014) | 18 |
| 4.4 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 23 |
| 4.5 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 23 |
| 4.6 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012) | 23 |
STATEMENT OF WORK
December 29, 2017 VAMC Fayetteville, NC
I. PROJECT DATA:
TITLE: Renovate for Psychosocial and Rehabilitation and Recovery Center (PRRC) PROJECT No: 565-17-307 Contracting Officer’s Representative (COR): Zachary Swavely, Facilities Management Service (910-822-7930) Requestor: Wendy Gillis, Chief, Facilities Management Service (910-822-7933) Construction duration: 270 Days Outline of Scope of Work:
The Contractor shall provide all supervision, labor, materials, and equipment necessary to complete Project 565-17-307, Renovate for Psychosocial Rehabilitation and Recovery Center at the Fayetteville Veterans Affairs Medical Center in accordance with the plans and specifications. The project entails the renovation of Building no. 46, which is approximately 4,265 GSF. The work includes, but is not limited to the following: demolition of interior walls, ceiling grid, flooring, etc.; framing, drywalling, finishing and painting; mechanical; electrical; plumbing; exterior improvements; etc. Performance of this work shall meet all State, Federal, and Veterans Affairs regulations and requirements as indicated in the plans and specifications.
Specific duties will include but are not limited to the following:
· Contractor shall completely prepare site for building operations, including demolition and removal of existing structures and perform work as required by the drawings and specifications.
· Visits to the site by Bidders may be made only by appointment with the VISN6 Centralized Acquisition Services Contracting Specialist or his designated COR.
· All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access. Bidders are to report to the COR to obtain day badges. Upon award of the contract, VA issued Contractor work badges are to be requested from the COR prior to commencing any work. Badges must be worn at all times when working at the facility. (Any ID badge that is lost must be reported to the COR.)
· VA WAREHOUSE WILL NOT RECEIVE OR STORE ANY PROJECT RELATED EQUIPMENT OR MATERIALS.
· Hours of Operation: Work will be performed between the hours of 7:00am-5:00pm, Monday-Friday. Some work may be performed at different hours when approved by COR.
---END---
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
(a) If the bid/offer exceeds $150,000, a bid guarantee is required in an amount not less than twenty (20) percent of the bid/offer price or $3M, whichever is less.
(b) Bidders are reminded that an acceptable Bid Guarantee MUST be received with the bid/offer before the bid opening. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids/offers, will require rejection of the bid/offer in all cases except those listed in Federal Acquisition Regulation (FAR) 28.101-4, and may be cause for rejection even then. For guidance, Bidders/Offerors are referred to FAR provision 52.228-1, BID GUARANTEE (SEP 1996) in the solicitation, FAR Part 28.101 Bid Guarantees, and FAR Part 28.2 Sureties and Other Security for Bonds. Corporate sureties offered for bonds must appear on the list contained in the Department of Treasury Circular 570, “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and Acceptable Reinsuring Companies, ” See http://www.fms.treas.gov/c570/c570.html
(c) If the contract will exceed $30,000 but will not exceed $150,000, the bidder/offeror to whom award is made will be required to furnish a Payment Bond, Standard Form 25A, or alternative payment protection.
(d) If the contract will exceed $150,000, the bidder/offeror to whom award is made shall be required to furnish a Payment Bond, Standard Form 25A, and a Performance Bond, Standard Form 25. Copies of the Standard Forms 25A and 25 may be obtained upon application to the Issuing Office.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
SUBMISSION OF BIDS/OFFER
The bidder/offeror shall submit the following in response to this Request for proposal:
(a) A completed and signed Standard Form 1442.
(b) A completed copy of the Representations and Certifications (See FAR 52.204-8 Annual Representations and Certifications (MAR 2012)).
(c) A fully executed bid bond.
(d) Documentation of their safety record.
(e) All forms and/or certifications as directed in the solicitation and basis for award, including the specifications.
SAFETY AND ENVIRONMENTAL RECORD: In order to be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an Experience Modification Rate (EMR) of equal to or less than 1.0.
All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record with their bid.
1. A self-certification on company letterhead that the bidder has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. Bidders shall submit copies of their OSHA logs (OSHA Form 300A) for the past three years with their bid. If the firm has been in business for less than three years, they shall submit copies of their OSHA logs for the period of time they have been in business.
1. Information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.
DESCRIPTION OF WORK: See SCOPE OF WORK and BID ITEM LIST.
PROJECT MAGNITUDE COST RANGE: $500,000.00 - $1,000,000.00
NAICS: The NAICS Code for this procurement is 236220, Commercial and Institutional Construction, with a maximum small business size standard of $36.5 million.
TIMELINE:
Solicitation issued- 03/05/2018 Site visit-03/20/2018 see pre-bid conference RFI due - NLT 03/27/2018 Government Response - On or about 04/03/2018 Proposals Due - On or about 04/06/2018 SDVOSB SET-ASIDE: Effective June 20, 2007, Public Law 109-461, the Veterans Benefits, Health Care, and Information Technology Act of 2006 allow procurements to be set-aside for SDVOSBs and VOSBs. This procurement is 100% set-aside for Service-Disabled, Veteran-Owned Small Business (SDVOSB). Bids are solicited only from SDVOSB concerns and bids received from concerns that are not SDVOSB concerns shall be rejected. In order to be considered, the firm must be shown in the Center for Business Enterprise (VetBiz) website as verified at the time of submission of their bid. No award can be made unless the vendor is registered.
Plans/Drawings/Specifications: Drawings and specifications are attached in electronic format to this solicitation. Offerors are responsible for downloading and printing their own bid sets. The VA will not provide hard copies of the drawings and specifications to any offeror. Contractors are responsible for ensuring that any construction document package used for bidding or construction is complete and up-to-date.
RESIDENT PROJECT ENGINEER: All reference to "Resident Project Engineer" in the solicitation will be changed to "Contracting Officer’s Representative" or “COR.”
GENDER: Wherever masculine gender is used in the solicitation and contract documents, it shall be considered to include both masculine and feminine.
DEPARTMENT OF VETERANS AFFAIRS: All reference to "Veteran's Administration" or "VA" in the solicitation will be changed to Department of Veterans Affairs".
METRIC PRODUCTS: Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerances specified using conversion tables and contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.
If a product is manufactured to metric dimensions and those dimensions exceed the tolerances specified in inch-pound units, a request should be made to the Contracting Officer, in writing, to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.
CONTRACTOR RESPONSIBILITY: Contractor shall be required to complete all contract work and schedule a final inspection within the specified contract performance period. Should the Contractor fail to complete the contract work (including scheduling of the final inspection), and it is determined by the Government to be a Contractor-caused delay, the Contractor shall be in default status. If the Government determines it to be in the best interest of the Government to allow the Contractor to continue to perform contract work, the Contractor shall provide equitable consideration to the Government for additional time granted for completion of contract work. Such agreement shall not be deemed a waiver of the Government’s right to terminate this contract in the event the Contractor fails to complete the contract work (including scheduling of the final inspection) on or before the completion date.
TRAINING: Effective July 1, 2005, all employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COTR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s competent person shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.
TB TESTING: It is the responsibility of the contractor to provide TB training annually and a PPD test annually for any employee(s) providing services at VAMC, Fayetteville, North Carolina. The Government reserves the right to review the contractor’s records.
PRE-BID CONFERENCE: A pre-bid conference (SITE VISIT) has been scheduled for March 20, 2018 at 10:00 a.m., at Fayetteville VAMC, Bldg. 46, located at 2300 Ramsey St., Fayetteville, NC. This pre-bid conference will be the only opportunity for potential bidders to visit the site.
All potential bidders, subcontractors, and suppliers are strongly encouraged to attend this pre-bid conference.
NOTE: QUESTIONS REGARDING THIS SOLICITATION MUST BE SUBMITTED E-MAIL (frank.fogg@va.gov); NO TELEPHONE QUESTIONS WILL BE ACCEPTED. CUT OFF FOR RFI QUESTIONS IS 4:00 PM (LOCAL TIME), March 27, 2018.
KEYS: All keys provided the Contractor for use during the project shall be returned to the Contracting Officer's Representative (COR) at completion of the work or upon request. No keys shall be reproduced by the Contractor. There shall be a charge of $10.00 for each key that is lost or not returned to the COR. Payment shall be made to the VA Medical Center, Fayetteville, NC upon receipt of a Bill of Collection.
PREPARATION OF BIDS/OFFERS/PROPOSALS: Neither the VAMC nor the VISN 6 NCO will pay for any costs incurred in preparation and submission of bids or proposals.
PRIVACY AND CONFIDENTIALITY: Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information. Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized by this contract or its’ attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.
The C&A requirements do not apply and a Security Accreditation Package is not required. If the contractor opts to use a computer or computer system for processing contract documents, the requirements of FIPS 140-2 for encryption of contract documents must be met.
VETS 100: Title 38, USC Section 4212(d) and Public Law 105-339, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS 100 reporting information can be done electronically at: http://vets100.cudenver.edu. Award cannot be made unless the awardee has filed their VETS 100 report; therefore, all bidders/offerors are encouraged to file every year.
SYSTEM FOR AWARD MANAGEMENT (SAM): Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Award cannot be made until the contractor has registered. Bidders are encouraged to ensure that they are registered in SAM prior to submitting their bid.
PROPOSAL SUBMISSION DUE DATE: All proposals shall be submitted by the prime contractor, VIA E-MAIL (frank.fogg@va.gov); NO HARD COPY PROPOSALS OR FACSIMILES WILL BE ACCEPTED. All proposals are due by 4/6/2018 4:00 PM, EST.
NOTE: To be considered and accepted as timely the proposal must be uploaded in its entirety prior to the deadline. Failure to provide a proposal in its entirety prior to the deadline will render the proposal noncompliant Basis of Award Project 565-17-307: Reconfigure and Renovate Psychosocial and Rehabilitation and Recovery Center (PRRC) Fayetteville VAMC
A. BASIS FOR AWARD.
Award will be made to the lowest priced, technically acceptable responsible offeror, whose proposal conforms to all stated terms, conditions, representations, certifications, and any other information required by this solicitation. Technical tradeoff will not be made and no additional credit will be given for exceeding the minimum requirements. In the event an offeror’s proposal is determined to be unacceptable in any of these factors, the entire proposal will be considered unacceptable and the offeror will be ineligible for award.
To be considered technically acceptable for award each offeror must provide with their submitted offer:
1. Technical Approach - Technical approach to complete the project in accordance with the sow, drawings, specifications, and general requirements. Offerors shall submit a capability statement demonstrating a clear understanding of the statement of work, including operations and maintenance problems presented therein. The offeror should provide evidence of sufficient planning to show that work will be accomplished as required and on schedule, utilizing all available resources to meet requirements. At a MINIMUM, shall include with proposal the following:
· Provide confirmation capability of meeting the entire Project Scope.
· Registered as Service Disabled Veteran Owned–Small Business Vendor
· https://www.vip.vetbiz.gov/
· Active Sam at the time of submission
· Provide organizational Key Personnel
2. Management/Quality Control Approach - Proposal shall address your Management/Quality Control Approach to complete the project in accordance with the sow, drawings, specifications, and general requirements. Please provide:
· Safety plan
· Quality control plan
· Osha Cert Person Name and Credentials
· Scheduling Methodology
3. Relevant Experience/Past Performance – The Relevant Experience/Past Performance evaluation will assess the relative risks associated with an offeror's likelihood of success in performing the solicitation's requirements as indicated by that offeror's record of Relevant Experience/Past Performance.
· Offerors must provide a reference and a successfully completed contract that demonstrate recent and relevant record of performance in supplying services that meet the requirements described in the RFP. Provide description of projects, dollar value, and Point of Contact(s) including phone/FAX numbers.
4. Price. All CLIN items to include base and alternates in the Price Schedule must include a price to include Offerors cost breakdown in sufficient detail to permit a complete analysis of labor, burden, materials, equipment, transportation, supervision, and disposal. The total evaluated price will consist of the offeror’s proposed price and the government’s independent cost estimate. The Government may determine that an offer is technically acceptable; however, the prices are significantly unbalanced. Price reasonableness will be performed by the Contracting Officer If, during evaluation, it is determined that discussions are necessary, offerors’ Final Proposal Revisions (FPR) after discussions will be considered in making the source selection decision.
B. EVALUATION METHODOLOGY. The award decision will be based on the "Lowest Price, Technically Acceptable" Evaluation Standards Acceptable /Go ALL the minimum acceptable criteria are clearly met and demonstrated by the proposal. The offeror's proposal meets the performance and technical capability requirements defined in the sow, drawings, specifications, and general requirements.
Unacceptable /No-go Not all the minimum acceptable criteria are met by the proposal. An unacceptable proposal contains one or more deficiencies. Proposal fails to meet specified minimum performance and technical capability requirements defined in the SOW, or provide the minimum required documentation with proposal.
NOTE: Once the proposals have been determined to be "technically acceptable," award will based on cost/price only.
The following table will be used for each proposal received to score each LPTA factor as to whether it is Acceptable or Unacceptable.
| Non- Cost/Price Factors |
| Offeror |
| Technically Acceptable/ Go/ No-Go |
Technical Approach
Management/Quality control Approach
Past Performance
SSEB INSTRUCTIONS:
The SSEB establish the requirements of acceptability, and will evaluate proposals in accordance with the factors stated in the RFP and Basis of Award. In evaluating the technical portion of the proposals, the SSEB will evaluate utilizing the above methodology to establish acceptability. The attached template is provided to assist the SSEB in evaluating these factors. Each factor will be scored as Acceptable/Go or Unacceptable/No Go as defined above. Each proposal will be evaluated against the sow, drawings, specifications, and general requirements and the stated evaluation criteria. Each proposal is evaluated using the same standards.
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014) AND ALTERNATE II (JUN 2009)
(a) Definitions. "Bahrainian, Mexican, or Omani construction material," "commercially available off-the-shelf (COTS) item," "construction material," "designated country construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials Under Trade Agreements" (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute shall submit the request with its offer, including the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material, except foreign construction material from a designated country other than Bahrain, Mexico, or Oman that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.4 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Frank A. Fogg NCO 6 Contracting Officer Hand-Carried Address:
Department of Veterans Affairs Contracting Office Network Contracting Office 6 201 Hay St Fayetteville NC 28301 Mailing Address:
Department of Veterans Affairs Contracting Office Network Contracting Office 6 201 Hay st.
Fayetteville NC 28301
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— March 20, 2018 at 10:00am (local time)
(c) Participants will meet at— Fayetteville VAMC, Bldg 46 2300 Ramsey St., Fayetteville, NC (End of Provision)
GENERAL CONDITIONS
REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS)
a. As prescribed in Federal Acquisition Regulation (FAR) Part 42.1502 and 42.1503, the Department of Veterans Affairs (VA) evaluates contractor past performance on all contracts that exceed $100,000. The FAR requires that the Contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, Contractor Performance Assessment System (CPARS), which is maintained by the Naval Sea Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the Federal Awardee Performance and Integrity Information System (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.
b. The Contractor will have an opportunity to review their ratings/comments, under the step “Contractor Comments” in CPARS. You will be notified via email by the CPARS system to review the report and provide comments. Each contractor whose contract award is estimated to exceed $100,000 may register with CPARS database at the following web address: www.cpars.gov in order to review the past performance evaluations. Help in registering can be obtained by contacting Customer Support Desk @ DSN: 684-1690 or COMM: 207- 438-1690. Registration should occur no later than thirty days after contract award, and must be kept current should there be any change to the Contractor's registered representative.
Notification to Contractor
CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM
(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of Veterans Affairs has implemented use of the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15
(b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
(c) Please furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm’s past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.
(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, system requirements, and training information for CPARS are available at www.cpars.gov. The CPARS User Manual, registration for online training for Contractor Representatives may be found at this site.
(e) You have 14 calendar days following the Assessing Official signature date to submit comments before the evaluation is made available in the Past Performance Information Retrieval System (PPIRS). You have a total of 60 calendar days following the Assessing Official signature date to submit comments. Any comments that you submit will be posted to PPIRS. If you do not sign and return the evaluation within 60 calendar days the evaluation will be returned to the Assessing Official, you will no longer be able to provide comments and the evaluation will be annotated as follows: 'The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this evaluation.' Partially completed comments that were not signed and returned to the Government within 60 calendar days will be removed from the evaluation.
(f) The following guidelines apply concerning your use of the past performance evaluation:
(1) Protect the evaluation as “source selection information.” After review, transit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.
(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, preaward surveys, responsibility determination, production readiness reviews, or other similar purposes.
(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been completed.
(End of Notice)
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause)
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 270 calendar days after receipt of the Notice to Proceed (NTP). The time stated for completion shall include final cleanup of the premises.
(End of Clause)
4.3 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014)
(a) Definitions. As used in this clause— "Bahrainian, Mexican, or Omani construction material" means a construction material that—
(1) Is wholly the growth, product, or manufacture of Bahrain, Mexico or Oman; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in Bahrain, Mexico, or Oman into a new and different construction material distinct from the materials from which it was transformed.
"Caribbean Basin country construction material" means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
"Commercially available off-the-shelf (COTS) item"— (1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Component" means an article, material, or supply incorporated directly into a construction material.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
"Cost of components" means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
"Designated country" means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement country (Armenia, Aruba, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Netherlands, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, or United Kingdom);
(2) A Free Trade Agreement country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
"Designated country construction material" means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
"Domestic construction material" means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
"Foreign construction material" means a construction material other than a domestic construction material.
"Free Trade Agreement country construction material" means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
"Least developed country construction material" means a construction material that—
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
"United States" means the 50 States, the District of Columbia, and outlying areas.
"WTO GPA country construction material" means a construction material that—
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and all the Free Trade Agreements except the Bahrain FTA, NAFTA, and the Oman FTA apply to the this acquisition. Therefore, the Buy American statute restrictions are waived for designated country construction materials other than Bahrainian, Mexican, or Omani construction materials.
(2) The Contractor shall use only domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
| None |
| None |
| None |
| None |
| None |
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of…