Attachment 3 - SOW Removal of abandoned telecomunication.pdf
PDF 112 KB Posted
- Solicitation number
- 36C24527Q0025
About this file
This is a Statement of Work (SOW) for the removal of abandoned telecommunications equipment at the Washington, DC Veterans Affairs Medical Center.
The contractor must furnish all labor, supervision, materials, equipment, tools, permits, transportation, testing, disposal, and incidental services to safely disconnect, remove, and dispose of abandoned telecommunications infrastructure within the MER-3 (Main Equipment Room) of the Main Hospital Building. Scope includes removal of cabinets, racks, Motorola cabinets, control panels, power supplies, copper cabling, fiber optic cabling, coaxial cabling, communication cabling, control cabling, low-voltage cabling, exposed conduit (concealed conduit may remain with written approval), junction boxes, pull boxes, cable trays, wireways, supports, hangers, brackets, and cable pressurization systems including tanks, regulators, manifolds, valves, and tubing. The contractor must disconnect equipment from electrical and communication systems prior to demolition, patch wall penetrations, restore disturbed finishes, and dispose of materials off-site with waste manifests submitted to the VA Contracting Officer's Representative (COR) upon completion. Work must comply with NFPA 70 (NEC), OSHA Requirements, ANSI/TIA Telecommunications Standards, BICSI TDMM, and applicable Federal, State, Local, EPA, and VA requirements. Critical requirements include protecting all active systems (fire alarm, nurse call, security, access control, BAS, public address/paging, fiber backbone, and active data networks) with immediate repair or replacement of any damage at no additional cost to the Government. The contractor must perform daily quality inspections with three hold points (initial demolition area, mid-project inspection, final acceptance walkthrough), coordinate outages with VA Engineering at least 72 hours in advance, maintain emergency access, provide barricades and dust control, follow Lockout/Tagout procedures, and comply with VA Interim Life Safety Measures and Infection Control Risk Assessment requirements as directed. Work shall be performed during normal VA business hours unless approved otherwise. The contractor must field verify existing conditions prior to bidding, submit a demolition work plan, project schedule/phasing plan, safety plan, Lockout/Tagout procedures, disposal plan, restoration materials, and waste documentation. Submittals include before-and-after photographs and final punch list completion with the VA COR. A minimum one-year workmanship warranty is required on all patching, restoration, and repair work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IMG_5688-scaffolding.jpeg | JPEG file | |
| Attachment 2 - Site Visit information.pdf | ||
| Conduit Entrance to Building2.jpg | JPG image | |
| Cables at Base on Antenna.jpg | JPG image | |
| 36C24527Q0025 0001.pdf | ||
| Attachment 1 - Response to questions.pdf | ||
| IMG_5688-Circled.jpeg | JPEG file | |
| IMG_5685-Circled.jpeg | JPEG file | |
| 36C24527Q0025.pdf | ||
| Supplemental Instructions - Telecom Removal.pdf | ||
| Past Performance Questionnaire - telecom revoval.pdf | ||
| Service Contract Act WD No. 2015-4281.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Title: Removal of Abandoned Telecommunications Equipment at the Washington, DC Veterans Affairs Medical Center
Project Description
The Contractor shall furnish all labor, supervision, materials, equipment, tools, permits, transportation, testing, disposal, and all incidental services necessary to safely disconnect, remove, and properly dispose of abandoned telecommunications equipment, cabling, conduit, cable pressurization systems, and associated accessories located within the MER-3 (Main
Equipment Room) of the Main Hospital Building at the Department of Veterans Affairs Medical
Center, Washington, DC. All work shall be performed in close coordination with the VA
Contracting Officer's Representative (COR) and VA Telecommunications personnel to verify that all equipment identified for removal is abandoned and to ensure that active telecommunications systems remain fully operational throughout the duration of the project. The
Contractor shall take all necessary precautions to prevent interruption of existing telecommunications, life safety, security, and other critical building systems. The Contractor shall perform all work in accordance with applicable VA standards and industry best practices.
APPLICABLE STANDARDS
Work shall conform to the latest adopted editions of the following:
• NFPA 70 (NEC)
• OSHA Requirements
• ANSI/TIA Telecommunications Standards (where applicable)
• BICSI Telecommunications Distribution Methods Manual (TDMM)
• Applicable Federal, State, Local, EPA, and VA requirements
EXISTING CONDITIONS AND CONTRACTOR RESPONSIBILITY
Contractor shall field verify existing conditions prior to bidding and report discrepancies to the VA COR. Active systems shall remain operational unless approved otherwise.
SUBMITTALS
• Demolition work plan
• Project schedule/phasing plan
• Safety plan
• Lockout/Tagout procedures
• Disposal plan
• Restoration materials
• Waste documentation (if applicable)
DEMOLITION
• Verify with the VA COR that all equipment identified for removal is abandoned.
• Remove abandoned telecommunications equipment including cabinets, racks, Motorola cabinets, control panels, power supplies, and mounting hardware.
• Remove abandoned copper, fiber optic, coaxial, communication, control, and low-voltage cabling.
• Remove abandoned exposed conduit. Concealed conduit may remain only with written COR approval.
• Remove abandoned junction boxes, pull boxes, cable trays, wireways, supports, hangers, brackets, and hardware.
• Remove abandoned cable pressurization systems including tanks, regulators, manifolds, valves, tubing, piping, fittings, supports, wiring, and accessories.
• Disconnect equipment from electrical and communication systems prior to demolition.
• Protect active electrical, fire alarm, security, nurse call, BAS, paging, and telecommunications systems.
• Patch wall penetrations and restore disturbed finishes to match adjacent surfaces.
• Dispose of removed materials off-site in accordance with all regulations.
• Submit waste manifest(s) and disposal documentation to VA COR upon completion of the project as evidence of proper disposal.
• Clean work areas daily and upon project completion.
PROTECTION OF EXISTING SYSTEMS
The Contractor shall protect all existing systems that are to remain in service, including:
• Fire Alarm
• Nurse Call
• Security
• Access Control
• Building Automation System (BAS)
• Public Address/Paging
• Fiber Backbone
• Active Data Networks
• Any damage to active systems shall be immediately repaired or replaced by the Contractor at no additional cost to the Government.
FIELD VERIFICATION
Investigate all telecommunications infrastructure before demolition. Equipment of uncertain operational status shall remain until written direction is received from the VA COR.
QUALITY ASSURANCE AND HOLD POINTS
• Daily quality inspections
• Hold Point 1 – Initial demolition area
• Hold Point 2 – Mid-project inspection
• Hold Point 3 – Final acceptance walkthrough
SAFETY, ACCESS, AND PHASING
• Coordinate outages with VA Engineering.
• Maintain emergency access.
• Provide barricades and dust control.
• Follow Lockout/Tagout procedures.
• Comply with applicable VA Interim Life Safety Measures (ILSM) and Infection Control Risk Assessment (ICRA) requirements when directed by the VA.
• Minimize disruption to hospital operations.
CLEANUP AND CLOSEOUT
• Remove all debris, abandoned cabling, conduit, equipment, dust, and miscellaneous materials daily.
• Leave MER-3 in broom-clean condition.
• Restore disturbed finishes.
• Provide disposal documentation (if required).
• Provide before-and-after photographs.
• Complete final punch list and final walkthrough with the VA COR.
WARRANTY
Provide a minimum one (1) year workmanship warranty on all patching, restoration, and repair work associated with this project.
WORK HOURS AND COORDINATION
Work shall be performed during normal VA business hours unless otherwise approved by the VA COR. Any required shutdowns, outages, or after-hours work shall be coordinated with the VA COR and VA Telecommunications Department a minimum of seventy-two (72) hours in advance.