This is a Sources Sought Notice for market research purposes that is neither a solicitation nor a request for proposals, and does not obligate the Government to award a contract. The Department of Veterans Affairs (VA) Veterans Health Administration, through the Perry Point VA Medical Center, is seeking qualified contractors to remove abandoned telecommunications equipment, cabling, conduit, and cable pressurization systems from the Main Equipment Room (MER-3) of the Main Hospital Building at the VA Medical Center in Washington, DC. Responses must be submitted in writing by email to jameel.gordon@va.gov with the subject line "Notice ID No. 36C24526Q0853 - Removal of Abandoned Telecommunications Equipment" no later than 11:00 AM EST on September 28, 2026. Interested parties must provide company information including name, address, point of contact, phone/email, SAM Unique Entity ID, CAGE code, tax ID, business type classification, and a detailed Capability Statement demonstrating qualifications and ability to perform the work.

The scope of work requires the contractor to furnish all labor, materials, equipment, tools, permits, and services necessary to safely disconnect and remove abandoned telecommunications infrastructure while ensuring all active systems remain fully operational throughout the project. Work must comply with VA Master Construction Specifications, NFPA 70 (NEC), OSHA requirements, ANSI/TIA standards, and BICSI guidelines. Key deliverables include a demolition work plan, project schedule, safety plan, lockout/tagout procedures, disposal plan, and waste documentation. The contractor must conduct daily quality inspections with three hold points, coordinate with VA personnel and engineering, maintain emergency access, and provide proper disposal documentation and before-and-after photographs. A minimum one-year workmanship warranty is required on all patching, restoration, and repair work. Work shall be performed during normal VA business hours unless otherwise approved, with any required shutdowns coordinated at least 72 hours in advance.

View the file

Other files

File Type Posted
36C24526Q0853.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sources Sought Notice Sources Sought Notice

SUBJECT*
Removal of Abandoned Telecommunications Equipment

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
21902
SOLICITATION NUMBER*
36C24526Q0853
RESPONSE DATE/TIME/ZONE
09-24-2026 3:00PM EASTERN TIME, NEW YORK, USA
ARCHIVE
60 DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
N

SET-ASIDE

PRODUCT SERVICE CODE*
Z1AA
NAICS CODE*
238210
CONTRACTING OFFICE ADDRESS
Department of Veterans Affairs

Perry Point VA Medical Center 361 Boiler House Rd, Building 101C Perry Point, MD 21902

POINT OF CONTACT*

Contracting Officer Jameel Gordon and Mike Wilson jameelgordon@va.gov, Michael.wilson37@va.gov 410-642-2411 ext 26911

PLACE OF PERFORMANCE

ADDRESS
Department of Veterans Affairs

Washington DC VA Medical Center

50 Irving Street NW

Washington, DC 20422

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

AGENCY’S URL
https://www.va.gov/
URL DESCRIPTION
Department of Veteran Affairs
AGENCY CONTACT’S EMAIL ADDRESS
https://www.va.gov/plo/about/saos.asp
EMAIL DESCRIPTION
VHA Procurement & Logistics Office

DESCRIPTION

SOURCES SOUGHT ANNOUNCEMENT: This is a “SOURCES SOUGHT ANNOUNCEMENT ONLY”, it is neither a solicitation announcement nor a request for proposals or quotes and does not obligate the Government to award a contract. Requests for a solicitation will not receive a response. Responses to this sources-sought must be in writing. The purpose of this SOURCES SOUGHT ANNOUNCEMENT is for market research to make appropriate acquisition decisions and to gain knowledge of potential sources capable of providing the services described below.

Documentation on technical expertise must be presented in sufficient detail for the Government to determine that your company possesses the necessary functional area expertise and experience to compete for this acquisition. Responses to this notice shall include the following:

(a) Company name:

(b) Address:

(c) Point of Contact:

(d) Phone, Fax (if applicable), and Email:

(e) SAM Unique Entity ID:

(f) Cage Code:

(g) Tax ID Number:

(h) Type of business, SDVOSB; VOSB, WOSB, small, large, etc., as appropriate:

(i) Must provide a Capability Statement that addresses the organization’s qualifications and ability to perform as a contractor for the statement of work described below. Failure to provide sufficient information may result in the Government’s inability to determine whether the respondent is capable. GENERAL STATEMENTS OF CAPABILITY ARE NOT ACCEPTABLE.

(j) Federal Supply Schedule Contracting # if applicable

(k) General Pricing

All interested parties should submit information by email only to jameel.gordon@va.gov. All emails must have as the subject line, Notice ID No. 36C24526Q0853 - Removal of Abandoned Telecommunications Equipment. All submissions must be received no later than 11:00 AM (EST) on September 28, 2026.

Removal of Abandoned Telecommunications Equipment, Cabling, Conduit, and Cable Pressurization System Department of Veterans Affairs Medical Center Location: Washington, DC

Project Description The Contractor shall furnish all labor, supervision, materials, equipment, tools, permits, transportation, testing, disposal, and all incidental services necessary to safely disconnect, remove, and properly dispose of abandoned telecommunications equipment, cabling, conduit, cable pressurization systems, and associated accessories located within the MER-3 (Main Equipment Room) of the Main Hospital Building at the Department of Veterans Affairs Medical Center, Washington, DC. All work shall be performed in close coordination with the VA Contracting Officer's Representative (COR) and VA Telecommunications personnel to verify that all equipment identified for removal is abandoned and to ensure that active telecommunications systems remain fully operational throughout the duration of the project. The Contractor shall take all necessary precautions to prevent interruption of existing telecommunications, life safety, security, and other critical building systems. The Contractor shall perform all work in accordance with applicable VA standards and industry best practices.

APPLICABLE STANDARDS

Work shall conform to the latest adopted editions of the following:

· VA Master Construction Specifications

· NFPA 70 (NEC)

· OSHA Requirements

· ANSI/TIA Telecommunications Standards (where applicable)

· BICSI Telecommunications Distribution Methods Manual (TDMM)

· Applicable Federal, State, Local, EPA, and VA requirements

EXISTING CONDITIONS AND CONTRACTOR RESPONSIBILITY

Contractor shall field verify existing conditions prior to bidding and report discrepancies to the VA COR. Active systems shall remain operational unless approved otherwise.

SUBMITTALS

· Demolition work plan

· Project schedule/phasing plan

· Safety plan

· Lockout/Tagout procedures

· Disposal plan

· Restoration materials

· Waste documentation (if applicable)

DEMOLITION

· Verify with the VA COR that all equipment identified for removal is abandoned.

· Remove abandoned telecommunications equipment including cabinets, racks, Motorola cabinets, control panels, power supplies, and mounting hardware.

· Remove abandoned copper, fiber optic, coaxial, communication, control, and low-voltage cabling.

· Remove abandoned exposed conduit. Concealed conduit may remain only with written COR approval.

· Remove abandoned junction boxes, pull boxes, cable trays, wireways, supports, hangers, brackets, and hardware.

· Remove abandoned cable pressurization systems including tanks, regulators, manifolds, valves, tubing, piping, fittings, supports, wiring, and accessories.

· Disconnect equipment from electrical and communication systems prior to demolition.

· Protect active electrical, fire alarm, security, nurse call, BAS, paging, and telecommunications systems.

· Patch wall penetrations and restore disturbed finishes to match adjacent surfaces.

· Dispose of removed materials off-site in accordance with all regulations.

· Submit waste manifest(s) and disposal documentation to VA COR upon completion of the project as evidence of proper disposal.

· Clean work areas daily and upon project completion.

PROTECTION OF EXISTING SYSTEMS

The Contractor shall protect all existing systems that are to remain in service, including:

· Fire Alarm

· Nurse Call

· Security

· Access Control

· Building Automation System (BAS)

· Public Address/Paging

· Fiber Backbone

· Active Data Networks

· Any damage to active systems shall be immediately repaired or replaced by the Contractor at no additional cost to the Government.

FIELD VERIFICATION

Investigate all telecommunications infrastructure before demolition. Equipment of uncertain operational status shall remain until written direction is received from the VA COR.

QUALITY ASSURANCE AND HOLD POINTS

· Daily quality inspections

· Hold Point 1 – Initial demolition area

· Hold Point 2 – Mid-project inspection

· Hold Point 3 – Final acceptance walkthrough

SAFETY, ACCESS, AND PHASING

· Coordinate outages with VA Engineering.

· Maintain emergency access.

· Provide barricades and dust control.

· Follow Lockout/Tagout procedures.

· Comply with applicable VA Interim Life Safety Measures (ILSM) and Infection Control Risk Assessment (ICRA) requirements when directed by the VA.

· Minimize disruption to hospital operations.

CLEANUP AND CLOSEOUT

· Remove all debris, abandoned cabling, conduit, equipment, dust, and miscellaneous materials daily.

· Leave MER-3 in broom-clean condition.

· Restore disturbed finishes.

· Provide disposal documentation (if required).

· Provide before-and-after photographs.

· Complete final punch list and final walkthrough with the VA COR.

WARRANTY

Provide a minimum one (1) year workmanship warranty on all patching, restoration, and repair work associated with this project.

WORK HOURS AND COORDINATION

Work shall be performed during normal VA business hours unless otherwise approved by the VA COR. Any required shutdowns, outages, or after-hours work shall be coordinated with the VA COR and VA Telecommunications Department a minimum of seventy-two (72) hours in advance.

END OF STATEMENT OF WORK