This is a Request for Quote (RFQ) issued by the Department of Veterans Affairs for the demolition and removal of Trailer 363T located at the Perry Point VA Medical Center in Perry Point, Maryland. The solicitation (RFQ number 36C24525Q0828) seeks a contractor to provide services for total demolition, removal, regrading, and off-site disposal of an existing double-wide trailer constructed in 1996, covering approximately 1,416 square feet. The trailer is considered structurally unsound due to groundhog and water damage to support piers.

Key details include a period of performance from 09/25/2025 to 09/24/2026, with questions due by 09/10/2025 at 9AM EST and quotes due by 09/12/2025 at 9AM EST. The contract is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 236220 with a size standard of $45 Million. The solicitation requires the contractor to handle all demolition work, including removal of attached structures like concrete steps, concrete pads, and roof structures, while VA will disconnect utilities beforehand. The evaluation will be based on technical approach, past performance, and price, with technical and past performance combined being equal to price.

View the file

Other files

File Type Posted
36C24525Q0828 0001_1.docx DOCX document
Site Map.pdf PDF
36C24525Q0828 0001 1.pdf PDF
Att 5 - VA Perry Point 9H 363T FP Roof Sampling rpt.pdf PDF
Att 4 - VA Summary Report Bldg 363T.pdf PDF
Trailer Flr Plan.pdf PDF
Att 2 Trailer 363T Pictures.pdf PDF
Sanitary Sewer Map.pdf PDF
36C24525Q0828_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE 1 of

633OF63

1. REQUISITION NO.

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL

TIME

9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

8(A)

NAICS:

SIZE STANDARD:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ IFB RFP

15. DELIVER TO CODE 16. ADMINISTERED BY CODE

17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE

TELEPHONE NO. UEI: EFT:

PHONE: FAX:

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED

SEE ADDENDUM

19. 20. 21. 22. 23. 24.

ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION (REV. NOV 2021)

PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212

7. FOR SOLICITATION

INFORMATION CALL:

STANDARD FORM 1449

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

512-25-3-444-0377

36C24525Q0828 09-03-2025

Crystal Brown 410-642-2411 09-12-2025

9AM EDT

19ACQ

Department of Veterans Affairs

VAMC

10 N Greene St

Baltimore MD 21201

X 100

X

236220

$45 Million

N/A

X

VAMC(512)

Perry Point MD 21902

19ACQ

VAMC

10 N Greene St

Baltimore MD 21201

Vendor is to complete E.2

Addendum Instructions to Offerors

PAYMENT WILL BE MADE BY

FSC e-Invoice Payment

Invoice must be submitted electronically http://www.fsc.va.gov/einvoice.asp

Invoice Setup Information 1-877-489-6135

See CONTINUATION Page

Contractor is to Demolish and Remove Trailer 363T per the attached Statement of Work.

The period of performance is 09/25/2025 - 09/24/2026.

Questions are due 09/10/2025 by 9AM EST.

Quotes are due 09/12/2025 by 9AM EST.

**MUST RESPOND TO QUESTIONS AT THE END OF THE STATEMENT

OF WORK.

Questions and Quotes are to be emailed with the RFQ number in the subject line to Crystal.Brown5@va.gov

See CONTINUATION Page

X X

X 1

Crystal Brown

NCO515L1 65674

36C24525Q0828

Table of Contents

SECTION A

A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS

AND COMMERCIAL SERVICES

SECTION B - CONTINUATION OF SF 1449 BLOCKS

B.1 CONTRACT ADMINISTRATION DATA

B.2 STATEMENT OF WORK

B.3 PRICE/COST SCHEDULE

ITEM INFORMATION

SECTION C - CONTRACT CLAUSES

C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS

AND COMMERCIAL SERVICES (NOV 2023)

C.2 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED

SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)

(DEVIATION)

C.3 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)

(DEVIATION)

C.4 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV

2018)

C.5 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)

C.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

C.7 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT

STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND

COMMERCIAL SERVICES (JAN 2025) (DEVIATION FEB 2025)

SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS

D.1 TRAILER PICTURES

D.2 FLOOR PLAN

D.3 SEWER MAP

SECTION E - SOLICITATION PROVISIONS

E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND

COMMERCIAL SERVICES (SEP 2023)

E.2 52.212-1 ADDENDUM INSTRUCTIONS TO OFFERORS

E.3 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS

AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

E.4 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT

ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023)

E.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB

1998)

E.6 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL

SERVICES (NOV 2021)

E.7 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—

COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY 2024) (DEVIATION

FEB 2025)

SECTION B - CONTINUATION OF SF 1449 BLOCKS

B.1 CONTRACT ADMINISTRATION DATA

1. Contract Administration: All contract administration matters will be handled by the following individuals:

a. CONTRACTOR:

b. GOVERNMENT: Contracting Officer 36C245

VAMC

10 N Greene St

Baltimore MD 21201

2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:

[X] 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or

[] 52.232-36, Payment by Third Party

3. INVOICES: Invoices shall be submitted in arrears:

a. Quarterly []

b. Semi-Annually []

c. Other [X] At completion

4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment

Requests.

ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:

AMENDMENT NO DATE

B.2 STATEMENT OF WORK

Scope of Work Demolish and Remove Trailer 363T

1. OVERVIEW —

1.1 Government Agency Department and Address:

VA Maryland HealthCare System – VISN5 – Perry Point VAMC – Perry Point, MD 21902

1.2 Project Title, Number and Location:

Project Title: Demolish and Remove Trailer 363T

1.3 Scope of Work

Trailer 363T is structurally unsound and a safety hazard due to groundhog and water damage to several of the support piers. Provide services necessary for the total demolition, removal, regrading, and off-site disposal of the existing double-wide Trailer 363T, located at the Perry

Point VA Medical Center. The scope shall also include the demolition, removal and off-site disposal of all attached structures such but not limited to the existing concrete steps, concrete pads, metal roof above steps, and entry roof columns including foundations. The single level double wide Trailer 363T was constructed in 1996 with a square footage of approximately 1,416 square feet. The overall outside face of wall dimension is approximately 23.5 feet by 60.25 feet

(. Trailer 363T consists of interior office spaces, a conference room, and a unisex toilet room.

VA shall disconnect all existing utilities for the trailer before demolition can begin. Known utilities include a main power feed, piped sanitary and domestic water. Remove all furniture, fixtures, and miscellaneous accessories for off-site disposal. The existing trailer is supported by typical steel beams usually provided with trailers that are supported on concrete block piers. Due to known groundhog disturbance issues around and below the trailer, care shall be taken during demolition work to avoid further grading issues. There is an existing sanitary sewer pipe currently running diagonally below Trailer 363T. Confirm the exact location of the existing sanitary sewer pipe to avoid possible conflicts and/or pipe damage before proceeding with the trailer removal. Regrading and backfilling shall only be performed as necessary to safely remove Trailer 363T. Backfill and compaction required to safely remove Trailer 363T must be done is 1-to-2-foot lifts suitable for typical compactions requirements. Final grading shall be smooth and free of stones/debris. Before any regrading and backfilling can be provided, all known ground disturbances must be documented and discussed with the COR. VA shall perform all other regrading and backfilling not necessary to safely remove Trailer 363T. Also, VA shall establish vegetation upon removal of Trailer 363T by the contractor. Previous samplings of possible asbestos collected by Aerosol Monitoring & Analysis, Inc. (AMA) of suspect materials within trailer 363T revealed No Asbestos.

1.4 Work Items Under this Task Order

Offers are to submit proposals based on the project specifications and drawings provided under the project solicitation. The resulting total bid amount shall then be broken down item by item for review of quantities, unit costs, and labor costs.

Contractor shall make arrangements to visit the site to survey existing conditions and to determine the methods of the work to be performed prior to submitting proposal.

Work items under this task order include the following but is not limited to:

• Complete all demolition work as detailed in this SOW. All work and materials shall be in accordance with the attached construction specifications. Contractor shall be responsible for adherence to all VA and OSHA construction safety requirements pertaining to the project scope as described in the project drawings and specifications.

• Unless noted otherwise, all new surface repair work shall match the existing adjacent work as much as practical.

• Work Site Protection and Administration shall be included.

• Warranty on new work shall be good for a period of 1 year from date of completion per FAR unless otherwise stated.

• Removal and Disposal and/or recycling of all demolished building materials and construction waste per applicable regulations shall be included. Manifests/disposal/recycle tonnage must be summarized and reported to the COR.

• Contractor shall be responsible for all material deliveries, storage, and the coordination of deliveries. Over-height and over-weight restrictions are in place in one or all of the site access points.

• Contractor responsible for all temporary site operations facilities, including temporary utility connections, temporary worker restrooms/port-o-johns, field office, storage areas/CONEX boxes, etc. Contractor shall provide total site security measures.

• Contractor shall be responsible for providing and maintaining all aspects of construction site safety including but not limited to:

o Fire Extinguishers o Construction site fencing and access control o Refer to Specification 01 00 00 General Requirements for all requirements pertaining to the project including the availability and usage of government provided utilities.

o Refer to specification 01 33 23 Shop Drawings, Product Data, and Samples for project submittal requirements.

1.5 Additional Terms and Conditions

1.5.1 Schedule

Please review specification section 01 32 16.15 for requirements for schedule. Please note that the contractor’s bid proposal provided at the time of bid due date shall require a draft CPM schedule. The intent is to proceed with submittals immediately after contract award, submittals for the long lead items shall be developed, provided, and reviewed.

A project Notice to Proceed (NTP) is planned to be issued roughly 30 days post award.

Contractor shall mobilize onsite beginning construction within 15 days of NTP issue. The contractor shall have (30) Thirty calendar days to complete all work including closeout. See below chart for NTP:

ID Milestone Task Description Duration Schedule

Date

1 Project NTP 1 Day Award + 30

2 Site Mobilization 1 Day NTP + 1

3 Complete all work 15 Days NTP + 16

4 Project Close-out 14 Days NTP + 30

Liquidated Damages (LD) per (FAR 11.5) are provided in contract documents.

1.5.2 Pricing and Payment

1.5.2.1 This project will be deemed complete when all of the required tasks outlined in this SOW are complete and function as intended by design; the work shall be completed within the areas defined in this document. The VA will complete a final walk-through and inspection of all work before processing final payment.

1.5.2.2 The contractor may submit progress payment invoices according to the Contracting

Officer’s specifications at intervals acceptable to the VA. These progress payments will be substantiated by the COR inspections and the daily logs submitted by the contractor.

A schedule of values will need to be submitted and approved.

1.5.2.3 Progress payment invoices shall be sent via email to the COR for approval and payment.

1.5.2.4 Final payment will not be processed until final walk-through and approval is complete which includes all punch list items.

1.6 Construction Requirements

1.6.1 The Contractor shall have the skills, availability, capacity and all other required resources required to complete the job on time without delay.

1.6.2 All site contractors shall have completed the Occupational Safety & Health

Administration (OSHA) approved 10-hour construction safety training.

1.6.3 Mechanical and Plumbing contractors shall have technical training and demonstrable track records of working experience in construction, inspection, and testing of plumbing systems and related components in healthcare, industrial, educational, and commercial facilities. Contractor must hold a current license by the State of Maryland as a licensed Master Plumber/Gas Fitter or approved by COR.

1.6.4 All work is to shall be in compliance with local, state and federal rules and regulations, and VA technical standards. Compliance is to whichever rule or regulation is the most stringent. VA Master Specifications shall be used as the default when no specifications are issued and when a referenced specification is not found in the projects RFP package, they are at https://www.cfm.va.gov/til/.

The intent of the default specifications is to furnish concise industrial and/or commercial standards for construction of Government facilities. If the Statement of Work does not address a specification for an element of the work, the default specification shall apply for the element of work as approved by COR. The omittance of a VA specification, does not relieve the contractor to perform required work under the base task order cost proposal.

1.6.5 Provide daily on-site project management to coordinate all building trades and provide liaison for construction and VA Project Engineering. General Foreman will be designated and be on-site at all times.

1.6.6 All employees of contractor shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and be restricted from unauthorized access. VA issued ID Badges shall be worn by all workers while within the campus boundaries. Contractor shall make all necessary arrangements to obtain the required badging prior to commencement of work. VA issued ID Badges shall be worn by all workers at all times.

1.6.7 Follow all Infection Control Risk Assessment (ICRA) guidelines for dust control during all construction and demolition work.

1.6.8 Follow Interim Life Safety Measures (ILSM). Any series of Operational Actions taken to temporarily reduce hazards posed by Life Safety deficiencies which have been created by demolition, renovation, or construction works, and which are to remain in place and in effect for duration of Contract work. Provide ILSM where fire protection, fire suppression or smoke/fire partitions will be shut down or rendered ineffective during construction. Coordinate with VA safety office through COR. ILSM must be posted outside work area at all times.

1.6.9 All equipment and materials shall be approved prior to being brought on job site.

1.6.10 Normal work hours are 7:00am to 3:30pm, Monday to Friday. Contractor shall make prior arrangements to work earlier or later with COR. Also, contractor shall make arrangements for subcontractors to work in secured areas. VA will not grant access to subcontractors, it is the responsibility of the contractor.

1.6.11 Daily logs shall be submitted to the COR the Monday following each week worked.

1.6.12 When using special keys for access to roof, mechanical and electrical areas, doors must be kept closed and locked while in such spaces.

1.6.13 Contractor must obtain a burn permit from VA Safety Office / Fire Dept prior to any welding, flame cutting, soldering work, and burning.

1.6.14 The work performed shall be in a professional environment, employees must conduct themselves accordingly. Employees shall not use abusive language, carry firearms, or bring alcoholic beverages on site. Employee's dress code shall consist of normal work uniform. Shirts must be worn at all times.

1.6.15 Contractor shall provide general clean up to construction area daily to the satisfaction of the COR.

1.6.16 Remove demolished equipment and restore site.

1.6.17 Hospital smoking policy (NO SMOKING ON CAMPUS).

1.6.18 OSHA and VA CONSTRUCTION SAFETY STANDARDS will be enforced.

Contractor Supervisor must have 30-hour OSHA Construction Safety course. All contractor employees must have 10-hour OSHA Construction Safety course.

1.6.21 For quality control, the individual may not carry dual roles in the construction project. The VA shall require a person with QC/QA background that there only role is to validate that the construction meets or exceeds requirements of the contract. This person will generate a final punch list and provide to the COR.

Then the COR will schedule review the completed job with contractor or/and code officials to generate a punch list. The QC inspector shall provide summary to the COR on a weekly basis with inspection sheets and corrections or commented.

2.0 Safety and Environmental Precautions

2.1. The Contractor shall comply with all applicable Federal, State and local legal requirements regarding workers health and safety. The requirements include but are not limited to, those found in Federal and State Occupational Safety and

Health Act (OSHA) statutes and regulations, such as applicable provisions of

Title 29, Code of Federal Regulations (CFR) Parts 1910 and 1926. Contractor is solely responsible for determining the legal requirements that apply to activities, and shall ensure safe and healthful working conditions for its employees.

2.2. Contractor shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government Property.

2.3. The Contractor shall perform the work in a manner consistent with the area security and fire safety regulations especially with regard to exits and exit way access. Utility shutdowns shall not compromise security, communication or fire safety for occupants. Egress must be maintained for contract workers per OSHA.

2.4. No flammable liquids shall be stored or used in the medical center.

2.5. The necessary number and appropriate types of portable fire extinguishers are required per National Fire Protection Agency (NFPA) 10 and NFPA 241.

2.6. The Contractor shall receive from the station fire department a permit for all cutting, welding, and soldering. All permits shall be prominently displayed during all construction. Permits must be opened at the start of each activity and closed at the end of each workday.

2.7. All necessary precautions shall be taken by the contractor to prevent accidental operation of any existing smoke detectors or sprinkler heads.

2.8. Contractor shall be responsible for operational actions taken to temporarily reduce the hazard posed by life safety deficiencies created during and until completion of construction.

2.9. In order to provide for control of all environmentally hazardous materials arising from demolition and/or construction activities, the Contractor shall comply with all applicable environmentally hazardous material control and all applicable provisions of the Corps of Engineers’ Manual EM 385-1-1, “General Safety

Requirements” as well as the specific requirements stated elsewhere in the

Contract Documents.

2.10. All overhead lifts shall comply to VA requirements which may include off shift/days lifts (IE weekends) as scheduled and approved by COR.

2.11. Site mobilization area: The site mobilization area will be designated prior to the start of work. Area shall be fixed fence and be secured to allow access only to authorized personnel. A job board with required permits, bulletins or site documentation shall be installed in area that can be visibly observed by the general public. Temporary walk path (stone or other means) shall be provided if contractor places office trailer in the area. No material tracking onto the sidewalk or roadways is allowed. Area shall be repaired with topsoil and hydroseed when weather conditions allow. No material shall be allowed to be wind blown off the site. Housekeeping of the area shall be performed daily or as required.

Contractor is required for any snow removal and protection of assets. All material/equipment shall be covered and protected from weather elements.

Sidewalk must always be accessible. Keys must be provided to the VA for any locked fences or other areas as deemed by the COR.

3.0 Waste Disposal and Management

All waste will be properly handled and disposed of in an environmentally sound manner and will comply with local and federal guidelines. Keeping the premises free from debris is a key component to maintaining a safe work environment. Below are the types of waste and the process for each.

3.1 General Non-Hazardous Waste

3.1.1 A construction project generates waste either from the parts that are removed or from the packaging of the new products being installed. The contractor shall ensure that all installation debris and product packaging is removed from the work area and placed in trash receptacles that the contractor provides.

3.1.2 This waste will be transported and disposed of by the contractor’s waste management company.

3.1.3 Comply with VA Master Specification 017419 Construction Waste Management. This specification identifies materials that MUST be recycled or reused during construction and demolition projects. Additionally, VHA requires that 50% of demolition debris be diverted from the solid waste stream. Contractor shall document all disposal records or recycling records, with quantity and destination of all waste streams.

3.2 Hazardous Waste (Includes but not limited to Lead and Lead-Based Paint

Wastes)

3.2.1 The contractor must dispose of all universal wastes that does not remain intact as hazardous waste per EPA hazardous waste guidelines (40 CFR 260-299) and

COMAR 26 Subtitles 13-18. The contractor must also dispose of all hazardous wastes per EPA hazardous waste guidelines (40 CFR 260-299) and COMAR 26

Subtitles 13-18.

3.2.2 All required paperwork such as hazardous waste profiles, hazardous waste manifests and land disposal restriction (LDR) forms that go with the hazardous waste manifests will be filled out by a MD licensed, hazardous waste subcontractor. The contractor will schedule and coordinate hazardous waste removal with VAMHCS Safety personnel. Hazardous waste manifests will be signed by ONLY a VAMHCS employee with DOT RCRA training certification

(please contact VAMHCS GEMS Manager) and a copy provided to the VAMHCS

GEMS Manager for the specific VAMHCS facility. Final signed manifests must be received by the VAMHCS from the hazardous waste Treatment, Storage, and

Disposal Facility within 45 days of waste shipment per EPA 40 CFR 263.20-.25 as well as Code of Maryland Regulations (COMAR) 26.13.03.06.

3.4.3 Comply with EPA and MDE requirements for proper handling (such as bagging, sealing and recycling) Mercury-Containing Devices (may include but are not limited to thermometers, manometers, pressure stats, gauges, float or level controls, load meters, supply relays, phase splitters, and sink traps) per 40 CFR

273 and COMAR 26.13.02.08, 26.13.10.06, 26.13.10.09 and 26.13.10.20,

26.13.10.21 and 26.13.10.26 or latest requirements.

3.4.4 All hazardous waste expected as a result of renovation, demolition or construction activities (including but not limited to mercury-containing dental amalgam wastes, fluorescent bulbs, electrical devices that contain PCBs) must be properly managed and disposed in accordance with EPA and MDE requirements per EPA 40 CFR 260-299 as well as COMAR 26.13.02.01, 26.13.02.08, 26.13.10.20, 26.13.10.21 and 26.13.10.26 or latest requirements.

3.4.5 Records of hazardous waste disposal (such as manifests, hazardous waste profiles, LDRs) must be provided by approved waste transporter and signed by an approved VAMHCS Manifest signer from the VAMHCS Safety Department.

All records provided to COR and VAMHCS GEMS Coordinator at

VAMHCSGEMSProgram@va.gov

3.4.6 All hazardous chemicals that need to remain at the job site must be stored and handled in accordance with EPA; MDE; OSHA and NFPA requirements

3.4.7 Contractor must adhere to the lead in construction standard (29 CFR 1926.62(a) where lead is encountered in the course of work. If any lead is present, these regulations apply. The employer (contractor) must determine if employees will be exposed above the Permissible

Exposure Limit for lead.

7. ATTACHMENTS – In addition to this Scope of Work, the following separate solicitation attachments are considered to be crucial to development of the demolition contractor proposal and should be referenced as in-scope conditions.

Attachment 1: Trailer 363T Floor Plan 1 page

Attachment 2: Trailer 363T Pictures 3 pages

Attachment 3: Sanitary Sewer Location Map 1 page

Attachment 4: Trailer 363T Asbestos Report dated March 2018 23 pages

Attachment 5: Trailer 363T Asbestos Report dated June 2023 14 pages

MANDATORY QUESTIONS

8. Confirmation that your organization has the capability & expertise to meet the performance requirements while complying with applicable limitations in subcontracting by responding to the questions below with your response:

a. Do you intend to self-perform this effort?

b. If you are located outside the immediate area, how will you self-perform?

c. Or, do you intend to subcontract work under this contract?

d. If you intend to subcontract work under this contract, how will you ensure compliance with the limitations on subcontracting?

- - - E N D S OW- - -

B.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBE

R

DESCRIPTION OF

SUPPLIES/SERVIC

ES

QUANTIT

Y

UNI

T UNIT PRICE AMOUNT

1.00 JB ________________

Provide services necessary for the total demolition, removal, regrading, and off-site disposal of the existing double-wide Trailer 363T, located at the Perry Point VA Medical Center.

Also, include the demolition, removal and off-site disposal of all attached structures such but not limited to the existing concrete steps, concrete pads, metal roof above steps, and entry roof columns including foundations.

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: P400 - Salvage - Demolition of Buildings

LOCAL STOCK NUMBER: 0

GRAND TOTAL ________________

SECTION C - CONTRACT CLAUSES

C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL

PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The

Government must exercise its post-acceptance rights—

(1) Within a reasonable time after the defect was discovered or should have been discovered;

and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims

Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the

Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the

Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the

Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by

Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.—

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt

Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-

5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting

Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the

Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the

Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The

Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the

Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain

Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with

Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments

(9) The specification.

(t) [Reserved]

(u) Unauthorized Obligations.

(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service

(TOS), or similar legal instrument or agreement, that includes any clause requiring the

Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of Clause)

ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL

PRODUCTS AND COMMERCIAL SERVICES

Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.

The following clauses are incorporated into 52.212-4 as an addendum to this contract:

(End of Addendum to 52.212-4)

C.2 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED

SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)

(DEVIATION)

(a) Definition. for the Department of Veterans Affairs, ‘‘Service-disabled Veteran-owned small business concern or SDVOSB’’:

(1) Means a small business concern—

(i) Not less than 51 percent of which is owned by one or more service-disabled Veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled Veterans or eligible surviving spouses (see VAAR

802.201, Surviving Spouse definition);

(ii) The management and daily business operations of which are controlled by one or more service-disabled Veterans (or eligible surviving spouses) or, in the case of a service-disabled

Veteran with permanent and severe disability, the spouse or permanent caregiver of such

Veteran;

(iii) The business meets Federal small business size standards for the applicable North

American Industry Classification System (NAICS) code identified in the solicitation document;

(iv) The business has been certified for ownership and control pursuant to 38 U.S.C. 8127, 13 CFR 128, and is listed as certified in the SBA certification database at https://veterans.certify.sba.gov/; and

(v) The business agrees to comply with VAAR subpart 819.70 and Small Business

Administration (SBA) regulations regarding small business size, government contracting, and the Veteran Small Business Certification Program at 13 CFR parts 121, 125, and 128.

(2) The term ‘‘Service-disabled Veteran’’ means a Veteran, as defined in 38 U.S.C. 101(2), with a disability that is service-connected, as defined in 38 U.S.C. 101(16).

(3) The term ‘‘small business concern’’ has the meaning given that term under section 3 of the Small Business Act (15 U.S.C. 632).

(4) The term ‘‘small business concern owned and controlled by Veterans with service-connected disabilities’’ has the meaning given the term ‘‘small business concern owned and controlled by service-disabled veterans’’ under section 3(q)(2) of the Small Business Act (15

U.S.C. 632(q)(2)).

(5) The term “SDVOSB participant” or certified SDVOSB means a small business that has been certified in the SBA Veteran Small Business Certification Program and listed in the SBA certification database (see 13 CFR 128.102).

(b) General. In order for a concern to submit an offer and be eligible for the award of an

SDVOSB set-aside or sole source contract, the concern must qualify as a small business concern under the size standard corresponding to the NAICS code assigned to the contract and be listed as an SDVOSB participant in the SBA certification database as set forth in 13 CFR

128.

https://veterans.certify.sba.gov/

(1) Offers received from entities that are not certified SDVOSBs and listed in the SBA certification database at the time of offer shall not be considered.

(2) Any award resulting from this solicitation shall be made to a certified SDVOSB listed in the

SBA certification database who is eligible at the time of submission of offer(s) and at the time of award.

(3) The requirements in this clause apply to any contract, order or subcontract where the firm receives a benefit or preference from its designation as an SDVOSB, including set-asides, sole source awards, and evaluation preferences.

(c) Representation. Pursuant to 38 U.S.C. 8127(e), only certified SDVOSBs listed in the SBA certification database are considered eligible to receive award of a resulting contract. By submitting an offer, the prospective contractor represents that it is an eligible and certified

SDVOSB as defined in this clause, 13 CFR 121, 125, and 128, and VAAR subpart 819.70.

(d) Agreement/LOS certification. When awarded a contract action, including orders under multipleaward contracts, an SDVOSB agrees that in the performance of the contract, the

SDVOSB shall comply with requirements in VAAR subpart 819.70 and SBA regulations on small business size, and government contracting programs at 13 CFR part 121 and part 125, including the non-manufacturer rule and limitations on subcontracting (LOS) requirements in 13

CFR 121.406(b) and 13 CFR 125.6. For the purpose of limitations on subcontracting, only certified SDVOSBs listed in the SBA certification database (including independent contractors) shall be considered eligible and/or ‘‘similarly situated’’ (i.e., a firm that has the same small business program status as the prime contractor). An otherwise eligible firm further agrees to comply with the required LOS certification requirements in this solicitation (see 852.219–75 or

852.219–76 as applicable). These requirements are summarized as follows:

(1) Services. In the case of a contract for services (except construction), the SDVOSB prime contractor will not pay more than 50% of the amount paid by the government to the prime for contract performance to firms that are not certified SDVOSBs listed in the SBA certification database (excluding direct costs to the extent they are not the principal purpose of the acquisition and the SDVOSB/ VOSB does not provide the service, such as airline travel, cloud computing services, or mass media purchases). When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.

(2) Supplies/products.

(i) In the case of a contract for supplies or products (other than from a non-manufacturer of such supplies), the SDVOSB prime contractor will not pay more than 50% of the amount paid by the government to the prime for contract performance, excluding the cost of materials, to firms that are not certified SDVOSBs listed in the SBA certification database. When a contract includes both supply and services, the 50 percent limitation shall apply only to the supply portion of the contract.

(ii) In the case of a contract for supplies from a non-manufacturer, the SDVOSB prime contractor will supply the product of a domestic small business manufacturer or processor, unless a waiver as described in 13 CFR 121.406(b)(5) has been granted. Refer to 13 CFR

125.6(a)(2)(ii) for guidance pertaining to multiple item procurements.

(3) General construction. In the case of a contract for general construction, the SDVOSB prime contractor will not pay more than 85% of the amount paid by the government to the prime for contract performance, excluding the cost of materials, to firms that are not certified

SDVOSBs listed in the SBA certification database.

(4) Special trade construction contractors. In the case of a contract for special trade contractors, no more than 75% of the amount paid by the government to the prime for contract performance, excluding the cost of materials, may be paid to firms that are not certified

SDVOSBs listed in the SBA certification database.

(5) Subcontracting. An SDVOSB subcontractor must meet the NAICS size standard assigned by the prime contractor and be certified and listed in the SBA certification database to count as similarly situated. Any work that a first tier SDVOSB subcontractor further subcontracts will count towards the percent of subcontract amount that cannot be exceeded. For supply or construction contracts, the cost of materials is excluded and not considered to be subcontracted.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .