36C24525Q0633-AMEND 1-UPDATED SOW-SDVOSB-HVAC REPAIRS IT DATA ROOMS-DC VMAC.pdf
PDF 89 KB Posted
- Solicitation number
- 36C24525Q0633
About this file
This Statement of Work (SOW) details HVAC repairs for IT rooms and closets at the Washington DC VA Medical Center. The project requires installing Variable Air Volume (VAV) and Dual Duct terminal boxes in three specific locations: 1C-112, 3C-119, and 1E-236. The contractor must provide and install one VAV box without reheat in the 1C-112 and 3C-119 IT Closets, connecting them to existing cold deck supply ductwork. In the 1E-236 Suite area, six Dual Duct terminal boxes must be installed, each matching the capacity of existing equipment and equipped with factory-installed Direct Digital Controls (DDC). Additionally, a 350 CFM VAV box must be installed in the 1E-236 IT Closet.
The scope includes integrating all new terminal boxes into the existing building automation system (BAS), with all controls to be completed by Siemens Control BAS. The contractor is responsible for providing necessary equipment, ductwork modifications, controls, and integration, ensuring compatibility with the facility's systems. Requirements include submitting equipment approvals, providing as-built drawings and O&M manuals, and training VA staff. Safety and security protocols must be followed, including proper badging, infection control, and protection of sensitive IT equipment. The project will be coordinated with VA Engineering and IT staff to minimize operational disruptions, with specific points of contact provided: Daniel Pollard (Project Manager) and Lonnell Roberts (Engineering Supervisor).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24525Q0633-AMEND 1-QnA-SDVOSB-HVAC REPAIRS IT DATA ROOMS-DC VMAC.pdf | ||
| 36C24525Q0633 0001_1.docx | DOCX document | |
| 36C24525Q0633 0001-AMEND 1-DATA ROOMS ADD ROOMS TO SOW.pdf | ||
| VA Campus Map.pdf | ||
| WAGE DETERMINATION.pdf | ||
| 36C24525Q0633_1.docx | DOCX document | |
| S02-36C24525Q0633-SDVOSB-HVAC REPAIRS IN IT DATA ROOMS-DC VMAC.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
IT Room and IT Closet HVAC Repairs
Washington DC VA Medical Center
Locations: 1E-236 Suite & IT Closet, 3C-119 IT Closet, 1C-112 IT Closet
1.0 INTRODUCTION
This Statement of Work (SOW) outlines the requirements for the supply and installation of Variable Air Volume (VAV) and Dual Duct terminal boxes to improve environmental control in the IT Room Suite 1E-236 and IT Closets 1E-236, 3C-119, and 1C-112 at the Washington DC VA Medical Center.
2.0 SCOPE OF WORK
The contractor shall provide all labor, materials, equipment, supervision, and incidentals necessary to:
- Supply and install VAV boxes (without reheat) in 1C-112 and 3C-119 IT Closets, connecting them to the existing cold deck supply ductwork.
- In the 1E-236 Suite area, supply and install six (6) Dual Duct terminal boxes, each with matching capacity to the existing equipment. All boxes must be equipped with factory-installed Direct Digital Controls (DDC).
- In the 1E-236 IT Closet, supply and install a VAV box with a capacity of 350 CFM, connected to the appropriate supply ductwork.
- Integrate all new terminal boxes into the existing building automation system (BAS) as required.
- All controls must be completed by Siemens Control BAS for proper operation.
- Test and commission all equipment for proper operation.
3.0 DETAILED REQUIREMENTS
3.1 1C-112 and 3C-119 IT Closets
- VAV Boxes:
- Provide and install one (1) VAV box (no reheat) in each IT Closet.
- Each VAV box must be connected to the existing cold deck supply ductwork.
- VAV boxes must be sized appropriately for the room load, coordinate with VA Engineering for confirmation.
- All VAV boxes must be compatible with the facility’s BAS/DDC system.
- Include all necessary controls, actuators, and sensors.
3.2 1E-236 Suite Area
- Dual Duct Terminal Boxes:
- Provide and install six (6) Dual Duct terminal boxes.
- Each box must have matching capacity to the existing box it replaces (coordinate with VA Engineering for confirmation of sizes).
- All boxes must be factory-equipped with DDC controls compatible with the facility’s
BAS.
- Provide all necessary ductwork modifications, controls, and integration.
3.3 1E-236 IT Closet
- VAV Box:
- Provide and install one (1) VAV box with a capacity of 350 CFM.
- Connect to the appropriate supply ductwork (cold deck).
- Ensure full integration with BAS/DDC.
3.4 Controls and Integration
- All VAV and Dual Duct terminal boxes must be equipped with factory-installed DDC controls.
- Integrate all new devices into the existing building automation system.
- Provide programming, point mapping, and graphics as required for full BAS functionality.
- Test and commission all controls.
3.5 General Installation
- All work must comply with VA standards, local codes, and manufacturer’s recommendations.
- Contractor shall coordinate all shutdowns and tie-ins with VA Engineering and IT staff to minimize disruption to operations.
- Contractor is responsible for all patching, painting, and restoration of finishes affected by the work.
3.6 Documentation
- Provide submittals for all equipment and controls for VA approval prior to installation.
- Submit as-built drawings, O&M manuals, and warranty documentation upon completion.
- Provide training to VA staff on operation and maintenance of new equipment.
3.7 Cleanup
- Remove all debris and restore work areas to the original condition.
- Dispose of all waste in accordance with facility and environmental regulations.
4.0 SCHEDULE
- All work to be scheduled in coordination with VA Engineering and IT to avoid disruption to critical services.
- Work to be completed within [Insert number] days of Notice to Proceed.
5.0 SAFETY & SECURITY
- Contractor must comply with all VA, OSHA, and facility safety requirements.
- All personnel must be properly badged and escorted as required.
- Infection control and protection of sensitive IT equipment and data must be always maintained.
6.0 POINTS OF CONTACT
- VA Project Manager: DANIEL POLLARD, 202-745-2356, Daniel.Pollard@va.gov
- VA Engineering Supervisor: LONNELL ROBERTS, 202-745-7698, Lonnell.Roberts@va.gov mailto:Daniel.Pollard@va.gov mailto:Lonnell.Roberts@va.gov