This document contains questions and answers related to a request for quote (RFQ) from the Department of Veterans Affairs (VA) for National Pollutant Discharge Elimination System (NPDES) General Permit support services at two VA medical centers in Maryland. The services include updating mapping and reports for the medical centers' small municipal separate storm sewer systems to comply with NPDES permit and reporting requirements. While the VA cannot extend the October 16th quote submission deadline, offerors may provide alternative past performance formats beyond CPARs and PPQs. The cost will be determined by competitive quotes, with performance to begin upon award. The VA will provide completed maps and prior year reports to the awardee. Licensing and badging requirements are also outlined.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. QUESTION Response

We are very experienced providing these same services for other Maryland and Virginia customers; however, even for experienced firms like ours, the technical and pricing/costing requirements are difficult to meet by the October 16th deadline.

Will the government please consider extending the submission due date October 30th to ensure qualified firms like ours can submit a compliant proposal? Would the government be willing to respond to our request by October 9th?

Unfortunately, the using service does not feel comfortable extending the quote due date to ensure all necessary steps are able to be completed and award is made prior to the end of the current contract on 10/30.

Some of our State of Maryland government customers have policies that prohibit them from completing rating forms (e.g., PPQs) that are not of their own format. Will the government please consider accepting other forms of past performance assessment other than PPQs and CPARs?

No issue with providing a past performance assessment that is different from the format provided.

Is there a cost estimate , budget or ballpark figure for the project listed? Is there an actual start date for the project?

Cost will be determined by competitve quotes. Start date is listed on the RFQ.

4 From Section II.b.i, Will VA provide the completed MS4 map? Yes, upon award, the maps and prior year reports will be provided to the awardee.

5 For Section II.b.ii, How many outfalls are located on each site? Loch Raven: 5; Perry Point: 30

For Section II.d.iii, How many BMPs are currently located at each site?

Loch Raven: 8; Perry Point: 39

For Section II.c, Will the contractor be required to resolve all non-stormwater complaints, including those covered under required NPDES permits and SWPPPs? And if so, will the contractor be required to submit inspection findings to complainant?

Contractor will not be required to resolve non-stormwater complaints.

Form General Requirements 4.1, What types of drawings will be required to be completed by the contractor (as-builts for MS4 submittals, O&M drawings for RFPs, updated designs for current conditions, etc.)?

Reproduction of previously created drawings, updating and creation of drawings for MS4 reporting requirements

From General Requirements 1.2.2, Will the licensed land surveyor be required to complete as-built drawings to confirm impervious area restoration calculations? Or is it anticipated that a surveyor be required to complete current drawings as part of the ongoing MS4 reporting?

Licensed land surveyor not required for completion of this item. Updates to reporting only based on as-built permits/calculations by 3rd party designers.

For Section: II.e and Table 1 Scope of Work Matrix, Has a Pollution Prevention Plan/Good Housekeeping Plan or SOPs been developed or established?

Yes

The MS4 scope as understood from the MS4 permit does not require the need for a licensed surveyor to support any scope.

Please confirm if this is a requirement.

Confirmed.

The scope outlines the requirements for badging. Badging at Perry Point and Loch Raven have not been required to support inspection activity in the past permit years. Please confirm if this is a requirement.

Badging is required for prime contractor staff directly involved in field work - responsible for escorting subs