0719-375 VAMC Steams Tunnels_Revision 1_20201105.pdf
PDF 354 KB Posted
- Solicitation number
- 36C24520B0005
About this file
This document contains a federal solicitation and related structural engineering drawings and details for a construction project. The Department of Veterans Affairs is seeking a Service Disabled Veteran Owned Small Business to replace steam piping, insulation, and related equipment between Buildings 310 and 217 at the VA Medical Center in Martinsburg, West Virginia. The estimated cost range for the project is $1-2 million. Interested firms must be verified in VetBiz VIP and registered in SAM.gov to be eligible. A pre-bid site visit will be held on a date specified in the solicitation, with questions due to the contracting officer. Bids are due around November 17th, 2020 and will be publicly opened, with award to the responsive responsible bidder offering the lowest price.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q_A.docx | DOCX document | |
| 36C24520B0005 0002.docx | DOCX document | |
| Bldg. 310 Pump Room Photos.zip | ZIP file | |
| Pre-Bid Site Visit Sign-in Sheet.pdf | ||
| 36C24520B0005 0001.docx | DOCX document | |
| Bldg. 302 Corridor Photos.zip | ZIP file | |
| Phase 2 Q_A.docx | DOCX document | |
| Inspection Report_Data- Sheets Final.zip | ZIP file | |
| Bldg. 217 Corridor Photos.zip | ZIP file | |
| Bldg. 217 Pump Room Photos.zip | ZIP file | |
| Bldg. 306 Pump Area Photos.zip | ZIP file | |
| Bldg. 306 Corridor Photos.zip | ZIP file | |
| 613-21-105 Replace Steam Piping PH 2_Drawings.pdf | ||
| 613-21-105 Replace Steam Piping PH 2_Specs.pdf | ||
| 36C24520B0005_1.docx | DOCX document | |
| 613-21-105 Replace Steam Piping PH 2_ICRA ILSM.pdf | ||
| 613-21-105 Replace Steam Piping PH 2_Contr Resp Postures.docx | DOCX document | |
| Security_CompletePacket.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3" CLR
C L R
(4) #5 EPOXY DOWELS 3'-0"
LONG, WITH 6" EMBED
#5 @12 EACH WAY
#5 @12 EACH WAY
BITUMINOUS
WATER PROOFING
PER SPECIFICATION
SAW CUT 2" WIDE x 2" DEEP SLOT IN
WALL TO EXTEND 1'-6" ON EACH
SIDE OF OPENING
INSERT #5 BAT INTO SLOT AND
REPAIR FISH WITH WALL USING
VERTICAL REPAIR MORTAR
REPAIR OPENING IN EXISTING
WALL IN ACCORDANCE WITH
SPECIFICATIONS
1' - 0"
1 1/2" 1 1/2"
1/2"
3/8x6" PLATE
3/16
"W12x35
(3) 3/4"⌀ EPOXY ANCHOR
BOLTS 6" EMBED
/2
"9
3/8 GUSSET
PLATE
9"
3/16
3/8 PLATE
(3) 3/4"⌀ BOLTS
3/16
TYP
1 1/2"
1' - 1"
(4) 3/4"⌀ EPOXY
BOLTS, EMBED 6"
3/4 PLATE
HSS5x5x3/8
W12x35
ATTACH TYPICAL PIPE SUPPORT
TO FLANGE WITH ALL THREAD
L3x3x1/4 x 5" LONG WITH
1/2"⌀ EPOXY ANCHORS
EMBED 4", USE SCREEN
TUBE FOR HOLLOW CELLS
THROUGH PANEL
FASTENER @12
THROUGH PANEL
FASTENER @12
1/8"x4" PLATE CONTINUOUS SEALANT JOINT
TO BUILDING
1/2":1'-0" SLOPE
2" THICK 22GA
INSULATED WALL
ROOF PANEL
T Y
P
/2
M
IN
THROUGH PANEL
FASTENER @ 12
1/8"x4" BENT PLATE
CONTINUOUS
L3x3x1/4 @ 2'-8"
AND AT CORNERS
L3x3x1/4 @ 2'-8"
AND AT CORNERS
4x4x3/8 PLATE WITH 1/2'⌀
EPOXY ANCHOR, EMBED
3" INTO TOP OF WALL
1/8"x4" PLATE
2" THICK 22GA
INSULATED WALL
ROOF PANEL
3/16
TYP
3/16
TYP
PROVIDE MANUFACTURES
STANDARD DETAILS AT BASE,
EAVE AND BUILDING JOINT.
ACCEPTABLE MANUFACTURES
ARE MBCI, KINGSPAN, AND
AWIP.
3/16
EXISTING TUNNEL
NEW PIPES, SEE MECH
1" +/-2"
1"
9 1/8"
EXISTING 2x6 @12
5 5
VIF
8 1/2"
2S3.02
M
A X
1' - 2 5/8"
/8
REPAIR OPENING IN EXISTING
WALL IN ACCORDANCE WITH
SPECIFICATIONS
NO ADDITIONAL REINFORCING
REQUIRED FOR OPENINGS AT
THIS TUNNEL WALL
C L R
(4) #5 EPOXY DOWELS 3'-0"
LONG, WITH 6" EMBED
#5 @12 EACH WAY
#5 @8 VERTICAL
BITUMINOUS
WATER PROOFING
PER SPECIFICATION
CLR
3"
#5 @12 HORIZONTAL
2S3.01
SIM
Sheet Notes:
1. Sections are based on original drawings and limited field observation. General contractor must verify all dimensions and coordinate with final mechanical layout.
2. Existing pipes shown shall either remain or be removed in accordance with mechanical.
3. All existing structural framing shall remain.
EXISTING TUNNEL WALL
HSS10x4x1/2
10x16x1/2 PLATE
(4) 3/4" ANCHOR BOLT EMBED 9",
TYPICAL
U N
D E
R S
ID
E
O F
E X
P A
N S
IO
N
J O
IN
T
A N
C H
O R
S
V .I
.F F
R O
M T
U N
N E
L F
L O
O R
T O
INFILL CONCRETE TO BOTTOM OF
PIPE ANCHOR
EXISTING 2x6 @12
EXISTING (3) 2x6
DROP BEAM
ANCHOR BASE, BY OTHERS
#4x24" LONG @12 BOTH WAYS. DOWEL
INTO EXISTING CONCRETE 4". DRILL 1" ⌀
HOLE FOR BAR AND GROUT SOLID BEFORE
POURING CONCRETE BLOCK
PROVIDE (3) #4 @3" O.C. HOOPS
WITHIN DEPTH ANCHOR BOLT
1 1/2"
/2 " 3
6"
1/4
BID DOCUMENTS
SUBMISSION
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Numbers
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS:
VAMC - Martinsburg, WV
ARCHITECT/ENGINEERS:
Scale:
AS NOTEDSEAL: 613-19-102REPAIR-PIPING BLDGS
500, 217, 318, & 328 to BOILER PLANT - PHASE-2 500, 217, 318, & 328
Office of
Construction and Facilities Management o n e e ig h th in c h o n e fo o t 1
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
F
E
D
C
B
A
97 8654321
VA FORM 08-6231
MEP ENGINEERS
Valley Engineering 4901 Crowe Drive Mount Crawford, VA 22841 of 6
BID DOCUMENTS SUBMISSION
97 8654321
STRUCTURAL ENGINEERS
Engineering Solutions 100 10th Street NE, Suite 200 Charlottesville, VA 22902
2S3.01
STRUCTURAL DETAILS - SUB PHASE-1
07/29/2020 TM VK
1" = 1'-0"2S1.02 2S3.01
1 TUNNEL SECTION A @ BLDG 302
1" = 1'-0"2S1.02 2S3.01
TUNNEL SECTION B @ BLDG 217 - TYPICAL INTERIOR
PIPE SUPPORTS
1" = 1'-0"2S1.02 2S3.01
4 TUNNEL SECTION C @ BLDG 217
Keynotes
1 Dimension varies as tunnel slopes.
General contractor must coordinate this dimension with final mechanical layout in field.
2 Dimension varies based on location of thrust block. Pipe elevation varies and tunnel floor slopes. General contractor must coordinate this dimension with final mechanical layout.
5 Dimension can vary depending on relative distance between pipes vertically and horizontally.
XX
1" = 1'-0"2S3.01
2 TYPICAL ANCHOR BLOCK
1. REVISION FOR INSULATED METAL PANEL DETAILS 11/05/2020
07/27/2020
| Sheets |
| 2S3.01 - STRUCTURAL DETAILS - SUB PHASE-1 |