CONSTRUCTION MODERNIZE SPECIALTY CLINICS Federal contract opportunity
Solicitation number
36C24519B0008
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 5

About this file

36C24519B0008 0003 Revised Drawings EP502, EP503 _ Revised Specification 27 52 23.pdf

View the file

Other files for this federal contract opportunity

Other files attached to CONSTRUCTION MODERNIZE SPECIALTY CLINICS, newest first.
File Type Posted
36C24520C0030-000.docx DOCX document
36C24519B0008-0005000.docx DOCX document
36C24519B0008-0005001.pdf PDF
36C24519B0008-0005000.docx DOCX document
36C24519B0008-0005001.pdf PDF
36C24519B0008-0004002.pdf PDF
36C24519B0008-0004001.pdf PDF
36C24519B0008-0004000.docx DOCX document
36C24519B0008-0004001.pdf PDF
36C24519B0008-0004000.docx DOCX document
36C24519B0008-0004002.pdf PDF
36C24519B0008-0003000.docx DOCX document
36C24519B0008-0003001.pdf PDF
36C24519B0008-0003002.docx DOCX document
36C24519B0008-0003000.docx DOCX document
36C24519B0008-0003002.docx DOCX document
36C24519B0008-0003001.pdf PDF
36C24519B0008-0003003.pdf PDF
36C24519B0008-0002000.docx DOCX document
36C24519B0008-0002000.docx DOCX document
36C24519B0008-0001000.docx DOCX document
36C24519B0008-0001001.pdf PDF
36C24519B0008-0001000.docx DOCX document
36C24519B0008-0001001.pdf PDF
36C24519B0008-003.docx DOCX document
36C24519B0008-003.docx DOCX document
Pages_from_Mechanical_Part_1.pdf PDF
Electrical_Drawings.pdf PDF
Architectural_Part_2,_Interiors_and_Equipment_Drawings.pdf PDF
Pages_from_Mechanical_Part_3.pdf PDF
36C24519B0008_1.docx DOCX document
Plumbing_Drawings.pdf PDF
Pages_from_Mechanical_Part_4.pdf PDF
Pages_from_Mechanical_Part_2.pdf PDF
Modernize_Specialty_Clinics_Specifications.pdf PDF
Fire_Protection_and_Supression_Drawings.pdf PDF
General,_Hazardous,_Structural_and_Part_1_Architectural_Drawings.pdf PDF
36C24519B0008-000.docx DOCX document
36C24519B0008-000.docx DOCX document
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Modernize Specialty Clinics VA244-13-D-0211

Louis A. Johnson VA Medical Center

Clarksburg, WV HDG #16015

27 52 23 - 1

SECTION 27 52 23

NURSE CALL AND CODE BLUE SYSTEMS

PART 1 - GENERAL

1.1 SECTION SUMMARY

A. Work covered by this document includes design, engineering, labor, material and products, equipment warranty and system warranty, training and services for, and incidental to, the complete installation of an extension of the existing fully operating National Fire Protection

Association (NFPA) – Life Safety Code 101.3-2 (a) Labeled and (b)

Listed, Emergency Service Nurse-Call and/or Life Safety listed Code

Blue Communication System and associated equipment (here-in-after referred to as the System) provided in approved locations indicated on the contract drawings. These items shall be tested and certified capable of receiving, distributing, interconnecting and supporting

Nurse-Call and/or Code Blue communications signals generated local and remotely as detailed herein.

B. Work shall be complete, Occupational Safety and Health Administration

(OSHA), National Recognized Testing Laboratory (NRTL – i.e.

Underwriters Laboratory [UL]) Listed and Labeled; and VA Central

Office (VACO), Telecommunications Voice Engineering (TVE 005OP3B) tested, certified and ready for operation.

C. The System shall be delivered free of engineering, manufacturing, installation, and functional defects. It shall be designed, engineered and installed for ease of operation, maintenance, and testing.

D. The term “provide”, as used herein, shall be defined as: designed, engineered, furnished, installed, certified, tested, and warranty by the Contractor.

E. Specification Order of Precedence: In the event of a conflict between the text of this document and the Project’s Contract Drawings outlined and/or cited herein; THE TEXT OF THIS DOCUMENT TAKES PRECEDENCE.

HOWEVER, NOTHING IN THIS DOCUMENT WILL SUPERSEDE APPLICABLE EMERGENCY

LAWS AND REGULATIONS, SPECIFICALLY NATIONAL AND/OR LOCAL LIFE AND

PUBLIC SAFETY CODES. The Local Fire Marshall and/or VA Public Safety

Officer are the only authorities that may modify this document’s

EMERGENCY CODE COMPLIANCE REQUIREMENTS, on a case by case basis, in writing and confirmed by VA’s Project Manager (PM), COR and TVE-

Clarksburg, WV HDG #16015

27 52 23 - 2

005OP3B. The VA PM is the only approving authority for other amendments to this document that may be granted, on a case by case basis, in writhing with technical concurrencies by VA’s PM, RE, TVE-

005OP3B and identified Facility Project Personnel.

F. The Original Equipment Manufacturer (OEM) and Contractor shall ensure that all management, sales, engineering and installation personnel have read and understand the requirements of this specification before the system is designed, engineered, delivered and provided. The Contractor shall furnish a written statement stating this requirement as a part of the technical submittal that includes each name and certification, including the OEMs. The Contractor is cautioned to obtain in writing, all approvals for system changes relating to the published contract specifications and drawings, from the PM and/or the COR before proceeding with the change.

1.2 RELATED SECTIONS

A. 01 33 23 – SHOP DRAWINGS, PRODUCT DATA AND SAMPLES.

B. 07 84 00 – FIRESTOPPING.

C. 27 05 11 – REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS.

D. 27 05 26 – GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS.

E. 27 05 33 – RACEWAYS AND BOXES FOR COMMUNICATIONS SYSTEMS.

F. 27 10 00 – CONTROL, COMMUNICATION AND SIGNAL WIRING.

G. 27 11 00 – TELECOMMUNICATIONS ROOM FITTINGS.

H. 27 15 00 – COMMUNICATIONS STRUCTURED CABLING.

1.3 DEFINITION

A. Provide: Design, engineer, furnish, install, connect complete, test, certify and warranty.

B. Work: Materials furnished and completely installed.

C. Review of contract drawings: A service by the engineer to reduce the possibility of materials being ordered which do not comply with contract documents. The engineer's review shall not relieve the

Contractor of responsibility for dimensions or compliance with the contract documents. The reviewer's failure to detect an error does not constitute permission for the Contractor to proceed in error.

D. Headquarters (aka VACO) Technical Review, for National and VA

Communications and Security, Codes, Frequency Licensing Standards, Guidelines and Compliance:

Clarksburg, WV HDG #16015

27 52 23 - 3

Office of Telecommunications

Special Communications Team (005OP3B)

1335 East West Highway – 3rd Floor

Silver Spring, Maryland 20910,

(O) 301-734-0350, (F) 301-734-0360

E. Owner: VAMC Lexington, KY Leestown Division

F. Contractor: Systems Contractor; you; successful bidder.

1.4 REFERENCES

A. The installation shall comply fully with all governing authorities, laws and ordinances, regulations, codes and standards, including, but not limited to:

1. United States Federal Law:

a. Departments of:

1) Commerce, Consolidated Federal Regulations (CFR), Title 15 –

Under the Information Technology Management Reform Act (Public

Law 104-106), the Secretary of Commerce approves standards and guidelines that are developed by the:

a) Chapter II, National Institute of Standards Technology

(NIST – formerly the National Bureau of Standards). Under

Section 5131 of the Information Technology Management

Reform Act of 1996 and the Federal Information Security

Management Act of 2002 (Public Law 107-347), NIST develops

– Federal Information Processing Standards Publication

(FIPS) 140-2—Security Requirements for Cryptographic

Modules.

b) Chapter XXIII, National Telecommunications and Information

Administration (NTIA – aka ‘Red Book’) Chapter 7.8 / 9;

CFR, Title 47 Federal communications Commission (FCC) Part

15, Radio Frequency Restriction of Use and Compliance in

“Safety of Life” Functions & Locations.

2) FCC - Communications Act of 1934, as amended, CFR, Title 47 –

Telecommunications, in addition to Part 15 – Restrictions of use for Part 15 listed Radio Equipment in Safety of Life /

Emergency Functions / Equipment/ Locations (also see CFR, Title 15 – Department of Commerce, Chapter XXIII – NTIA):

Clarksburg, WV HDG #16015

27 52 23 - 4

a) Part 15 – Restrictions of use for Part 15 listed Radio

Equipment in Safety of Life / Emergency Functions /

Equipment/Locations.

b) Part 58 – Television Broadcast Service.

c) Part 90 – Rules and Regulations, Appendix C.

3) Health, (Public Law 96-88), CFR, Title 42, Chapter IV Health &

Human Services, CFR, Title 46, Subpart 1395(a)(b) JCAHO “a hospital that meets JCAHO accreditation is deemed to meet the

Medicare conditions of Participation by meeting Federal

Directives:”

a) All guidelines for Life, Personal and Public Safety; and, Essential and Emergency Communications.

4) Labor, CFR, Title 29, Part 1910, Chapter XVII - Occupational

Safety and Health Administration (OSHA), Occupational Safety and Health Standard:

a) Subpart 7 - Definition and requirements (for a NRTL – 15

Laboratory’s, for complete list, contact

(http://www.osha.gov/dts/otpca/nrtl/faq_nrtl.html):

1) UL:

a) 44-02 – Standard for Thermoset-Insulated Wires and

Cables.

b) 65 – Standard for Wired Cabinets.

c) 83-03 – Standard for Thermoplastic-Insulated Wires and Cables.

d) 467-01 – Standard for Electrical Grounding and

Bonding Equipment

e) 468 – Standard for Grounding and Bonding Equipment.

f) 486A-01 – Standard for Wire Connectors and Soldering

Lugs for Use with Copper Conductors

g) 486C-02 – Standard for Splicing Wire Connectors.

h) 486D-02 – Standard for Insulated Wire Connector

Systems for Underground Use or in Damp or Wet

Locations.

i) 486E-00 – Standard for Equipment Wiring Terminals for

Use with Aluminum and/or Copper Conductors.

j) 493-01 – Standard for Thermoplastic-Insulated http://www.osha.gov/dts/otpca/nrtl/faq_nrtl.html

Clarksburg, WV HDG #16015

27 52 23 - 5

Underground Feeder and Branch Circuit Cable.

k) 514B-02 – Standard for Fittings for Cable and

Conduit.

l) 1069 – Hospital Signaling and Nurse Call Equipment.

m) 1449 – Standard for Transient Voltage Surge

Suppressors.

n) 1479-03 – Standard for Fire Tests of Through-

Penetration Fire Stops.

o) 1666 – Standard for Wire/Cable Vertical (Riser) Tray

Flame Tests.

p) 1863 – Standard for Safety, Communications Circuits

Accessories.

q) 2024 – Standard for Optical Fiber Raceways.

r) 60950-1/2 – Information Technology Equipment –

Safety.

2) Canadian Standards Association (CSA): same tests as for

UL.

3) Communications Certifications Laboratory (CCL): same tests as for UL.

4) Intertek Testing Services NA, Inc. (ITSNA formerly

Edison Testing Laboratory [ETL]): same tests as for UL.

b) Subpart 35 – Compliance with NFPA 101 – Life Safety Code.

c) Subpart 36 - Design and construction requirements for exit routes.

d) Subpart 268 - Telecommunications.

e) Subpart 305 - Wiring methods, components, and equipment for general use.

5) Department of Transportation, CFR, Title 49 (Public Law 89-

670), Part 1, Subpart C – Federal Aviation Administration

(FAA):

a) Standards AC 110/460-ID & AC 707 / 460-2E – Advisory

Circulars for Construction of Antenna Towers.

b) Forms 7450 and 7460-2 – Antenna Construction Registration.

6) Veterans Affairs (Public Law No. 100-527), CFR, Title 38, Volumes I & II:

Clarksburg, WV HDG #16015

27 52 23 - 6

a) Office of Telecommunications:

1) Handbook 6100 – Telecommunications.

a) Spectrum Management FCC & NTIA Radio Frequency

Compliance and Licensing Program.

b) Special Communications Proof of Performance Testing, VACO Compliance and Life Safety Certification(s).

b) Office of Cyber and Information Security (OCIS):

1) Handbook 6500 - Information Security Program.

2) Wireless and Handheld Device Security Guideline Version

3.2, August 15, 2005.

c) VA’s National Center for Patient Safety – Veterans Health

Administration Warning System, Failure of Medical Alarm

Systems using Paging Technology to Notify Clinical Staff, July 2004.

d) VA’s Center for Engineering Occupational Safety and Health, concurrence with warning identified in VA Directive 7700.

e) Office of Construction and Facilities Management (CFM):

1) Master Construction Specifications (PG-18-1).

2) Standard Detail and CAD Standards (PG-18-4).

3) Equipment Guide List (PG-18-5).

4) Electrical Design Manual for VA Facilities (PG 18-10), Articles 7 & 8.

5) Minimum Requirements of A/E Submissions (PG 18-15):

a) Volume B, Major New Facilities, Major Additions; and

Major Renovations, Article VI, Paragraph B.

b) Volume C - Minor and NRM Projects, Article III, Paragraph S.

c) Volume E - Request for Proposals Design/Build

Projects, Article II, Paragraph F.

6) Mission Critical Facilities Design Manual (Final Draft –

2007).

7) Life Safety Protected Design Manual (Final Draft –

2007).

8) Solicitation for Offerors (SFO) for Lease Based Clinics

– (05-2009).

b. Federal Specifications (Fed. Specs.):

Clarksburg, WV HDG #16015

27 52 23 - 7

1) A-A-59544-00 - Cable and Wire, Electrical (Power, Fixed

Installation).

2. National Codes:

a. American Institute of Architects (AIA): Guidelines for Healthcare

Facilities.

b. American National Standards Institute/Electronic Industries

Association/Telecommunications Industry Association

(ANSI/EIA/TIA):

1) 568-B - Commercial Building Telecommunications Wiring

Standards:

a) B-1 – General Requirements.

b) B-2 – Balanced twisted-pair cable systems.

c) B-3 - Fiber optic cable systems.

2) 569 - Commercial Building Standard for Telecommunications

Pathways and Spaces.

3) 606 – Administration Standard for the Telecommunications

Infrastructure of Communications Buildings.

4) 607 – Commercial Building Grounding and Bonding Requirements for Telecommunications.

5) REC 127-49 – Power Supplies.

6) RS 270 – Tools, Crimping, Solderless Wiring Devices, Recommended Procedures for User Certification.

c. American Society of Mechanical Engineers (ASME):

1) Standard 17.4 – Guide for Emergency Personnel.

2) Standard 17.5 – Elevator & Escalator Equipment (prohibition of installing non-elevator equipment in Elevator Equipment Room /

Mechanical Penthouse).

d. American Society of Testing Material (ASTM):

1) D2301-04 - Standard Specification for Vinyl Chloride Plastic

Pressure Sensitive Electrical Insulating Tape.

e. Building Industries Communications Services Installation (BICSI):

1) All standards for smart building wiring, connections and devices for commercial and medical facilities.

2) Structured Building Cable Topologies.

3) In consort with ANSI/EIA/TIA.

f. Institute of Electrical and Electronics Engineers (IEEE):

Clarksburg, WV HDG #16015

27 52 23 - 8

1) SO/TR 21730:2007 - Use of mobile wireless communication and computing technology in healthcare facilities -

Recommendations for electromagnetic compatibility (management of unintentional electromagnetic interference) with medical devices.

2) 0739-5175/08/©2008 IEEE – Medical Grade – Mission Critical –

Wireless Networks.

3) C62.41 – Surge Voltages in Low-Voltage AC Power Circuits.

g. NFPA:

1) 70 - National Electrical Code (current date of issue) –

Articles 517, 645 & 800.

2) 75 - Standard for Protection of Electronic Computer Data-

Processing Equipment.

3) 77 – Recommended Practice on Static Electricity.

4) 99 - Healthcare Facilities.

5) 101 - Life Safety Code.

3. State Hospital Code(s).

4. Local Town, City and/or County Codes.

5. Accreditation Organization(s):

a. Joint Commission on Accreditation of Hospitals Organization

(JCAHO) – Section VI, Part 3a – Operating Features.

1.5 QUALIFICATIONS

A. The OEM shall have had experience with three (3) or more installations of Nurse Call systems of comparable size and interfacing complexity with regards to type and design as specified herein. Each of these installations shall have performed satisfactorily for at least one (1) year after final acceptance by the user. Include the names, locations and point of contact for these installations as a part of the submittal.

B. The Contractor shall submit certified documentation that they have been an authorized distributor and service organization for the OEM for a minimum of three (3) years. The Contractor shall be authorized by the

OEM to pass thru the OEM’s warranty of the installed equipment to VA.

In addition, the OEM and Contractor shall accept complete responsibility for the design, installation, certification, operation, and physical support for the System. This documentation, along with

Clarksburg, WV HDG #16015

27 52 23 - 9 the System Contractor and OEM certifications must be provided in writing as part of the Contractor’s Technical submittal.

C. The Contractor’s Communications Technicians assigned to the System shall be fully trained, qualified, and certified by the OEM on the engineering, installation, operation, and testing of the System. The

Contractor shall provide formal written evidence of current OEM certification(s) for the installer(s) as a part of the submittal or to the COR before being allowed to commence work on the System.

D. The Contractor shall display all applicable national, state and local licenses.

E. The Contractor shall submit copy (s) of Certificate of successful completion of OEM’s installation/training school for installing technicians of the System’s Nurse Call and/or Code Blue equipment being proposed.

1.6 CODES AND PERMITS

A. Provide all necessary permits and schedule all inspections as identified in the contract’s milestone chart, so that the system is proof of performance tested, certified and approved by VA and ready for operation on a date directed by the Owner.

B. The contractor is responsible to adhere to all codes described herein and associated contractual, state and local codes.

1.7 SCHEDULING

A. After the award of contract, the Contractor shall prepare a detailed schedule (aka milestone chart) using “Microsoft Project” software or equivalent. The Contractor Project Schedule (CPS) shall indicate detailed activities for the projected life of the project. The CPS shall consist of detailed activities and their restraining relationships. It will also detail manpower usage throughout the project.

B. It is the responsibility of the Contractor to coordinate all work with the other trades for scheduling, rough-in, and finishing all work specified. The owner will not be liable for any additional costs due to missed dates or poor coordination of the supplying contractor with other trades.

Clarksburg, WV HDG #16015

27 52 23 - 10

1.8 REVIEW OF CONTRACT DRAWINGS AND EQUIPMENT DATA SUBMITTALS (AKA

TECHNICAL SUBMITTAL[S])

(Note: The Contractor is encouraged, but not required, to submit separate technical submittal(s) outlining alternate technical approach(s) to the system requirements stated here-in as long as each alternate technical document(s) is complete, separate, and submitted in precisely the same manner as outlined herein. VA will review and rate each received alternate submittal, which follows this requirement, in exactly the same procedure as outlined herein. Partial, add-on, or addenda type alternates will not be accepted or reviewed.)

A. Submit at one time within 10 days of contract awarding, drawings and product data on all proposed equipment and system. Check for compliance with contract documents and certify compliance with

Contractor's "APPROVED" stamp and signature.

B. Support all submittals with descriptive materials, i.e., catalog sheets, product data sheets, diagrams, and charts published by the manufacturer. These materials shall show conformance to specification and drawing requirements.

C. Where multiple products are listed on a single cut-sheet, circle or highlight the one that you propose to use. Provide a complete and through equipment list of equipment expected to be installed in the system, with spares, as a part of the submittal. Special

Communications (TVE-005OP3B) will not review any submittal that does not have this list.

D. Provide four (4) copies to the PM for technical review. The PM will provide a copy to the offices identified in Paragraph 1.3.C & D, at a minimum for compliance review as described herein where each responsible individual(s) shall respond to the PM within 10 days of receipt of their acceptance or rejection of the submittal(s).

E. Provide interconnection methods, conduit (where not already installed), junction boxes (J-Boxes), cable, interface fixtures and equipment lists for the: Telecommunications Rooms (TR), Nurses Stations (NS), Head End

Room (HER), Head End Cabinet (HEC), Head End Interface Cabinet (HEIC) and approved TCO locations TIP interface distribution layout drawing, as they are to be installed and interconnected to teach other (REFER TO

Clarksburg, WV HDG #16015

27 52 23 - 11

APPENDIX B – SUGGESTED TELECOMMUNI-CAITONS ONE LINE TOPOLOGY pull-out drawing).

F. Equipment technical literature detailing the electrical and technical characteristics of each item of equipment to be furnished.

G. Engineering drawings of the System, showing calculated of expected signal levels at the headend input and output, each input and output distribution point, and signal level at each telecommunications outlet.

H. Surveys Required as a Part of The Technical Submittal:

1. The Contractor shall provide the following System surveys that depict various system features and capacities required in addition to the on-site survey requirements described herein (see

Specification Paragraph 2.4.3). Each survey shall be in writing and contain the following information (the formats are suggestions and may be used for the initial Technical Submittal Survey requirements), as a minimum:

a. Nurse Call Cable System Design Plan:

1) An OEM and contractor designed functioning Nurse Call System cable plan to populate the entire TIP empty conduit/pathway distribution systems provided as a part of Specification 27 05

33 shall be provided as a part of the technical proposal. A specific functioning Nurse Call: cable, interfaces, J-boxes and back boxes shall coincide with the total growth items as described herein. It is the Contractor’s responsibility to provide the Systems’ entire Nurse Call cable and accessory requirements and engineer a functioning Nurse Call distribution system and equipment requirement plan of the following paragraph(s), at a minimum:

2) The required Nurse Call and/or Code Blue Equipment Locations:

EQUIPPED ITEM CAPACITY GROWTH

Master Stations

Dome Lights

Room

Corridor

Other

Patient Stations

Clarksburg, WV HDG #16015

27 52 23 - 12

EQUIPPED ITEM CAPACITY GROWTH

Single

Dual

Isolation

Other

Emergency Stations

Bath

Toilet

Isolation

Other

Staff Stations

Duty Stations

Code Blue

Supervisory Locations

Nurse Stations

Remote Locations

Telephone Operator’s Room

Police Control Room

Other

Audio Paging Access (when pre-approved by TVE-005OP3B)

Wireless Access (when pre-approved by

TVE-005OP3B)

Maintenance/Programming Console

Clarksburg, WV HDG #16015

27 52 23 - 13

EQUIPPED ITEM CAPACITY GROWTH

Location(s)

Central Control Cabinet/Equipment

Location

Power Supply(s)

UPS(s)

3) The required Nurse Call and/or Code Blue Cable

Plant/Connections:

The Contractor shall clearly and fully indicate this category for each item identified herein as a part of the technical submittal. For this purpose, the following definitions and sample connections are provided to detail the system’s capability:

EQUIPPED ITEM CAPACITY GROWTH

Central Control Cabinet/Equipment

Location

Power Supply(s)

UPS(s)

Essential Electrical Power Panel(s)

Other

Cable Plant

Supply to Locations Identified in

Paragraph 1.8.H.1.a.2)

Remote Locations

Telephone Operator Room

Police Control Room

Other

Maintenance/Program Console

Location(s)

Other

LAN (Local Facility)

Access/Equipment/Location (when pre-approved by TVE-005OP3B)

Wireless Access/Equipment/Location

(when pre-approved by TVE-005OP3B)

Clarksburg, WV HDG #16015

27 52 23 - 14

EQUIPPED ITEM CAPACITY GROWTH

PA Access/Equipment/Location (when pre-approved by TVE-005OP3B)

Other

1.9 PROJECT RECORD DOCUMENTS (AS BUILTS)

A. Throughout progress of the Work, maintain an accurate record of changes in Contract Documents. Upon completion of Work, transfer recorded changes to a set of Project Record Documents.

B. The floorplans shall be marked in pen to include the following:

1. Each device specific locations with UL labels affixed.

2. Conduit locations.

3. Each interface and equipment specific location.

4. Head-end equipment and specific location.

5. Wiring diagram.

6. Labeling and administration documentation.

7. Warranty certificate.

8. System test results.

1.10 WARRANTIES / GUARANTY

A. The Contractor shall warrant the installation to be free from defect in material and workmanship for a period of two (2) years from the date of acceptance of the project by the owner. The Contractor shall agree to remedy covered defects within four (4) hours of notification of major failures or within twenty-four (24) hours of notification for individual station related problems.

B. The Contractor shall agree to grantee the system according to the guidelines outlined in Article 4 herein.

1.11 USE OF THE SITE

A. Use of the site shall be at the GC’s direction.

B. Coordinate with the GC for lay-down areas for product storage and administration areas.

C. Coordinate work with the GC and their sub-contractors.

D. Access to buildings wherein the work is performed shall be directed by the GC.

Clarksburg, WV HDG #16015

27 52 23 - 15

1.12 DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft.

B. Store products in original containers.

C. Coordinate with the GC for product storage. There may be little or no storage space available on site. Plan to potentially store materials off site.

D. Do not install damaged products. Remove damaged products from the site and replaced with new product at no cost to the Owner.

1.13 PROJECT CLOSE-OUT

A. Prior to final inspection and acceptance of the work, remove all debris, rubbish, waste material, tools, construction equipment, machinery and surplus materials from the project site and thoroughly clean your work area.

B. Before the project closeout date, the Contractor shall submit:

1. OEM Equipment Warranty Certificates.

2. Evidence of compliance with requirements of governing authorities such as the Low Voltage Certificate of Inspection.

3. Project record documents.

4. Instruction manuals and software that is a part of the system.

5. System Guaranty Certificate.

C. Contractor shall submit written notice that:

1. Contract Documents have been reviewed.

2. Project has been inspected for compliance with contract.

3. Work has been completed in accordance with the contract.

PART 2 – PRODUCTS / FUNCTIONAL REQUIREMENTS

2.1 GENERAL REQUIREMENTS FOR EQUIPMENT AND MATERIALS

A. Furnish and install a complete and fully functional and operable Nurse

Call System for each location shown on the contract drawings and TCOs

WHOSE EMPTY CONDUIT SYSTEM WAS PROVIDED AS A PART OF SPECIFICATION 27

05 33.

B. Coordinate features and select interface components to form an integrated Nurse Call system. Match components and interconnections between the systems for optimum performance of specified functions.

C. Expansion Capability: The Nurse Call equipment interfaces and cables shall be able to increase number of enunciation points in the future by

Clarksburg, WV HDG #16015

27 52 23 - 16 a minimum of 50 percent (%) above those indicated without adding any internal or external components or main trunk cable conductors.

D. Equipment: Active electronic type shall use solid-state components, fully rated for continuous duty unless otherwise indicated. Select equipment for normal operation on input power usually supplied between

110 to 130 VAC, 60 Hz supplied from the Facility’s Emergency Electrical

Power System.

E. Meet all FCC requirements regarding equipment listing, low radiation and/or interference of RF signal(s). The system shall be designed to prevent direct pickup of signals from within and outside the building structure.

F. Weather/Water Proof Equipment: Listed and labeled by an OSHA certified

NRTL (i.e. UL) for duty outdoors or in damp locations.

2.2 SYSTEM DESCRIPTION

A. Furnish and install a complete and fully functional and operable Nurse

Call and/or Code Blue System WHOSE EMPTY CONDUIT SYSTEM WAS PROVIDED AS

A PART OF SPECIFICATION 27 05 33.

B. The Contractor shall continually employ interfacing methods that are approved by the OEM and VA. At a minimum, an acceptable interfacing method requires not only a physical and mechanical connection, but also a matching of signal, voltage, and processing levels with regard to signal quality and impedance. The interface point must adhere to all standards described herein for the full separation of Critical Care and

Life Safety systems.

C. The System Contractor shall connect the System ensuring that all NFPA and UL Critical Care and Life Safety Circuit and System separation guidelines are satisfied. The System Contractor is not allowed to make any connections to the Telephone System. VA shall arrange for the interconnection between the Systems with the appropriate responsible parties.

D. System hardware shall consist of a nurse call patient communications network comprised of nurse consoles, control stations, staff and duty stations, room and corridor dome lights, pull cord and/or emergency push button stations, wiring. And, other options such as, pocket page interfaces, computer interfaces, printer interfaces, wireless / telephone network interfaces, and nurse locating system interface (when

Clarksburg, WV HDG #16015

27 52 23 - 17 specifically approved first by TVE 005OP3B) and as shown on drawings.

All necessary equipment required to meet the intent of these specifications, whether or not enumerated within these specifications, shall be supplied and installed to provide a complete and operating nurse call patient communications network. It is not acceptable to utilize the telephone cable system for the control and distribution of nurse call signals and equipment.

E. System firmware shall be the product of a reputable firmware OEM of record with a proven history of product reliability and sole control over all source code. Manufacturer shall provide, free of charge, product firmware/software upgrades for a period of two (2) years from date of acceptance by VA for any product feature enhancements. System configuration programming changes shall not require any exchange of parts and shall be capable of being executed remotely via a modem connection (when specifically approved first by TVE 005OP3B).

F. The Nurse Call Head End Equipment shall be located in the

Telecommunications Room. The Nurse Call System may interface the PA system when specifically approved by VA Headquarters T VE 005OP3B during the project approval process prior to contract bidding.

G. The System shall utilize microprocessor components for all signaling and programming circuits and functions. Self-contained or onboard system program memory shall be non-volatile and protected from erasure from power outages for a minimum of 12 hours.

H. Provide a backup battery or a UPS for the System (including each distribution cabinet/point, CRT and Monitor) to allow normal operation and function (as if there was no AC power failure) in the event of an

AC power failure or during input power fluctuations for a minimum of 30 minutes.

I. Each Nurse Call System shall be designed to provide continuous electrical supervision of the complete and entire system (i.e. dome light bulbs [each light will be considered supervised if they use any one or a combination of (UL) approved electrical supervision alternates, as identified in UL-1069, 1992 revision], wires, contact switch connections, circuit boards, data, audio, and communication busses, main and UPS power, etc.). All alarm initiating and signaling circuits shall be supervised for open circuits, short circuits, and

Clarksburg, WV HDG #16015

27 52 23 - 18 system grounds. Main and UPS power circuits shall be supervised for a change in state (i.e. primary to backup, low battery, UPS on line, etc.). When an open, short or ground occurs in any system circuit, an audible and visual fault alarm signal shall be initiated at the nurse control station and all remote locations.

J. All passive distribution equipment shall meet or exceed -80 dB radiation shielding (aka RFI) shielding specifications and be provided with connectors specified by the OEM.

K. All equipment face plates utilized in the system shall be stainless steel, anodized aluminum or UL approved cycolac plastic for the areas where provided.

L. Noise filters and surge protectors shall be provided for each equipment interface cabinet, headend cabinet, control console and local and remote amplifier locations to insure protection from input primary AC power surges and to insure noise glitches are not induced into low voltage data circuits.

M. Plug-in connectors shall be provided to connect all equipment, except coaxial cables. Coaxial cable distribution points shall use coaxial cable connections recommended by the cable OEM and approved by the system OEM. Base band cable systems shall utilize barrier terminal screw type connectors, at a minimum. As an alternate, crimp type connectors installed with a ratchet type installation tool are acceptable provided the cable dress, pairs, shielding, grounding, connections and labeling are the same as the barrier terminal strip connectors. Tape of any type, wire nuts or solder type connections are unacceptable and will not be approved.

N. Audio Level Processing: The control equipment shall consist of audio mixer(s), volume limiter(s) and/or compressor(s), and power amplifier(s) to process, adjust, equalize, isolate, filter, and amplify each audio channel for each sub-zone in the system and distribute them into the System’s RF interfacing distribution trunks and amplification circuits. It is acceptable to use identified Telephone System cable pairs designated for Two-Way Radio interface and control use or identified as spare telephone cable pairs by the Facility’s Telephone

System Contractor. The use of telephone cable to distribute RF signals, carrying system or sub-system AC or DC voltage is not acceptable and

Clarksburg, WV HDG #16015

27 52 23 - 19 will not be approved. Additionally, each control location shall be provided with the equipment required to insure the system can produce its designed audio channel capacity at each speaker identified on the contract drawings. The Contractor shall provide: a spare set of telephone paging modules as recommended by the OEM (as a minimum provide one spare module for each installed module); one spare audio power amplifier, one spare audio mixer, one spare audio volume limiter and/or compressor, and one spare audio automatic gain adjusting device, and minimum RF equipment recommended by the OEM.

O. Contractor is responsible for pricing all accessories and miscellaneous equipment required to form a complete and operating system. Unless otherwise noted in this Part, equipment quantities shall be as indicated on the drawings.

P. System Performance:

1. At a minimum, each distribution, interconnection, interface, terminating point and TCO shall be capable of supporting the

Facility’s Nurse Call System voice and data service as follows:

a. Shall be compliant with and not degrade the operating parameters of the Public Switched Telephone Network (PSTN) and the Federal

Telecommunications System (FTS) at each PSTN and FTS interface

(if attachment is permitted by TVE 005OP3B), interconnection and

TCO terminating locations detailed on the contract drawings.

b. The System shall provide the following minimum operational functions:

1) Code Blue calls shall be cancelable at the calling station only. The nurse call master station (s) that a managing Code

Blue functions shall not have the ability to cancel Code Blue calls.

3) Calls placed from any Code Blue station shall generate Code

Blue emergency type audible and visual signals at each associated nurse control and duty station, respective dome lights and all local and remote annunciator panels. Calls placed from a bedside station shall generate emergency type visual signals at the bedside station and associated dome light(s) in addition to the previous stated stations and panels.

Clarksburg, WV HDG #16015

27 52 23 - 20

41) Activating the silencing device at any location, while a

Code Blue call or system fault is occurring shall mute the audible signals at the alarm location.

a) The audible alarm shall regenerate at the end of the selected time-out period until the call or fault is corrected.

b) The visual signals shall continue until the call is canceled and/or a fault is corrected. When the fault is corrected, all signals generated by the fault shall automatically cease, returning the System to a standby status.

c) Audible signals shall be regenerated in any local or remote annunciator panel that is in the silence mode, in the event an additional Code Blue call is placed in any Code Blue system.

d) The additional Code Blue call shall also generate visual signals at all annunciators to identify the location of the call.

2. Each System Nurse Call location shall generate a minimum of distinct calls:

a. Routine: single flashing dome lights & master station color and audio tone,

b. Staff Assist: rapid flashing dome lights & master station color and audio tone,

c. Emergency: Red flashing done lights & master station color and audio tone,

d. Each generated call shall be cancelable at ONLY the originating location,

e. Staff Locator: Green Flashing dome lights & master station color and audio tone, and

2.3 MANUFACTURERS

A. Manufacturer shall be Rauland Responder 5 series to match campus standard.

B. The products specified shall be new, FCC and UL Listed, labeled and produced by OEM manufacturer of record. An OEM of record shall be

Clarksburg, WV HDG #16015

27 52 23 - 21 defined as a company whose main occupation is the manufacture for sale of the items of equipment supplied and which:

1. Maintains a stock of replacement parts for the item submitted,

2. Maintains engineering drawings, specifications, and operating manuals for the items submitted, and

3. Has published and distributed descriptive literature and equipment specifications on the items of equipment submitted at least 30 days prior to the Invitation for Bid.

C. Specifications contained herein as set forth in this document detail the salient operating and performance characteristics of equipment in order for VA to distinguish acceptable items of equipment from unacceptable items of equipment. When an item of equipment is offered or furnished for which there is a specification contained herein, the item of equipment offered or furnished shall meet or exceed the specification for that item of equipment.

D. Equipment Standards and Testing:

1. The System has been defined herein as connected to systems identified as Critical Service performing various Emergency and Life

Support Functions. Therefore, at a minimum, the system shall conform to all aforementioned National and/or Local Life Safety Codes (which ever are the more stringent), NFPA, NEC, this specification, JCAHCO

Life Safety Accreditation requirements, and the OEM recommendations, instructions, and guidelines.

2. All supplies and materials shall be listed, labeled or certified by

UL or a NRTL where such standards have been established for the supplies, materials or equipment.

3. The provided equipment required by the System design and approved technical submittal must conform with each UL standard in effect for the equipment, as of the date of the technical submittal (or the date when the COR approved system equipment necessary to be replaced) was technically reviewed and approved by VA. Where a UL standard is in existence for equipment to be used in completion of this contract, the equipment must bear the approved UL seal.

4. Each item of electronic equipment to be provided under this contract must bear the approved UL seal or the seal of the testing laboratory that warrants the equipment has been tested in accordance with, and

Clarksburg, WV HDG #16015

27 52 23 - 22 conforms to the specified standards. The placement of the UL Seal shall be a permanent part of the electronic equipment that is not capable of being transportable from one equipment item to another.

2.4 PRODUCTS

A. General.

1. Contractor is responsible for pricing all accessories and miscellaneous equipment required to form a complete and operating system. The equipment quantities provided herein shall be as indicated on the drawings with the exception of the indicated spare equipment.

2. Contractor Furnished Equipment List (CFEs):

a. The Contractor is required to provide a list of the CFE equipment to be furnished. The quantity, make and model number of each item is required. Select the required equipment items quantities that will satisfy the needs of the system as described herein and with the OEM’s concurrence applied to the list(s), in writing.

Item Quantity Unit

1. //As required// Interface Panel(s)

1.a //As required// Electrical Supervision

Trouble Enunciator

1.a.1 //As required// Equipment Back Box(s)

1.b //As required// Telephone

1.c //As required// Public Address

1.d //As required// Radio Paging / Equipment

1.e //As required// Wireless / Equipment

1.f. //As required// Radio Pager / Equipment

1.g //As required// Wireless / Equipment

1.f //As required// Personal Communicator /

Equipment

2. //As required// Lightning Arrestor

3. //As required// Head End Equipment/Locations

3.a //As required// Cabinet(s)

3.a.1 //As required// AC Power Conditioner & Filter

3.a.2 //As required// AC Power Strip

3.a.3 //As required// UPS

3.a.4 //As required// Interconnecting Wire/Cables

3.a.5 //As required// Wire / Cable Connector(s)

3.a.6 //As required// Wire / Cable Terminator(s)

3.b //As required// Wire Management System

3.b //As required// Head End Function(s)

3.b.1 //As required// H7 Interface

3.b.2 //As required// Nurse Locator

3.b.3 //As required// Staff Locator

4. //As required// Master Station(s)

Clarksburg, WV HDG #16015

27 52 23 - 23

4.a //As required// Nurse Locator

4.b //As required// Staff Locator

5. //As required// Distribution System(s)

5.a //As required// Staff Station

5.a.1 //As required// Equipment Back Box(s)

5.b //As required// Duty Station

5.b.1 //As required// Equipment Back Box(s)

5.c //As required// Code Blue Station

5.c.1 //As required// Equipment Back Box(s)

5.c.2 2 (MIN) Remote Station(s)

5.d //As required// Patient Station(s)

5.d.1 //As required// Equipment Back Box(s)

5.d.2 //As required// Bed Interface(s)

5.d.3 //As required// Pillow Speaker

5.d.4 //As required// Push Button Cordset

5.d.5 //As required// Dummy Plugs

5.d.6 //As required// Bed Integrated Control

5.d.7 //As required// Lighting Interface Module

5.d.8 //As required// TV Control Interface

5.d.9 //As required// TV Control Jack

5.d.10 //As required// TV Interconnection Cables

5.d.11 //As required// HDTV Coaxial

5.d.12 //As required// HDTV/Nurses Call Interface/

Control

5.d.13 //As required// Auxiliary Mounting Interface

5.e //As required// Emergency Station(s)

5.e.1 //As required// Equipment Back Box(s)

5.e.2 //As required// Toilet Emergency Station

(waterproof)

5.e.3 //As required// Shower Emergency Station

(waterproof)

5.e.4 //As required// Lavatory Emergency Station

(waterproof)

5.f. //As required// Room Dome Light

5.f.1 //As required// Equipment Back Box(s)

5.g //As required// Other Dome Light(s)

5.g.1 //As required// Equipment Back Box(s)

5.g.2 //As required// Corridor Dome Light

5.g.3 //As required// Intersectional Dome Light

5.h //As required// System Cable(s)

5.h.1 //As required// Coaxial

5.h.2 //As required// System Pin

5.h.3 //As required// Audio

5.h.4 //As required// Control

5.h.5 //As required// Video

5.i //As required// System Connector(s)

5.i.1 //As required// Coaxial

5.i.2 //As required// System Pin

5.i.2 //As required// Audio

5.i.3 //As required// Control

5.i.4 //As required// Video

5.j //As required// Wire Management Required as described herein

Clarksburg, WV HDG #16015

27 52 23 - 24

//6. //As required// Mental Health Unit

6.a //As required// Head End Function(s)

6.a.1 //As required// H7 Interface

6.a.2 //As required// Nurse Locator

6.a.3 //As required// Staff Locator

6.b. //As required// Master Station(s)

6.b.1 //As required// Nurse Locator

6.b.2 //As required// Staff Locator

6.c //As required// Distribution System(s)

6.c.1 //As required// Staff Station

6.c.1.a //As required// Equipment Back Box(s)

6.c.2 //As required// Duty Station

6.c.2.a //As required// Equipment Back Box(s)

6.c.3 //As required// Patient Station(s)

6.c.3.a //As required// Equipment Back Box(s)\

6.c.4 //As required// Security Room(s)

6.c.4.a //As required// Security Station(s)

6.c.4.b //As required// Equipment Back Box(s)\

6.c.4.c //As required// Overhead Speaker/Microphone

6.c.4.d //As required// Equipment Back Box(s)\

6.c.4.e //As required// TV Surveillance System

6.c.4.f //As required// Equipment Back Box(s)\

6.c.4.g //As required// TV Interconnection Cables

6.c.4.h //As required// Audio Interconnection Cables

6.c.5 //As required// Emergency Station(s)

6.c.5.a //As required// Equipment Back Box(s)

6.c.5.b //As required// Toilet Emergency Station

(waterproof)

6.c.5.c //As required// Shower Emergency Station

(waterproof)

6.c.5.d //As required// Lavatory Emergency Station

(waterproof)

6.c.6 //As required// Room Dome Light

6.c.7 //As required// Other Dome Light(s)

6.c.7.a //As required// Equipment Back Box(s)

6.c.7.b //As required// Corridor Dome Light

6.c.7.c //As required// Intersectional Dome Light

6.c.8 //As required// System Cable(s)

6.c.8.a //As required// Coaxial

6.c.8.b //As required// System Pin

6.c.8.c //As required// Audio

6.c.8.d //As required// Control

6.c.8.e //As required// Video

6.c.9 //As required// System Connector(s)

6.c.9.a //As required// Coaxial

6.c.9.b //As required// System Pin

6.c.9.c //As required// Audio

6.c.9.d //As required// Control

6.c.9.e //As required// Video

6.c.9.f //As required// Wire Management Required as described herein//

//7 //As required// Blind Rehabilitation Unit

7.a //As required// Head End Function(s)

Clarksburg, WV HDG #16015

27 52 23 - 25

7.a.1 //As required// H7 Interface

7.a.2 //As required// Nurse Locator

7.a.3 //As required// Staff Locator

7.b. //As required// Master Station(s)

7.b.1 //As required// Nurse Locator

7.b.2 //As required// Staff Locator

7.c //As required// Distribution System(s)

7.c.1 //As required// Staff Station

7.c.1.a //As required// Equipment Back Box(s)

7.c.2 //As required// Duty Station

7.c.2.a //As required// Equipment Back Box(s)

7.c.3 //As required// Patient Station(s)

7.c.3.a //As required// Equipment Back Box(s)\

7.c.4 //As required// Emergency Station(s)

7.c.4.a //As required// Equipment Back Box(s)

7.c.4.b //As required// Toilet Emergency Station

(waterproof)

7.c.4.c //As required// Shower Emergency Station

(waterproof)

7.c.4.d //As required// Lavatory Emergency Station

(waterproof)

7.c.5 //As required// Room Dome Light

7.c.5.a //As required// Equipment Back Box(s)

7.c.6 //As required// Other Dome Light(s)

7.c.6.a //As required// Equipment Back Box(s)

7.c.6.b //As required// Corridor Dome Light

7.c.6.c //As required// Intersectional Dome Light

7.c.7 //As required// System Cable(s)

7.c.7.a //As required// Coaxial

7.c.6.b //As required// System Pin

7.c.7.c //As required// Audio

7.c.7.d //As required// Control

7.c.7.e //As required// Video

7.c.8 //As required// System Connector(s)

7.c.8.a //As required// Coaxial

7.c.8.b //As required// System Pin

7.c.8.c //As required// Audio

7.c.8.d //As required// Control

7.c.8.e //As required// Video

7.c.9 //As required// Wire Management Required as described herein//

//8. //As required// Center for the Aging (aka

Nursing Home Care Unit)

8.a //As required// Head End Function(s)

8.a.1 //As required// H7 Interface

8.a.2 //As required// Nurse Locator

8.a.3 //As required// Staff Locator

8.b. //As required// Master Station(s)

8.b.1 //As required// Nurse Locator

8.b.2 //As required// Staff Locator

8.c //As required// Distribution System(s)

8.c.1 //As required// Staff Station

8.c.1.a //As required// Equipment Back Box(s)

Clarksburg, WV HDG #16015

27 52 23 - 26

8.c.2 //As required// Duty Station

8.c.2.a //As required// Equipment Back Box(s)

8.c.3 //As required// Patient Station(s)

8.c.3.a //As required// Equipment Back Box(s)\

8.c.4 //As required// Security Room(s)

8.c.4.a //As required// Security Station(s)

8.c.4.b //As required// Equipment Back Box(s)\

8.c.4.c //As required// Overhead Speaker/Microphone

8.c.4.d //As required// Equipment Back Box(s)\

8.c.4.e //As required// TV Surveillance System

8.c.4.f //As required// Equipment Back Box(s)\

8.c.4.g //As required// TV Interconnection Cables

8.c.4.h //As required// Audio Interconnection Cables

8.c.5 //As required// Emergency Station(s)

8.c.5.a //As required// Equipment Back Box(s)

8.c.5.b //As required// Toilet Emergency Station

(waterproof)

8.c.5.c //As required// Shower Emergency Station

(waterproof)

8.c.5.d //As required// Lavatory Emergency Station

(waterproof)

8.c.6 //As required// Room Dome Light

8.c.7 //As required// Other Dome Light(s)

8.c.7.a //As required// Equipment Back Box(s)

8.c.7.b //As required// Corridor Dome Light

8.c.7.c //As required// Intersectional Dome Light

8.c.8 //As required// System Cable(s)

8.c.8.a //As required// Coaxial

8.c.8.b //As required// System Pin

8.c.8.c //As required// Audio

8.c.8.d //As required// Control

8.c.8.e //As required// Video

8.c.9 //As required// System Connector(s)

8.c.9.a //As required// Coaxial

8.c.9.b //As required// System Pin

8.c.9.c //As required// Audio

8.c.9.d //As required// Control

8.c.9.e //As required// Video

8.c.9.f //As required// Wire Management Required as described herein//

//9. As required// Oncology, Radiology, Dialysis, Units (These units are treated the same as Blind

Rehabilitation Unit EXCEPT it does contains a CODE BLUE

Function. If these units are provided as a part of the project, AT A MINIMUM –

DUPLI-CATE THE BLINE

REHABILITATION UNIT’S

EQUIPMETN LISTE AND EDIT AND

RENUMBER ACCORD-INGLY)//

Clarksburg, WV HDG #16015

27 52 23 - 27

10. On Hand Spares Provide a separate system spares list as indicated in each equipment description.

B. Telecommunications Room(s) (TR):

1. Locate the Nurse Call floor distribution equipment as required by system design and OEM direction. Provide secured and lockable cabinet/rack(s) as required.

2. Head-End Equipment:

a. Provide all required power supplies, communications hubs, network switches, intelligent controllers and other devices necessary to form a complete system. Head-end components may be rack mounted or wall mounted in an enclosed metal enclosure.

b. Provide the head end equipment in the closest Telecommunications

Room where the System is installed.

c. Provide the System UPS inside the cabinet or in a separate cabinet adjacent to the head end cabinet that shall maintain a minimum of 30 minute battery back-up to all system components.

d. Equipment Cabinet: Comply with TIA/EIA-310-D. Lockable, ventilated metal cabinet houses terminal strips, power supplies, amplifiers, system volume control, and other switching and control devices required for conversation channels and control functions. See Paragraph 2.5.E for the Cabinet’s minimum internal items that are in addition to the installed System equipment.

e. Vertical Equipment Rack, Wall Mounted (to be included inside of the Equipment Cabinet) containing the following minimum items:

1) 36” (28RU) internal rack space, welded steel construction, minimum 20” usable depth, adjustable front mounting rails.

2) Install the following products in rack provided by same manufacturer or as specified:

a) Security screws w/ nylon isolation bushings.

b) Textured blank panels.

c) Custom mounts for components without rack mount kits.

d) Security covers.

e) Internal system ground copper buss (may be substituted with a bare #0 AWG copper wire or equivalent size copper mesh

Clarksburg, WV HDG #16015

27 52 23 - 28 strip connected to ONLY THE FACILITY’S SIGNAL GROUNDING

SYSTEM.

f) Power Sequencer- rack-mounted power conditioner and

(provide as-needed) delayed sequencer(s) with (2) unswitched outlets each and contact closure control inputs.

Connect the conditioner to one of the dual duplex outlets.

g) Two (2) each 120VAC @ 20A dual duplex outlets, connected via conduit to the nearest Electrical Service Panel that is supplied by the Facility’s Essential Electrical System.

h) One (1) each 120VAC @ 15A Power Distribution Strip(s).

Connect each strip to the unstitched outlet on the power conditioner.

C. TIP Cable Systems:

Connect the system to the TIP system provided as a part of

Specification Section 27 15 00, COMMUNICATIONS STRUCTURED CABLING.

Provide additional…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .