36C24426B0020 0001.docx

DOCX document 494 KB Posted

Attached to
Z2DA--Replace HVAC Steam Equipment and Piping Buildings 12 and 15
Solicitation number
36C24426B0020
Issued by

About this file

This is Amendment 0001 to a sealed bid solicitation for HVAC steam equipment and piping replacement work at a Department of Veterans Affairs Medical Center facility in Coatesville, Pennsylvania. The amendment, issued by the VA Network Contracting Office 4 on June 8, 2026, extends the bid deadline to July 20, 2026 at 10:00 AM via electronic submission to Elizabeth.Wilson6@va.gov, with bid opening scheduled for July 20, 2026 at 10:15 AM via Microsoft Teams.

The scope of work involves replacing HVAC steam equipment and piping in Buildings 12 and 15 at the VA Medical Center, identified as Project 542-26-107. The amendment provides contractor responses to 48 requests for information addressing key project requirements including: confirmation that all existing steam condensate piping to be replaced is located inside buildings; removal of all steam condensate piping; underground utility gas line installation specifications (minimum 3 feet below finished grade); electrical work requirements for ductless split systems; brick and mortar patching to match existing facades; ASME B31.9 and B31.1 piping code compliance with required ASME stamps; hydrostatic testing without x-ray requirements; water provision by facility for testing; no asbestos assumed but contractor field verification required; coordination of steam shutdowns with the Contracting Officer requiring three weeks' advance notice; no schedule extensions for rock removal; and staged coordination with the Contracting Officer for fill material stockpiling. The amendment includes a contractor sign-in sheet from the June 22, 2026 site visit and clarifies that certain drawings (MD-105) do not apply to this project. Staffing requirements mandate separate Site Safety and Health Officer (SSHO) and Quality Assurance/Quality Control (QA/QC) personnel independent of the site superintendent. Tax must be included in proposals. The solicitation includes standard FAR and VA-specific clauses applicable to federal construction contracts.

View the file

Other files

File Type Posted
S02 36C24426B0020 corrected pg 1 renumbered block 10.pdf PDF
Sign in Sheet_06222026.pdf PDF
Drawings combined 12 and 15.pdf PDF
SAM.gov Wage Rates.pdf PDF
36C24426B0020.docx DOCX document
Construction Safety Standards.pdf PDF
010000-General Reqs 052026.pdf PDF
VAMC Submittal Registry 542-26-107.xlsx XLSX spreadsheet
MEP-1.pdf PDF
GEMS Contractor training.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority)

THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 07-10-2026 542-26-107 00244 Department of Veterans Affairs Network Contracting Office 4 VA Medical Center 1400 Blackhorse Hill Road Coatesville, PA 19320 00244 Department of Veterans Affairs Network Contracting Office 4 VA Medical Center 1400 Blackhorse Hill Road Coatesville, PA 19320 To all Offerors/Bidders

36C24426B0020 06-08-2026

X X X x Replace HVAC System Equipment and Piping Buildings 12 and 15 Solicitation Number: 36C24426B0020, Project No. 542-26-107

This amendment is issued to provide the following information:

1. Contractor Sign-In Sheet from site visit on June 22, 2026.

2. VA Responses to Contractor RFI’s

3. Provide a sketch detail

4. Corrected page 1 of solicitation - renumbered block 10

5. SAM System Statement and FAR /VAAR Clauses and Provision Deviations

Elizabeth Wilson Contracting Officer Replace HVAC Steam Equipment and Piping Buildings 12 and 15 Project 542-26-107 | Solicitation 36C24426B0020

AMENDMENT 0001

1. Please confirm if all existing steam condensate piping called for to be replaced is physically inside the building.

VA Response: Yes

2. Does our scope require us to remove ALL steam condensate piping?

VA Response: Yes

3. Documents do not show a design for the new underground utility gas line. Per the pre-bid this will be required. Please provide design including depth, material, and distance.

VA Response: Refer to contract specifications 23 1123 paragraph 2.6 for material. Gas piping shall be installed minimum 3 feet below finished grade per attached detail and specification 23 11 23. Distance for gas main is from existing gas regulator behind building 13 to building 12 machine shop east bay unit heater.

4. The condensate line in BLD 15 is notated to be removed and replaced. Please show drawing allocating locations and run for this condensate line.

VA Response: Refer to referenced contract drawings.

5. There is electrical work required for the ductless split system please provide panel location and location of new unit as to price.

VA Response: Wire new ductless split system to nearest electrical panel within machine shop area.

6. Note shows after condensing unit and wall bracket is removed contractor is to patch wall to match existing. Please provide documentation of what existing is and the extend of the patch work.

VA Response: Contractor shall utilize brick and mortar of similar type and color to patch any openings created during construction to match existing facade.

7. Could the government please provide the below information in regards to the existing heat exchangers to the best of their ability?

· Existing HX manufacturer, model number, serial number, and nameplate photos. OR a copy of the schedules from the drawings when they were installed.

· Design capacity in MBH/BTUH.

· Heating hot water flow rate, entering water temperature, and leaving water temperature.

· Steam pressure available at HX inlet.

· Condensate return pressure or gravity/pumped return condition.

· Shell diameter, overall length, tube bundle length, and required tube pull clearance.

· Tube material, shell material, tube sheet material, ASME requirements, design pressure, and design temperature.

VA Response: Not applicable, does not apply to this project.

8. Please provide the below information for the steam powered return pump located in Bld 14:

a. GPM

b. Receiver size

c. Pump head

d. Operating pressure

e. Steam pressure VA Response: The 2” pump is a Spirax Sarco pressure powered pump model Pivotrol® Pump PTC Pressure Powered Pump.

9. Please provide the below information for the electric condensate pump unit located in the Bld 15 steam pit:

a. GPM

b. Receiver size

c. Pump head

d. Operating pressure

e. Steam pressure VA Response: There is no pump located in steam pit of building 15.

10. MD-105 shows work in building 17 and 69. Please advise as to the intent of this drawing as it relates to bldgs. 12 and 15.

VA Response: This drawing does not apply and should be removed from the contract documents.

11. There are no patient areas impacted by this project but VA staff areas are impacted. Please advise if any ICRA – related work is required to protect the VA employees.

VA Response: Yes

12. Could the government please confirm the size of the condensate piping located in Building 15 (Laundry) that is to be replaced?

VA Response: Refer to referenced contract drawings.

13. Will the sign-in sheet from site visit be available in addendum?

VA Response: Included in Amendment 0001

14. Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?

VA Response: No, the site super cannot be SSHO.

15. If no to the question above, will the SSHO need to be full-time for this project?

VA Response: No

16. Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC?

VA Response: No, the site super cannot be QA/QC.

17. If no to the question above, will the QA/QC need to be full time for this project?

VA Response: No

18. Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?

VA Response: No

19. Please confirm if tax should be included in our proposal?

VA Response: Yes

20. Please confirm the current design documents meet current VA TIL guidelines.

VA Response: Confirmed

21. Just a FYI block 10 the numbering is off. We don’t want to miss something important.

VA Response: See attached corrected page 1

22. The Scope of Work for HVAC Modifications – Page 6 of 40 Building 14, Item 1 states: "This work must be coordinated during warm months to allow for a steam system shutdown as required." Please clarify the Government's expectations if contract award and the required period of performance do not permit this work to be performed during the required warm-weather shutdown period. Please identify how this work will be coordinated and whether any schedule impacts associated with the required shutdown will be addressed by the Government.

VA Response: Steam must be available for heating during cold weather months. Any work not completed within this time must be coordinated with COR for schedule adjustments if necessary.

23. What is the Government’s expectation for hot water demand while steam is shut down?

VA Response: Hot water demand may be interrupted temporarily when the COR is given a three week advanced notice in writing.

24. Will shutdowns be required to be done during off hours or weekends?

VA Response: Shutdowns to be coordinated with COR with a minimum of three weeks advance notice in writing.

25. Please provide three recommended resources for vendors or contractors local to the project site.

VA Response: This is the contractor’s responsibility.

26. Please confirm if the code requirements for mechanical piping installation and testing are subject to ASME B31.9 Building Services Piping, and will the mechanical installation contractor be required to hold an ASME U, S, H or R stamp?

VA Response: Yes, and Yes

27. Please confirm if the code requirements for mechanical piping installation and testing are subject to B31.1 Power Piping and will the mechanical installation contractor be required to hold an ASME U, S, H or R stamp?

VA Response: Yes, and Yes

28. Will hydrostatic testing be sufficient on all pipe welds or will x-ray be required?

VA Response: No x-rays required

29. If X-ray is required, what percentage of welds and who will be responsible for the cost of testing?

VA Response: No x-rays required

30. If hydrostatic testing is required will the water necessary for hydrostatic testing of piping systems be provided by the facility?

VA Response: Yes

31. Please confirm if there is assumed asbestos on any piping that is to be removed whether underground or within manholes or buildings?

VA Response: There is no assumed asbestos. Contractor to field verify conditions and notify the COR if asbestos is found.

32. Will boiler plant, mechanical rooms etc. be cleared of all stored items prior to the contractor entering those areas?

VA Response: Yes

33. Who is the vendor or contractor currently servicing and maintaining the Building Automation System or Temperature Controls System?

VA Response: Controls vendor is CM3

34. With regards to underground utility work how much open trenching be allowed at a time?

VA Response: None

35. After backfilling, topsoil and seed have been applied who is responsible for watering? If the contractor is responsible will water be provided by the facility?

VA Response: The government will water grass seed as needed. Contractor is not responsible.

36. On all underground utility work please confirm if excavated material is acceptable for re-use as backfill other than that required?

VA Response: See attached detail.

37. Please confirm if the contractor is responsible for any rock removal that is encountered. If so, what is the assumed elevations and quantity of rock material?

VA Response: Contractor is responsible for rock removal if encountered. No significant rock removal is anticipated.

38. Please confirm if a unit price can be established for rock removal as opposed to carrying in bid?

VA Response: No

39. If an extreme amount of rock is encountered/removed, please confirm if extra time will be added to the contract completion date?

VA Response: No

40. Please confirm if there is a separate staging area onsite for fill material to be stockpiled for re-use?

VA Response: Yes, coordinate with COR.

41. Please confirm if an onsite arborist is required for any tree removal or tree protection?

VA Response: No

42. Please advise if the site contains any contaminated soil that needs to be removed.

VA Response: No

43. If the underground site package requires removal of contaminated soils. Will the site contractor be required to have operators trained and certified in all various levels of contamination handling?

VA Response: Yes

44. What are the requirements by the site contractor for the storage of contaminated soil on site?

VA Response: Contaminated soil is not anticipated in this area of excavation. Coordinate with COR for any unforeseen soil conditions.

45. Please confirm if we will be allowed to keep a locked storage container or conex box within the grounds.

VA Response: Yes, coordinate location(s) with COR.

46. Advise on existing piping sizes and routing throughout existing buildings that is called to be removed and/or replaced in kind. No piping or sizes are indicated on the provided floor plans.

VA Response: Refer to referenced drawings.

47. Please provide plans or advise on exterior site conditions along proposed path for new underground gas service.

VA Response: Soils is sandy loam with small rocks except for areas around and underneath sidewalks.

48. To allow sufficient time to review responses and prepare our bid we kindly request that you please extend the bid date at least one week.

VA Response: Bid date will not be extended.

Bids are due on July 20, 2026, 10:00 AM via electronic mail to Elizabeth.Wilson6@va.gov. Bid opening will be held on July 20, 2026, 10:15 AM, details below:

Microsoft Teams meeting Join: https://teams.microsoft.com/meet/289080861299649?p=gaueh74mmGqglivFVl Meeting ID: 289 080 861 299 649 Passcode: xY2RC7QJ

Need help? | System reference Dial in by phone +1 872-701-0185,,277091040# United States, Chicago Find a local number Phone conference ID: 277 091 040# For organizers: Meeting options | Reset dial-in PIN

SAM System statement and include the following Provisions/Clauses:

52.204-7System for Award Management-Registration (NOV 2024) (DEVIATION NOV 2025)
52.214-3Amendments to Invitations for Bids (DEC 2016) (DEVIATION NOV 2025)
52.214-5Submission of Bids (DEC 2016) (DEVIATION NOV 2025)
52.214-7Late Submissions, Modifications and Withdrawals of Bids (NOV 1999) (DEVIATION NOV 2025)
52.204-7System for Award Management-Registration (NOV 2024) (DEVIATION NOV 2025)
52.216-1Type of Contract (APR 1984) (DEVIATION NOV 2025)
52.233-2Service of Protest (SEP 2006) (DEVIATION NOV 2025)
52.240-90Security Prohibitions and Exclusions Representations and Certifications

(DEVIATION NOV 2025)

52.204-10Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (DEVIATION NOV 2025)
52.204-13System for Award Management Maintenance (OCT 2018) (DEVIATION NOV 2025)
52.209-6Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (JAN 2025) (DEVIATION NOV 2025)
52.209-10Prohibition on Contracting with Inverted Domestic Corporations. (NOV 2015) (DEVIATION NOV 2025)
52.219-8Utilization of Small Business Concerns (JAN 2025) (DEVIATION NOV 2025)
52.219-28PostAward Small Business Program Rerepresentation (JAN 2025) (DEVIATION NOV 2025)
52.222-3Convict Labor. (JUN 2003) (DEVIATION NOV 2025
52.222-4Contract Work Hours and Safety Standards - Overtime Compensation

(MAY 2018) (DEVIATION NOV 2025

52.222-6Construction Wage Rate Requirements (AUG 2018) (DEVIATION NOV 2025)
52.222-7Withholding of Funds (MAY 2014) (DEVIATION NOV 2025)
52.222-8Payrolls and Basic Records (JUL 2021) (DEVIATION NOV 2025)
52.222-10Compliance with Copeland Act Requirements (FEB 1988) (DEVIATION NOV 2025)
52.222-11Subcontracts (Labor Standards) (MAY 2014) (DEVIATION NOV 2025)
52.222-12Contract Termination-Debarment (MAY 2014) (DEVIATION FEB 2025)
52.222-14Disputes Concerning Labor Standards (FEB 1988) (DEVIATION NOV 2025)
52.222-35Equal Opportunity for Veterans (JUN 2020) (DEVIATION NOV 2025)
52.222-36Equal Opportunity for Workers with Disabilities (JUN 2020) (DEVIATION NOV 2025
52.222-37Employment Reports on Veterans (JUN 2020) (DEVIATION NOV 2025)
52.222-40Notification of Employee Rights Under the National Labor Relations Act

(DEC 2010) (DEVIATION NOV 2025)

52.222-50Combating Trafficking in Persons (NOV 2021) (DEVIATION NOV 2025)
52.222-54Employment Eligibility Verification (JAN 2025) (DEVIATION NOV 2025)
52.222-55Minimum Wages for Contractor Workers Under Executive Order 14026

(JAN 2022) (DEVIATION NOV 2025)

52.222-62Paid Sick Leave Under Executive Order 13706 (JAN 2022) (DEVIATION NOV 2025)
52.223-23Sustainable Products (MAY 2024) (DEVIATION NOV 2025)
52.225-9Buy American--Construction Materials (OCT 2022) (DEVIATION NOV 2025)
52.229-3Federal, State and Local Taxes (FEB 2013) (DEVIATION SEP 2025
52.233-1Disputes (May 2014) (DEVIATION NOV 2025)
52.233-3Protest After Award (AUG 1996) (DEVIATION NOV 2025)
52.233-4Applicable Law for Breach of Contract Claim (OCT 2004) (DEVIATION NOV 2025)
52.236-2Differing Site Conditions (APR 1984) (DEVIATION AUG 2025)
52.236-3Site Investigation and Conditions Affecting the Work (APR 1984) (DEVIATION AUG 2025)
52.236-5Material and Workmanship (APR 1984) (DEVIATION AUG 2025)
52.236-6Superintendence by the Contractor (APR 1984) (DEVIATION AUG 2025)
52.236-7Permits and Responsibilities (NOV 1991) (DEVIATION AUG 2025)
52.236-8Other Contracts (APR 1984) (DEVIATION AUG 2025)
52.236-9Protection of Existing Vegetation, Structures, Equipment, Utilities andImprovements (APR 1984) (DEVIATION AUG 2025)
52.236-10Operations and Storage Areas (APR 1984) (DEVIATION AUG 2025)
52.236-11Use and Possession Prior to Completion (APR 1984) (DEVIATION AUG 2025)
52.236-12Cleaning Up (APR 1984) (DEVIATION AUG 2025)
52.236-13Accident Prevention (NOV 1991) (DEVIATION AUG 2025)
52.236-14Availability and Use of Utility Services (APR 1984) (DEVIATION AUG 2025)
52.236-15Schedules for Construction Contracts (APR 1984) (DEVIATION AUG 2025)
52.236-17Layout of Work (APR 1984) (DEVIATION AUG 2025)
52.236-21Specifications and Drawings for Construction (FEB 1997) (DEVIATION AUG 2025)
52.240-91Security Prohibitions and Exclusions (DEVIATION NOV 2025)
52.243-4Changes (JUN 2007) (DEVIATION JUL 2025)
52.253-1Computer Generated Forms (JAN 1991) (DEVIATION NOV 2025)
852.219-73VA Notice to Total Set-Aside for Certified Service-Disabled Veteran-Owned

Small Businesses (JAN 2023) (DEVIATION)

852.219-75VA Notice of Limitations on Subcontracting – Certificate of Compliance for Services and Construction (JAN 2023) (DEVIATION)
852.222-71Compliance with Executive Order 13899 (DEVIATION) (APR 2025)

“System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.”

See attached document: Sign in Sheet_06222026.

See attached document: S02 36C24426B0020 corrected pg 1 renumbered block 10.

End of Document Solicitation 36C24426B0020 Replace HVAC Buildings 12 and 15

AMENDMENT 0001

image1.jpeg

File details come from the government source that posted it. Updated .