36C24426R0005 0001.pdf
PDF 281 KB Posted
- Solicitation number
- 36C24425R0102
About this file
This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a Department of Veterans Affairs project involving an Enclose Pharmacy Air Handling Unit (AHU). The amendment changes the solicitation number from 36C24425R0102 to 36C24426R0005 for Project 503-24-104, with all other documents remaining relevant. The proposal due date is extended from 01 October 2025 to 10 October 2025 at 10:00 AM EST.
The amendment includes responses to Request for Information (RFI) questions, which provide clarifications about the project. Key details include confirming the pharmacy is considered critical, noting the current project is not funded to rework parking lots or driveways, and providing contact information for a JCI Metasys service provider. Additional information covers pre-purchased equipment, generator specifications, transformer relocation, and testing requirements. The contracting officer for this modification is Christopher McDevitt from the Network Contracting Office 4.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 4
0001 09-25-2025
503-24-104
00244
Department of Veterans Affairs Network Contracting Office 4
00244
Department of Veterans Affairs Network Contracting Office 4
To all Offerors/Bidders
36C24426R0005
X
X X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 10-10-2025 10:00 AM EST
X 1
The above numbered solicitation for Enclose Pharmacy AHU is amended to reflect the following:
Solicitation 36C24425R0102 for Project 503-24-104 Enclose Pharmacy AHU is being replaced with Solicitation 36C24426R0005 Only the solicitation number is being changed. All documents, etc remain relevant.
Please see the attached responses to RFI's submitted on 08 September 2025.
The proposal due date is being extended from 01 October 2025 until 10 October 2025.
Proposals are due on no later than 10 October 2025 at 10:00AM EST.
Christopher McDevitt Contracting Officer
# Question VA Final Answer
1 Per section 1.4 VA Facilities, of the PSRDM, "pharmacy does not specifically show up in the main three categorizations (critical, essential, or ancillary). The only time the word "pharmacy" is listed is under Table 1-5 Facilities with Varying Designations where it lists consolidated mail-out pharmacies (CMOP). Is this considered a CMOP or another type of facility within another categorization?
It is not considered a CMOP. The medical center falls under critical categorization in which the pharmacy is internal to the building;
therefore pharmacy is critical as well.
2 Per section 3.3 Standoff Distance, of the PSRDM, a minimum standoff distance is established -- 25 feet for essential and ancillary uses and 50 feet for critical uses. Is the Design/Build team responsible for the design and construction associated with these requirements? This would include fencing, bollards, reworking parking, building/site access, etc.
The current project is not funded to include any rework of the parking lot or driveways. Project scope is for the blast wall and any associated work with the air handler.
5 Please see attached .JPG, do you require any of these options for the safety rail?
Follow Specification Section 07 72 10 Rooftop Fall Protection and Accessories.
6 Please provide the contact information for the JCI Metasys service provider. Marcos Gonzalez, marcos.gonzalez@jci.com Phone: 814-392-8643
7 Please provide access to the existing electrical single line drawings showing the as built conditions for all panel boards and circuit breakers connected loads.
There are 8 electrical drawings of one lines, E601-E615 as well as E701-E703 which contains 25 panel schedules which include the affected panels.
mailto:marcos.gonzalez@jci.com
Every load connected to every circuit breaker, which is not needed or necessary. This will have to be addressed through the outage coordination.
8 Generator - 600kw bi-fuel listed in the spec will become obsolete on 10/1/2025.
Equipment must be released prior to this date to meet the spec to its entirety.
Please advise
Contractor to provide submittal for Generator at the start of the project.
9 Pre-purchased equipment DPES-E1/E2, DPCC-E1/E2 & DPLS-E is noted to be onsite:
a. Is the contractor responsible to lift load and transport the equipment from Storage? Can we have details for pricing relocation if responsible?
b. Can the manufacture and equipment specs be provided?
c. How many sections are the equipment broken into?
d. Who is responsible for Commissioning the pre-purchased equipment
e. Is Factory Testing covered in the Pre-Purchase?
f. Is 3rd party testing required for this equipment?
a. Yes.
b. No.
c. Individual sections.
d. Contractor.
e. No.
f. No.
10 Existing 750 KVA transformer in EM Switchboard Room gets relocated
a. Can the nameplate details be provided?
b. Are any tests required such as winding resistance, or oil sampling?
a. Photo of name plate attached.
b. No.
11 Are we required to have 3rd party NETA testing?
a. Pre-purchased equipment?
b. Existing Transformer
c. Feeders
a. No.
b. No
c. No
End of Document