This is a Statement of Work (SOW) for a renovation project at the New York VA OIG Space located at the Margaret Cochran Corbin VA Campus. The project, numbered 630SI3167B14, requires the removal and replacement of existing flooring, replacement of cove base, and repainting of walls across specified office spaces with minimal disruption to building operations. The scope encompasses 12 rooms and common areas totaling approximately 2,241 square feet of flooring, 667 linear feet of cove base, and 5,585 square feet of wall area requiring painting. Specific materials are mandated: Interface Textured Wood Grains Level Set A00416 Antique Dark Oak luxury vinyl tile flooring; Roppe Pinnacle 194 Burnt Umber 4-inch-high cove base; Sherwin-Williams Shoji White SW 7042 semi-gloss paint for standard walls and door frames; and Benjamin Moore 1648 Slate Blue semi-gloss paint for accent walls. Work is divided into two phases, with Phase 1 requiring completion of all spaces except Room 205-P within four days, followed by Phase 2 completion of the remaining work within one day.

The contractor must attend a pre-construction meeting, field-verify all dimensions and existing conditions, and submit product data, color samples, and installation instructions for VA approval prior to work commencement. The contractor is responsible for site protection, substrate preparation, removal of existing materials, proper installation per manufacturer specifications, cleanup, and closeout documentation including warranty and maintenance information. All work must be performed by qualified personnel to commercial standards with finished surfaces free of defects. The contractor must comply with VA safety requirements, infection-control procedures, building access protocols, and Federal records management obligations. A VA Privacy Training certification is required annually for all contractor and subcontractor personnel. The anticipated contract award date is on or before February 12, 2027, and the requirement is designated as a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside with an estimated construction magnitude between $100,000 and $250,000.

View the file

Other files

File Type Posted
S10.xls XLS spreadsheet
36C24227Q0135.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work - VA OIG Space Flooring, Cove Base, and Painting

STATEMENT OF WORK

New York VA OIG Space - Flooring Replacement, Cove Base Replacement, and Wall Painting Project Number: 630SI3167B14

1. Background The Department of Veterans Affairs requires renovation of selected rooms within the New York VA OIG Space. The work includes removal and replacement of existing flooring, replacement of cove base, and repainting of walls in the scoped spaces. The work shall be performed in a professional manner, coordinated with VA staff, and completed with minimal disruption to building operations.

2. Objective The objective of this project is to refresh and improve the finish condition of the OIG office space by installing new flooring, new cove base, and new wall paint finishes in the approved work areas.

3. Scope Areas

· Included spaces: Offices 201-P, 203-P, 205-P, 206-P, 207-P, 208-P, 211-P; Reception 215-P; Foyer; Entire Hall area; 205A-P and Open Office Area - Shared 204-P.

· Excluded spaces: Electric Rooms 210-PA and 210-P; Janitor Rooms 226-P and 227-P; Secure Storage Rooms 202-P.

· No flooring, cove base, or painting work shall be performed in the excluded rooms unless separately directed in writing by the VA.

4. Estimated Quantities The following quantities are for estimating only. The contractor shall field verify all measurements and existing conditions prior to ordering materials or starting work.

No.
Space
Room No.
Flooring SF
Cove Base LF
Total Wall Area SF
Shoji White SF
Slate Blue Accent SF
1
Office
201-P
161.00
48.3
355
237
118
2
Office
203-P
160.74
48.5
357
241
116
3
Open Office Area - Shared
204-P
282.74
64.3
483
483
115
4
Office
205-P
158.68
47.7
406
291
0
5
Office
206-P
158.68
47.9
407
281
126
6
Office
207-P
232.13
58.0
488
358
130
7
Office
208-P
228.76
61.6
517
376
141
8
Storage
209-9
20
13
-
-
0
9
Office
211-P
162.47
55.3
466
332
134
10
Foyer
-
42
23
208
208
0
11
Hall Area
-
365
105
1120
1120
0
12
Secure Storage
205A-P
104.77
46
368
368
0
12
Reception
215-P
164.52
48.3
410
292
118

TOTAL

2,241.49
666.9
5,585
4,587
998

Contractor shall field verify all dimensions.

5. Contractor Responsibilities

5.1 Pre-Construction Coordination and Submittals

· Attend a pre-construction meeting with VA representatives before starting work.

· Field verify all room dimensions, wall areas, flooring quantities, cove base lengths, existing conditions, substrate conditions, and site access requirements.

· Submit product data, color samples, and manufacturer installation instructions for new flooring, cove base, adhesives, primers, and paints for VA approval prior to installation.

· Submit a work schedule and phasing plan identifying areas of work, sequence, duration, and any required off-hour work.

· Coordinate all work with the VA COR, Engineering Service, OIG space occupants, and any other affected stakeholders.

5.1.1 Phasing

· Phase 1 – Complete all work for all spaces except Room 205-P in 4 days.

· Phase 2 – Complete remaining work including Room 205-P, in 1 day.

5.2 Site Protection and Preparation

· Protect adjacent finishes, doors, frames, millwork, flooring, walls, and building systems from damage, dust, paint, and construction debris.

· Maintain safe access, egress, and housekeeping throughout the project.

5.3 Removal and Demolition

· Remove existing flooring in the included spaces only.

· Remove existing cove base in the included spaces only.

· Remove loose, damaged, or failing paint and prepare existing wall surfaces for repainting.

· Dispose of all demolished flooring, cove base, packaging, and construction debris in accordance with applicable requirements and VA direction.

5.4 Substrate and Wall Preparation

· Prepare floor substrate to receive new flooring in accordance with manufacturer requirements.

· Patch, level, skim, clean, and correct minor substrate deficiencies as required for proper flooring installation.

· Patch nail holes, dents, minor wall damage, and surface imperfections prior to painting.

· Clean surfaces so they are dry, sound, smooth, and free from dust, grease, residue, or other contaminants.

5.5 New Flooring Installation

· Furnish and install new Luxury Vinyl Tile (LVT): Interface Textured Wood Grains – Level Set – A00416 Antique Dark Oak, in accordance with approved VA submittals.

· Install flooring in accordance with the manufacturer's written instructions, approved layout, adhesive requirements, and applicable industry standards.

· Provide straight cuts, tight seams, proper transitions, and clean terminations at doors, walls, casework, and adjoining finishes.

· Protect newly installed flooring until final acceptance by the VA.

5.6 Cove Base Replacement

· Furnish and install new Roppe Pinnacle 194 Burnt Umber, 4-inch-high cove base in the included spaces.

· Install cove base tight to the wall and floor with secure adhesion, straight lines, clean corners, and no gaps or loose sections.

· Coordinate installation with VA-approved submittals.

5.7 Wall Painting – Standard Walls, Door Frames, and Jambs

· Paint all walls not designated as accent walls with Sherwin-Williams Shoji White SW 7042, Semi-Gloss finish.

· Paint all door frames and door jambs with Sherwin-Williams Shoji White SW 7042, Semi-Gloss finish.

· Apply primer where required and a minimum of two finish coats, or additional coats necessary to achieve a uniform finish.

· Contractor shall field verify all dimensions.

5.8 Wall Painting – Accent Walls

· Paint all walls identified as accent walls on the drawings with Benjamin Moore 1648 Slate Blue, Semi-Gloss finish. (See annotated areas on Attachment A1.

· Provide clean, straight cut lines between accent walls and adjacent Shoji White walls, ceilings, trim, door frames, and other adjacent finishes.

5.9 Cleanup, Inspection, and Closeout

· Remove all debris, excess materials, tape, protection, tools, and equipment from the work area.

· Clean new flooring, cove base, and painted surfaces prior to VA inspection.

· Correct deficiencies, touch up paint, repair damaged finishes, and replace defective work at no additional cost to the Government.

· Provide closeout documentation including approved product data, color information, manufacturer care/maintenance instructions, and warranty information.

6. Workmanship and Quality Requirements

· All work shall be performed by qualified personnel experienced in commercial flooring, cove base installation, and interior painting.

· Finished surfaces shall be clean, uniform, complete, and free of visible defects, bubbles, gaps, excessive adhesive, roller marks, paint runs, uneven coverage, and damage.

· The contractor shall repair any damage caused by its work to adjacent finishes, furniture, doors, frames, walls, floors, ceilings, and building systems.

· All materials shall be new, unused, commercial grade, and submitted to the VA for approval prior to installation.

7. Safety and Coordination

· The contractor shall comply with all applicable safety requirements, VA site rules, infection-control requirements where applicable, and building access procedures.

· The contractor shall maintain a clean and safe work area at all times and shall not block exits, corridors, life-safety equipment, or required access routes.

· Any work that may affect occupants, access, noise, odors, or normal operations shall be coordinated in advance with the VA.

8. Deliverables

· Work schedule and phasing plan.

· Product data and color/material submittals for flooring, cove base, adhesives, primers, and paints.

· Field-verified quantity confirmation prior to material ordering.

· Completed flooring replacement, cove base replacement, standard wall painting, and accent wall painting in the approved spaces.

· Closeout package with warranty and care/maintenance information.

9. Materials Preferred by the Government

a. Flooring replacement - LVT: Interface Textured Woodgrains – Level Set – A00416 Antique Dark Oak

b. Wall Painting – Standard Walls, Door Frames, and Jambs - Field wall paint color/ Door Frame/Jamb: SW 7042 Shoji White; Semi-gloss

c. Accent wall paint color: Benjamin Moore 1648 Slate Blue; Semi-gloss

d. Cove Base: Roppe Pinnacle 194 Burnt Umber, 4-inch-high

e. Existing Flooring

Remaining spaces have this type of carpet Two Office Spaces have this type of flooring including the foyer.

10. VA Office of Information and Technology (OIT) Compliance Security Requirement The Certification & Accreditation (C&A) requirements do not apply; a Security Accreditation Package is not required.

Privacy Training Requirement All contractors and subcontractor personnel assigned to this project must complete the VA Privacy Training for Personnel Without Access to VA Computer Systems or VA Sensitive Information. Certifications of completion must be submitted to the COR annually.

NARA

Records Management Language for Contracts When Federal agencies acquire goods or services, they need to determine what Federal records management requirements should be included in the contract. Federal contractors often create, send, or receive Federal records. Federal contracts should provide clear legal obligations describing how the contract employees must handle Federal records.

Agency records officers, procurement counsel, and acquisitions officers must discuss how to integrate records management obligations into their existing procurement processes. NARA has developed the following language to be included as an agency-specific term and condition in Federal contracts for a variety of services and products. The majority of contracts should include language on records management obligations, but each contract should be evaluated individually. For example, the data-rights paragraph (Paragraph 10 below) may not be appropriate for all contracts. Instead, agencies may be better served by one of the established data-rights clauses in the Federal Acquisition Regulations.

This language should not replace specific records management requirements included within Federal information system contracts.

RECORDS MANAGEMENT OBLIGATIONS

A. Applicability This clause applies to all Contractors whose employees create, work with, or otherwise handle Federal records, as defined in Section B, regardless of the medium in which the record exists.

B. Definitions “Federal record” as defined in 44 U.S.C. § 3301, includes all recorded information, regardless of form or characteristics, made or received by a Federal agency under Federal law or in connection with the transaction of public business and preserved or appropriate for preservation by that agency or its legitimate successor as evidence of the organization, functions, policies, decisions, procedures, operations, or other activities of the United States Government or because of the informational value of data in them.

The term Federal record:

1. includes [Agency] records.

1. does not include personal materials.

1. applies to records created, received, or maintained by Contractors pursuant to their [Agency] contract.

1. may include deliverables and documentation associated with deliverables.

C. Requirements

1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

1. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.

1. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

1. [Agency] and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of [Agency] or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to [Agency]. The agency must report promptly to NARA in accordance with 36 CFR 1230.

1. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to [Agency] control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).

1. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and [Agency] guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.

1. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with [Agency] policy.

1. The Contractor shall not create or maintain any records containing any non-public [Agency] information that are not specifically tied to or authorized by the contract.

1. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.

1. The [Agency] owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which [Agency] shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.

1. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take [Agency]-provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.

[Note: To the extent an agency requires contractors to complete records management training, the agency must provide the training to the contractor.] D. Flowdown of requirements to subcontractors

1. The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this [contract vehicle], and require written subcontractor acknowledgment of same.

1. Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contractor.

Records Management Language for Contracts | National Archives

Contractor shall field verify all dimensions.

image3.png image4.png image5.png image1.png image2.png

File details come from the government source that posted it. Updated .