This is a Sources Sought Notice for a construction project at the Margaret Cochran Corbin VA Campus in New York. The Department of Veterans Affairs is conducting market research to identify qualified construction contractors for Project No. 630SI3167B14, which involves flooring replacement, cove base replacement, and wall painting at 423 E 23rd St, New York, NY 10010. The estimated magnitude of construction ranges between $100,000 and $250,000, and no expansion of the existing building footprint is anticipated. This requirement will be procured under FAR Part 36 as a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside, with the applicable NAICS code 236220 (Commercial and Institutional Building Construction) and a small business size standard of $45 million.
All interested SDVOSB firms must be registered in SAM.gov and verified in the SBA Veteran Small Business Certification (VetCert) database at the time of response to be considered for award. The anticipated award date for the construction contract is on or before February 12, 2027. This announcement is not a request for proposal, and the government will not pay nor reimburse any costs associated with responding to this market research notice. Prospective contractors must comply with VAAR 852.219-10 and VAAR 852.219-11 regarding Service-Disabled Veteran-Owned Small Business set-aside requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW.docx | DOCX document | |
| 36C24227Q0135.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary
| Column2 | Column1 | |
| Project | VA OIG Space Flooring, Cove Base Replacement, and Wall Painting | |
| Location | Manhattan, New York VA | |
| Prepared Date | ||
| Basis | SOW quantities; contractor shall field verify all dimensions | |
| Cost Summary | Amount | Basis / Formula |
| General Conditions | $0.00 | Cost Detail by category |
| Demolition | $0.00 | Cost Detail by category |
| Flooring | $0.00 | Cost Detail by category |
| Cove Base | $0.00 | Cost Detail by category |
| Painting | $0.00 | Cost Detail by category |
| Closeout | $0.00 | Cost Detail by category |
| Direct Construction Cost | $0.00 | Sum of all direct work |
| Bonds / Insurance (2.0%) | $0.00 | Direct Cost x 2.0% |
| Contractor Overhead & Profit (10.0%) | $0.00 | (Direct + Bonds/Insurance) x 10.0% |
| Escalation / Procurement Risk (3.0%) | $0.00 | (Direct + Bonds + O&P) x 3.0% |
| Contingency / Rounding to Approved Total | Balancing amount to establish final total | |
| GRAND TOTAL | $0.00 | Target total requested by VA |
| Key Quantities | Qty | Unit |
| Flooring Replacement | 2,241.49 | SF |
| Cove Base Replacement | 666.90 | LF |
| Total Wall Paint Area | 5,585.00 | SF |
| Shoji White SW 7042 | 4,587.00 | SF |
| Benjamin Moore Slate Blue 1648 | 998.00 | SF |
Cost Detail
| WBS | Category | Requirement / Work Task | Detailed Basis | Qty | Unit | Material/Equipment Unit Cost | Labor Hours | Labor Rate | Material/Equipment Cost | Labor Cost | Subtotal |
| 01.01 | General Conditions | Mobilization, field verification, preconstruction | Site verification, logistics, safety plan, submittals | 1.00 | LS | $0.00 | |||||
| 01.02 | General Conditions | Project management & superintendent | Scheduling, coordination, QA/QC oversight | 1.00 | LS | $0.00 | |||||
| 01.03 | General Conditions | Site protection, containment, daily cleanup | Dust protection, occupant protection, safe access/egress | 1.00 | LS | $0.00 | |||||
| 02.01 | Demolition | Remove existing flooring | Remove existing flooring in included OIG spaces - 2,241.49 SF | 2,241.49 | SF | $0.00 | |||||
| 02.02 | Demolition | Remove existing cove base | Remove existing 4-inch cove base - 666.9 LF | 666.90 | LF | $0.00 | |||||
| 02.03 | Demolition | Surface prep, debris handling and disposal | Hauling, disposal, substrate cleanup, minor scrape/grind | 1.00 | LS | $0.00 | |||||
| 03.01 | Flooring | Furnish LVT flooring | Interface Textured Wood Grains - Level Set A00416 Antique Dark Oak | 2,241.49 | SF | $0.00 | |||||
| 03.02 | Flooring | Install LVT flooring | Adhesive, layout, cutting, installation, transitions and terminations | 2,241.49 | SF | $0.00 | |||||
| 04.01 | Cove Base | Furnish 4-inch cove base | Roppe Pinnacle 194 Burnt Umber - 666.9 LF | 666.90 | LF | $0.00 | |||||
| 04.02 | Cove Base | Install 4-inch cove base | Adhesive, corners, clean lines, secure installation | 666.90 | LF | $0.00 | |||||
| 05.01 | Painting | Paint standard Shoji White walls | Sherwin-Williams Shoji White SW 7042 semi-gloss - 4,587 SF | 4,587.00 | SF | $0.00 | |||||
| 05.02 | Painting | Paint Slate Blue accent walls | Benjamin Moore 1648 Slate Blue semi-gloss - 998 SF | 998.00 | SF | $0.00 | |||||
| 05.03 | Painting | Wall prep, primer, patching and touch-up | Wall patching, primer where required, minor surface repairs - 5,585 SF | 5,585.00 | SF | $0.00 | |||||
| 06.01 | Closeout | Final cleaning, punch list, warranty, O&M | Final cleanup, deficiency correction, care/maintenance and warranty package | 1.00 | LS | $0.00 | |||||
| DIRECT CONSTRUCTION COST | $0.00 | $0.00 | $0.00 |
Labor Rates
| Trade / Role | Estimated Market Labor Rate | Unit | Used In Estimate | Notes |
| Project Manager | $/HR | General conditions | Manhattan commercial construction coordination | |
| Superintendent / Foreman | $/HR | Mobilization / field oversight | Field supervision, site access, safety | |
| Flooring Installer | $/HR | LVT installation | Commercial LVT installation labor | |
| Commercial Painter | $/HR | Wall painting and prep | Painting, patching, primer and finish coats | |
| Construction Laborer | $/HR | Demolition / disposal | Flooring/cove base removal, debris handling | |
| Closeout / Punchlist Labor | $/HR | Final cleanup and deficiencies | Finish correction and turnover support |
Equipment Basis
| Material / Allowance | Basis | Qty | Unit | Unit Cost | Extended Cost |
| LVT flooring | Interface Textured Wood Grains - Level Set A00416 Antique Dark Oak | 2,241.49 | SF | $0.00 | |
| LVT install materials/allowance | Adhesives, minor transitions and consumables | 2,241.49 | SF | $0.00 | |
| Roppe cove base | Roppe Pinnacle 194 Burnt Umber, 4-inch high | 666.90 | LF | $0.00 | |
| Cove base adhesive/consumables | Included as unit allowance | 666.90 | LF | $0.00 | |
| Shoji White paint material | Sherwin-Williams Shoji White SW 7042 semi-gloss | 4,587.00 | SF | $0.00 | |
| Slate Blue paint material | Benjamin Moore 1648 Slate Blue semi-gloss | 998.00 | SF | $0.00 | |
| Primer/patching material | Primer, spackle, sandpaper, sundries | 5,585.00 | SF | $0.00 |
File details come from the government source that posted it. Updated .