This is an Amendment to a Previous Combined Solicitation for repair and replacement of a steam line and condensate system at a VA medical facility. The solicitation number is 36C24226R0083, issued by the Department of Veterans Affairs Network Contracting Office 2 at James J. Peters VA Medical Center in Bronx, New York. The proposal response deadline is May 5, 2026 at 11:00 AM Eastern Time. The contracting officer is Nicholas Muro (Nicholas.Muro@va.gov). The place of performance is the VHA New Jersey Healthcare System Lyons Campus at 151 Knollcroft Road, Lyons, NJ 07939. The set-aside is for Service-Disabled Veteran-Owned Small Business (SDVOSBC), with Product Service Code Y1DA and NAICS Code 236220.
The amendment provides answers to recently submitted Requests for Information clarifying key project specifications. The scope includes demolishing and removing the existing steam condensate tank, pumps, and controls, then furnishing and installing a new condensate tank with pumps, pump controls, control panel, 4-inch steam pressure reducing valve (PRV), 4-inch steam strainer, and 4-inch Schedule 80 black steel piping. Critical clarifications include: the high-pressure steam supply is 4-inch diameter with a regulator reducing from 100 psi to 25 psi medium pressure; the existing condensate tank is 37" x 37" x 22.5"H with two 1.5 hp discharge pumps; material removal is the contractor's responsibility with no on-site disposal; material storage and fabrication may occur in the courtyard (Circle 2, Building 53); all new gaskets and bolts must follow manufacturer specifications (no 307A bolts); the maximum shutdown window for the main steam line is 12 hours with Executive Leadership Team approval; and all steam line work must be insulated with jackets on valves, strainer, and regulator. The project completion date may be extended to accommodate equipment procurement lead times of up to 60 days for the PRV and condensate tank.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 3.pdf | ||
| AMENDMENT 2.pdf | ||
| Site Visit Sign In Sheet.pdf | ||
| AMENDMENT 1.pdf | ||
| S02 Limitation on Subcontracting.pdf | ||
| SOW repair Steam Line and Condensate system Building 53.pdf | ||
| WD NJ20260042.pdf | ||
| 36C24226R0083.pdf | ||
| S02 Buy American Certificate.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment to a Previous Combined Solicitation
SUBJEC 561A4-26-509 I Repair Steam line and Condensate System building 53 T*
GENERAL INFORMATION
CONTRACTING OFFICE'S ZIP CODE*
SOLICITATION NUMBER*
RESPONSE DATE/TIME/ZONE
ARCHIVE
RECOVERY ACT FUNDS
SET-ASIDE
PRODUCT SERVICE CODE*
NAICS CODE*
CONTRACTING OFFICE ADDRESS
POINT OF CONTACT*
10468-3904
36C24226R0083
05-05-2026 11 :00 AM EASTERN TIME, NEW
YORK, USA
60 DAYS AFTER THE RESPONSE DATE
SDVOSBC
Y1DA
236220
Department of Veterans Affairs
Network Contracting Office 2
James J. Peters VA Medical Center
130 West Kingsbridge Road
Bronx NY 10468-3904
Nicholas Muro
Nicholas.Muro@va.gov
PLACE OF PERFORMANCE
ADDRESS
*= Required Field
VHA New Jersey Healthcare System
Lyons Campus
Amendment to a Previous Combined
Solicitation Page 1 of 8
POSTAL CODE
COUNTRY
151 Knollcroft Rd
Lyons NJ
07939
USA
ADDITIONAL INFORMATION
AGENCY'S URL
URL DESCRIPTION
AGENCY CONTACT'S EMAIL ADDRESS
EMAIL DESCRIPTION
www.VA.gov
Department of Veteran Affairs
DESCRIPTION
Please see the following page for further information.
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
0004 04-30-2026 561A4-26-509
36C242
Department of Veterans Affairs Network Contracting Office 2 James J. Peters VA Medical Center 130 West Kingsbridge Road Bronx NY 10468-3904
36C242
Department of Veterans Affairs James J. Peters VA Medical Center Network Contracting Office 2 130 West Kingsbridge Road Bronx NY 10468-3904
To all Offerors/Bidders 36C24226R0083
04-30-2026 X
X X
X 1
Amendment to Request for Proposal (36C24226R0083) Repair Steam Line and Condensate System building
This amendment is to provide answers to any recently submitted RFIs
PROPOSALS REMAIN DUE ON 05/05/2026 @ 11:00 AM
All other terms and conditions of the original submission remain unchanged.
Dayna Dickson-Miller Contracting Officer
Questions and Answers
Steam Line Repair Project (561A4-26-509)
Why specific tasks list 8" PRV 8" strainer, and 8" pipe but the material lists all specify 4" strainer 4" pipe, and 4" PRV etc. We need clarification.
- High pressure steam supply is 4” diameter. The strainer and regulator are also 4”. The steam regulator has an incoming pressure of 100# and reduces to our medium pressure set at 25# . No information tag for the amount of gallons. I have the dimensions of the condensate tank currently installed. 37” x 37” x 22.5H” with 2 front mounted discharge pumps 1.5 hp ,3500 rpm, 230/460 .
Project schedule will be affected by the lead time of equipment and material, will the project completion date get extended?
Yes, the project completion date can be extended to reflect the lead time of the equipment.
Will all of the demo material be disposed of by contractor or dropped at government location? If dropped at government location would that location be on campus?
All material removal is the contractor’s responsibility. No on-site disposal.
Will the government be providing a submittal register that we are to follow? Please provide an example of one?
No submittal will be needed, just the list of materials submitted by the GC
Can material be stored out in the courtyard? Can fabrication happen in courtyard.
Yes, the material can be stored in a safe place on campus and fabrication can occur int the courtyard (circle 2, building 53).
Can a dumpster be placed in courtyard or where will a laydown area for this project be?
The laydown area of this project can be in the courtyard (circle 2, building 53).
Will there be specifications for new gaskets, bolts and nuts used in the new installation?
Must not use 307A Bolts. We follow manufacturers specs for nuts and bolts
The SOW states Specific tasks: include demolishing and removing the existing steam condensate tank, pumps, and controls; furnishing and installing a new steam condensate tank and pumps, pump controls and control panel, 8-inch steam PRV, 8-inch steam strainer, and 8-inch Schedule 40 black steel piping; providing and installing all required valves.
The material list then states:
- 2 - OS&Y Valves - 4" 8 bolt 300#
- 4" strainer 8 bolt 300#
- 4" Steam PRV rated to reduce steam pressure from 1 00psi to medium pressure 25 psi
- Sensing line to be installed new for the replacement regulator
- Approximately 24' of 4" sch 80 pipe
- All new gaskets and bolts used for all flanges
- All pipe and fittings/nipples must be sch 80
Is there 8” valves and schedule 40pipe to be changed somewhere on this project?
Please confirm the size of the valves and schedule of pipe to be used.
- High pressure steam supply is 4” diameter. The strainer and regulator are also 4”.
The steam regulator has an incoming pressure of 100# and reduces to our medium pressure set at 25# . No information tag for the amount of gallons. I have the dimensions of the condensate tank currently installed. 37” x 37” x 22.5H” with 2 front mounted discharge pumps 1.5 hp ,3500 rpm, 230/460 .
- We are requesting clarification regarding a discrepancy identified in the project documents.
In the Specific Tasks section, the scope references installation of:
8" steam PRV
8" steam strainer
8" schedule 40 black steel piping
However, in the Material Lists, the components are identified as:
4" strainer
4" piping
4" PRV
Due to this inconsistency, we are unable to determine the correct sizing requirements for pricing and procurement.
Please confirm the correct sizes for the steam PRV, strainer, and associated piping to be included in the contractor’s scope.
- High pressure steam supply is 4” diameter. The strainer and regulator are also 4”. The steam regulator has an incoming pressure of 100# and reduces to our medium pressure set at 25# . No information tag for the amount of gallons. I have the dimensions of the condensate tank currently installed. 37” x 37” x 22.5H” with 2 front mounted discharge pumps 1.5 hp ,3500 rpm, 230/460 .
- We just wanted to verify if the lines for the condensate tank is 4in with 4in strainer and the amount of gallons in the condensate tank.
o High pressure steam supply is 4” diameter. The strainer and regulator are also 4”. The steam regulator has an incoming pressure of 100# and reduces to our medium pressure set at 25# . No information tag for the amount of gallons. I have the dimensions of the condensate tank currently installed. 37” x 37” x 22.5H” with 2 front mounted discharge pumps 1.5 hp ,3500 rpm, 230/460 .
- I reviewed the recent amendment for this solicitation and noticed it lists the proposal due date as April 20, 2026. However, SAM.gov currently reflects a due date of May 5, 2026. Could you please clarify which date is correct when you have a moment?
o The Correct Bid Due date is May 5th 2026 @ 11AM EST.
- Shut down hours to replace both os&y valves? Should this be priced out on premium time? Realistically how long can that main be down?
o This is the main steam for the building. A shutdown affects the heat and hot water. The Maximum would be 12 hours with approval from Executive Leadership Team.
- Please confirm that the only work required on the high-pressure steam main is replacement of piping between the OS&Y valves, including the OS&Y valves.
Clarification is requested due to conflicting information observed during the walkthrough and material list provided.
o Replacement of piping between the OS&Y valves, including the OS&Y valves on the High to med pressure reducing line. This is to include all pipe strainers, high to med pressure reducing regulator(100# - 25#), flanges, gaskets, all hardware.
- During walkthrough we did not see a pressure gauge on the medium pressure side of the PRV. Should it be included?
o Yes, please include
- SOW says roughly 10’ of venting should be replaced. Is this including overflow piping as well or is the following acceptable: Remove and replace all piping below union to include replacement of union.
o Remove and replace all piping below union to include replacement of union.
- The SOW requires completion within 30 days of NTP. Please confirm whether this duration will be adjusted to account for procurement lead times of major equipment (PRV, condensate tank), which may be up to 60 days, or if these items are expected to be procured and on-site prior to NTP.
Yes, this duration will be adjusted to account for procurement lead times of major equipment (PRV, condensate tank)
- Please provide insulation specifications including thickness, material type, and jacketing requirements (ASJ, aluminum, etc.). Also confirm whether valves, flanges, and specialties are to be insulated and jacketed.
o Yes. All the steam line work should be insulated and Jackets on valves, strainer, regulator etc.